- Update today marker to 2026-04-02 in both gantt charts
- Update gantt chart update log to Day 53 with Session 3 context
- Update risk register: M3-M9 completion percentages from Forgejo API
- Update footer: 40 open bugs, 119 open PRs, Session 3 active
- Update Current Status Summary: Day 53, 119 PRs, 114 issues, 40 bugs
- Update warning box: Session 3 launch with 16 workers / ~71 agents
- Update Parallel Workstreams: Testing track reflects current state
- Append What Has Been Completed: Day 50 reviewer blitz + Session 3 launch
- Update What Remains To Be Done: M8/M9 detail, 119 PRs, 40 bugs
- Update Schedule Risk Summary: Day 53 critical path blockers
- Append Day 53 Schedule Adherence entry with all required tables
Day 26 (2026-03-06) comprehensive PM update:
- Schedule adherence entry with milestone forecasts and developer status
- Updated Current Status Summary: 272 issues closed (77%), 1570/1922 SP (82%)
- PR #617 (UKO Layer 1) and #611 (domain analyzers) merged late Day 26
- Open PR count: 19 -> 15 (merge rate exceeding new PR rate for first time)
- Spec gap analysis: no major coverage gaps found across all 44K-line spec
- All 15 open PRs have PM status comments with action items and deadlines
- Updated milestone roadmap, track forecasts, developer forecasts, risk summary
- Workstream and completion sections updated with Day 26 merges
ISSUES CLOSED: none (PM/docs update only)