@@ -3269,7 +3269,7 @@ Note: Each cell is **completed/total story points** for that milestone/owner per
|
||||
| M6+ | 0/64 | - | 8/50 | 0/29 | 0/5 | 8/8 | - | 16/156 |
|
||||
| **Total** | **511/681** | **214/230** | **139/218** | **69/153** | **171/185** | **8/19** | **163/163** | **1275/1649** |
|
||||
|
||||
### 2026-03-04 (Day 24 since kickoff on 2026-02-09)
|
||||
### 2026-03-04 (Day 24)
|
||||
|
||||
- Timeline reference: Day 7/M1 = 2026-02-15, Day 14/M2 = 2026-02-22, Day 18/M3 = 2026-02-26, Day 22/M4 = 2026-03-02, Day 26/M5 = 2026-03-06, Day 30/M6 = 2026-03-10
|
||||
- Summary: **Project ~3d behind schedule (narrowing).** M3 decision PRs (#433, #464) both merged to master (Days 23-24). 7 bookkeeping issues updated to State/Completed (code already on master: #190, #194, #201, #208, #498, #499, #501). 3 bugs triaged (#522, #523, #524 — reported by Brent), created 2 test-first issues (#536, #537). 44 non-merge commits since Day 22. M5 (ACMS) remains critical path with 2 days to target. Hamza's M3 blockers now resolved — he can focus entirely on M5 ACMS work.
|
||||
|
||||