Docs: Fixed another formatting issue with the documentation

This commit is contained in:
2026-03-03 22:29:07 -05:00
parent 5935940276
commit 296431cfd6
+1
View File
@@ -3275,6 +3275,7 @@ Note: Each cell is **completed/total story points** for that milestone/owner per
- Summary: **Project ~3d behind schedule (narrowing).** M3 decision PRs (#433, #464) both merged to master (Days 23-24). 7 bookkeeping issues updated to State/Completed (code already on master: #190, #194, #201, #208, #498, #499, #501). 3 bugs triaged (#522, #523, #524 — reported by Brent), created 2 test-first issues (#536, #537). 44 non-merge commits since Day 22. M5 (ACMS) remains critical path with 2 days to target. Hamza's M3 blockers now resolved — he can focus entirely on M5 ACMS work.
**Day 24 highlights**:
- Decision recording PR #433 and plan explain PR #464 **both merged** (Hamza's M3 blockers resolved).
- 7 issues with code on master updated to State/Completed (#190, #194, #201, #208, #498, #499, #501). Forgejo dependency constraints prevent formal API closure but issues are clearly marked done.
- Additional features merged since Day 22: ACP facade wiring, skeleton compressor, backend implementations, devcontainer resource handler, context tiers, execution environment routing, multi-project subplan, large-project decomposition, safety profile enforcement, observability metrics, context CLI wiring.