@@ -10,14 +10,14 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
|
||||
@startgantt
|
||||
|
||||
title CleverAgents Core — Epic-Level Project Schedule
|
||||
footer Generated 2026-02-23 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1350 SP
|
||||
footer Generated 2026-02-26 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1350 SP
|
||||
|
||||
Project starts 2026-02-03
|
||||
saturday are closed
|
||||
sunday are closed
|
||||
printscale weekly zoom 2
|
||||
|
||||
today is 2026-02-24
|
||||
today is 2026-02-26
|
||||
today is colored in #FF6666
|
||||
|
||||
<style>
|
||||
@@ -155,8 +155,8 @@ ganttDiagram {
|
||||
|
||||
[Concurrency + Cleanup (#365)] as [CONCUR] on {Luis} requires 2 days
|
||||
[CONCUR] starts 2026-02-23
|
||||
[CONCUR] is 0% completed
|
||||
[CONCUR] is colored in #E8E8E8/Silver
|
||||
[CONCUR] is 100% completed
|
||||
[CONCUR] is colored in PaleGreen/SeaGreen
|
||||
|
||||
' ================================================================
|
||||
' PROJECTS & RESOURCES — WORKSTREAM B (Legendary #373 - DONE) — v3.1.0
|
||||
@@ -189,17 +189,17 @@ ganttDiagram {
|
||||
|
||||
[Actor + Skill Schema C0 (#354)] as [C0] on {Jeff} {Aditya} {Luis} {Brent} requires 7 days
|
||||
[C0] starts 2026-02-11
|
||||
[C0] is 93% completed
|
||||
[C0] is colored in LightSkyBlue/SteelBlue
|
||||
[C0] is 100% completed
|
||||
[C0] is colored in PaleGreen/SeaGreen
|
||||
|
||||
[Actor Runtime + Tool Exec (#355)] as [M1] on {Jeff} {Hamza} {Luis} {Brent} requires 3 days
|
||||
[M1] starts at [PROJ]'s end
|
||||
[M1] is 34% completed
|
||||
[M1] is 60% completed
|
||||
[M1] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Actor Graphs + Tool Sources (#356)] as [M2] on {Aditya} {Jeff} {Luis} {Brent} {Hamza} requires 5 days
|
||||
[M2] starts at [M1]'s end
|
||||
[M2] is 5% completed
|
||||
[M2] is 15% completed
|
||||
[M2] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.2.0 MILESTONE ─────────────────────────────────────────
|
||||
@@ -219,7 +219,7 @@ ganttDiagram {
|
||||
|
||||
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
|
||||
[M3] starts at [M2]'s end
|
||||
[M3] is 10% completed
|
||||
[M3] is 50% completed
|
||||
[M3] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
|
||||
@@ -240,12 +240,12 @@ ganttDiagram {
|
||||
|
||||
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
|
||||
[M4] starts at [M3]'s end
|
||||
[M4] is 27% completed
|
||||
[M4] is 40% completed
|
||||
[M4] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Security + Safety Hardening (#362)] as [SEC] on {Luis} requires 3 days
|
||||
[SEC] starts 2026-03-02
|
||||
[SEC] is 20% completed
|
||||
[SEC] is 60% completed
|
||||
[SEC] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Provider Fixes + Runtime (#363)] as [PROV] on {Luis} requires 2 days
|
||||
@@ -285,7 +285,7 @@ ganttDiagram {
|
||||
|
||||
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
|
||||
[LARGE] starts 2026-03-17
|
||||
[LARGE] is 52% completed
|
||||
[LARGE] is 55% completed
|
||||
[LARGE] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
|
||||
@@ -390,8 +390,8 @@ legend right
|
||||
**Risk Register**
|
||||
|= Epic |= Completion |= Risk |= Blocker |
|
||||
| PRE_TEST (#24) | 0% | Medium | Test framework gap |
|
||||
| M1 (#355) | 34% | Medium | Hamza/Luis blocked |
|
||||
| SEC (#362) | 20% | High | Security-critical |
|
||||
| M1 (#355) | 60% | Medium | MCP adapter + agent skills loader |
|
||||
| SEC (#362) | 60% | Medium | Remaining security hardening |
|
||||
| PROV (#363) | 0% | Low | Provider fixes deferred |
|
||||
| A9 (#352) | 0% | Low | Config deferred to v3.4 |
|
||||
----
|
||||
@@ -401,7 +401,7 @@ legend right
|
||||
| <back:LightSkyBlue> </back> | In Progress |
|
||||
| <back:#E8E8E8> </back> | Not Started |
|
||||
| <back:Gold> <> </back> | Milestone Target |
|
||||
| <back:#FF6666> | </back> | Today (2026-02-24) |
|
||||
| <back:#FF6666> | </back> | Today (2026-02-26) |
|
||||
----
|
||||
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
|
||||
~1350 total story points | ~2700 estimated hours
|
||||
@@ -428,7 +428,7 @@ saturday are closed
|
||||
sunday are closed
|
||||
printscale weekly zoom 2
|
||||
|
||||
today is 2026-02-24
|
||||
today is 2026-02-26
|
||||
today is colored in #FF6666
|
||||
|
||||
<style>
|
||||
@@ -1933,7 +1933,7 @@ legend right
|
||||
| <back:LightSkyBlue> </back> | Issue: In Progress |
|
||||
| <back:#E8E8E8> </back> | Issue: Not Started |
|
||||
| <back:Gold> <> </back> | Milestone Target |
|
||||
| <back:#FF6666> | </back> | Today (2026-02-24) |
|
||||
| <back:#FF6666> | </back> | Today (2026-02-26) |
|
||||
----
|
||||
213 Issues | 29 Epics | 9 Legendaries | 7 Milestones
|
||||
~1350 total story points | ~2700 estimated hours
|
||||
@@ -1948,13 +1948,15 @@ This section provides a high-level overview of the CleverAgents implementation r
|
||||
|
||||
### Current Status Summary
|
||||
|
||||
As of Day 16 (2026-02-24), the project has **~144 closed issues out of ~259 assigned issues** across all milestones (72% overall completion rate). The foundational layers — domain models, persistence, YAML schemas, CLI commands, quality automation, and CI/CD — are substantially built out. Today's progress includes the **actor compiler** (Jeff, #158 merged — YAML to LangGraph StateGraph compilation), **agent skills discovery** (Jeff, #161 merged), **actor CLI alignment** (Jeff, #288 merged), **CLI plan/action extensions** (Jeff, #325 merged), and a **database parallelism fix** (Brent, #418 merged).
|
||||
As of Day 18 (2026-02-26), the project has **~168 closed issues out of ~225 assigned issues** across all milestones (~75% overall completion rate). A major productivity surge over Days 16-18 closed **65 issues in 3 days**, substantially advancing M1, M2, M3, and M4. The foundational layers — domain models, persistence, YAML schemas, CLI commands, quality automation, CI/CD, validation pipeline, and security hardening — are now mature.
|
||||
|
||||
The primary blocker for M1 completion remains the **sandbox merge/apply pipeline** (#155, Luis — active branch) and the **E2E source-code smoke test suite** (#156, Brent). The M2 blockers are the **MCP adapter** (#159, Aditya — in review) and remaining **actor YAML extensions** (#157, Aditya — active branch). The actor compiler (#158) — previously the M2 critical-path blocker — was merged today.
|
||||
**Days 17-18 highlights**: Apply pipeline + validation-gated apply + diff review merged (Luis, PR #417 — #155, #175, #176, #178, #303, #186). Changeset persistence (Jeff, #163). Plan resume + concurrency locks (Jeff, #327, #328). Provider cost controls (Jeff, #324). Decision persistence (Hamza, PR #131 — #171). Async resource cleanup (Hamza, #321). Actor YAML hierarchy (Aditya, PR #432 — #157). Security hardening — template rendering + exception handling (Hamza, #319, #320). Brent QA batches: M1/M2 E2E suites (#156, #169, #326, #402, #403) and M3/M4 E2E suites (#179, #180, #404, #405, #187). CI concurrency groups (#452).
|
||||
|
||||
!!! warning "Schedule Risk: 7-9 Days Behind"
|
||||
**M1 is essentially complete** — only #323 (remove FakeListLLM defaults) remains open. The M2 blockers are the **MCP adapter** (#159, Aditya), **agent skills loader** (#160, Aditya), and **skill persistence/CLI** (#166, #167, #168). The M3 target date is today; 3 issues remain (#172 decision recording, #173 invariant enforcement, #174 plan explain CLI).
|
||||
|
||||
The project is running **7-9 days behind** the original aggressive schedule. M1 (target Feb 15) is overdue by 9 days; M2 (target Feb 22) is overdue by 2 days. A major workload rebalancing from Luis (33 remaining issues, lowest velocity) to Jeff (highest velocity, capacity available) is being executed to close the gap. Any `MoSCoW/Could Have` items in M1-M2 should be deferred to avoid further slippage.
|
||||
!!! warning "Schedule Risk: 5-7 Days Behind (Narrowing)"
|
||||
|
||||
The project is running **5-7 days behind** the original aggressive schedule, improved from 7-9 days at Day 16. The 65-issue closure burst over Days 16-18 substantially narrowed the gap. M1 (target Feb 15) is overdue by 11 days but essentially complete. M2 (target Feb 22) has 6 remaining issues. M3 (target Feb 26) has 3 remaining issues. The workload rebalancing executed on Day 16 is paying off — Jeff's throughput has been exceptional, and the validation/security batch from Luis/Hamza landed cleanly.
|
||||
|
||||
### Parallel Workstreams
|
||||
|
||||
@@ -1962,14 +1964,14 @@ Development is organized into six concurrent workstreams plus continuous quality
|
||||
|
||||
| Track | Focus Area | Status |
|
||||
| :---- | :--------- | :----- |
|
||||
| **A** — Plan Lifecycle | Action/plan domain models, persistence, CLI alignment, execute/apply wiring | Core models and persistence done; CLI extensions merged today (#325). Execute/apply pipeline in progress. Config service (#352) deferred to M5. |
|
||||
| **B** — Projects & Resources | Resource registry, project model, resource types, sandbox strategies, CLI | **Substantially complete.** Registry, models, CLI, handler runtime (git-checkout + fs-directory), DAG metadata all done. Auto-discovery remaining. |
|
||||
| **C** — Actors, Tools, Skills | Actor YAML schema/loader/compiler, tool registry/runtime, skill framework, MCP adapter, validation runner | **Actor compiler DONE** (#158 merged today). Agent skills discovery DONE (#161 merged today). Actor CLI aligned (#288 merged today). MCP adapter in review (Aditya PR #382). Agent skills loader in review (Aditya PR #416). Validation runner remaining. |
|
||||
| **D** — Decisions & Apply | Decision tree model, change tracking, diff review, apply pipeline, correction engine | Decision domain model and context snapshots done. **Decision persistence in review** (Hamza PR #131). Correction engine models done. Apply pipeline partially done; sandbox merge (#155) active. |
|
||||
| **E** — Subplans | Subplan domain model, orchestration, parallel execution, three-way merge | Domain model done; orchestrator and merge logic remaining |
|
||||
| **A** — Plan Lifecycle | Action/plan domain models, persistence, CLI alignment, execute/apply wiring | **Substantially complete.** Apply pipeline with validation gating merged (#155). Changeset persistence merged (#163). Concurrency locks + plan resume merged (#327, #328). Config service (#352) deferred to M5. |
|
||||
| **B** — Projects & Resources | Resource registry, project model, resource types, sandbox strategies, CLI | **Complete.** Registry, models, CLI, handler runtime (git-checkout + fs-directory), DAG metadata all done. |
|
||||
| **C** — Actors, Tools, Skills | Actor YAML schema/loader/compiler, tool registry/runtime, skill framework, MCP adapter, validation runner | Actor compiler, agent skills discovery, actor CLI, skill registry flattening, validation pipeline all DONE. Actor YAML hierarchy merged (#157). **MCP adapter** (#159, Aditya) and **agent skills loader** (#160, Aditya) remain. Skill persistence (#166) and skill CLI (#167, #168) remain. |
|
||||
| **D** — Decisions & Apply | Decision tree model, change tracking, diff review, apply pipeline, correction engine | **Major progress.** Decision persistence merged (#171). Validation-gated apply merged (#176). DoD gating merged (#178). Diff review artifacts merged (#303). Error recovery patterns merged (#186). Remaining: decision recording (#172), invariant enforcement (#173), plan explain CLI (#174). |
|
||||
| **E** — Subplans | Subplan domain model, orchestration, parallel execution, three-way merge | Domain model done; orchestrator and merge logic remaining. E2E M4 correction + subplan suites merged (#405). |
|
||||
| **F** — ACMS & Context | UKO ontology, CRP protocol, context strategies, assembly pipeline, hot/warm/cold tiers | Not yet started; scheduled for M5-M6 milestones |
|
||||
| **Q** — Quality & CI | Pre-commit hooks, Forgejo CI/CD, coverage enforcement (97%), security scanning | Complete. Database parallelism fix merged today (#418). |
|
||||
| **T** — Testing | Behave unit tests, Robot integration tests, ASV benchmarks, end-to-end smoke suites | Ongoing; CLI extension tests in review (Brent PR #420). E2E milestone suites (#402-#407) pending. Rui returns Feb 27. |
|
||||
| **Q** — Quality & CI | Pre-commit hooks, Forgejo CI/CD, coverage enforcement (97%), security scanning | Complete. CI concurrency groups and job timeouts added (#452). Security hardening: template rendering (#319) and exception handling (#320) merged. Async resource cleanup merged (#321). |
|
||||
| **T** — Testing | Behave unit tests, Robot integration tests, ASV benchmarks, end-to-end smoke suites | **Strong progress.** M1 E2E suite (#156), M2 E2E suite (#169, #403), M3 E2E suite (#179, #180, #404), M4 E2E suite (#405) all merged via Brent QA batches. M5 (#406) and M6 (#407) E2E suites remain. Rui returns Feb 27. |
|
||||
|
||||
### What Has Been Completed
|
||||
|
||||
@@ -1990,129 +1992,128 @@ The following major areas are fully or substantially implemented:
|
||||
- **Security hardening**: All `eval()`/`exec()` calls replaced with named operation registries, config security scanner detecting 15 disallowed patterns, AST-based code validation, Jinja2 sandboxed environments, secrets masking and validation.
|
||||
- **Agent skills discovery**: Filesystem scanning for Agent Skills Standard folders (SKILL.md with YAML front-matter), registering discovered skills as tools in ToolRegistry with configurable conflict handling (skip/error/replace), refresh hooks, and CLI integration (#161 merged 2026-02-24).
|
||||
- **CLI extensions**: Plan use command extended with --automation-profile, --invariant (repeatable), --strategy-actor/--execution-actor/--estimation-actor/--invariant-actor flags. Plan status/list and action show commands extended with profile, invariant, and actor override rendering across all output formats (#325 merged 2026-02-24).
|
||||
- **Quality automation**: Pre-commit hooks (12 hooks across 5 categories), Forgejo CI/CD pipeline with 10 nox-routed jobs, nightly quality monitoring, ADR compliance checking, 97% test coverage enforcement, comprehensive security scanning (Bandit + Semgrep + Vulture), and per-scenario temp database isolation for parallel Behave execution (#418 merged 2026-02-24).
|
||||
- **Apply pipeline with validation gating**: Sandbox merge/apply pipeline with conflict resolution (#155 merged 2026-02-25). Validation-gated apply (#176 merged 2026-02-25) with required/informational mode enforcement. Diff review artifacts (#303 merged 2026-02-25). DoD gating enforcement (#178 merged 2026-02-25). Error recovery patterns with CLI hints (#186 merged 2026-02-25).
|
||||
- **Decision persistence**: Decision persistence layer with database tables, repositories, and CRUD operations (#171 merged 2026-02-26, Hamza). Decision domain model, context snapshots, and influence DAG now fully persisted.
|
||||
- **Changeset persistence**: ChangeSet and diff artifact persistence with database migration and repository (#163 merged 2026-02-26, Jeff).
|
||||
- **Concurrency and resilience**: Plan and project concurrency locks with advisory locking (#327 merged 2026-02-25). Plan resume with state recovery and re-execution (#328 merged 2026-02-25). Provider cost controls and fallback routing (#324 merged 2026-02-25).
|
||||
- **Security hardening (Days 17-18)**: Template rendering hardened (#319 merged 2026-02-25). Explicit exception handling enforced (#320 merged 2026-02-25). Async resource cleanup and leak prevention (#321 merged 2026-02-26).
|
||||
- **Actor YAML hierarchy**: Extended hierarchical actor YAML schema with namespace inheritance, multi-level includes, and loader improvements (#157 merged 2026-02-26, Aditya).
|
||||
- **E2E milestone suites**: M1 source-code plan lifecycle suite (#156), M2 actor + tool source suite (#169), M1/M2 success criteria verification (#402, #403), M3 decision + validation suites (#179, #180, #404), M4 correction + subplan suite (#405) — all merged via Brent QA batches (2026-02-25 and 2026-02-26).
|
||||
- **Quality automation**: Pre-commit hooks (12 hooks across 5 categories), Forgejo CI/CD pipeline with 10 nox-routed jobs, nightly quality monitoring, ADR compliance checking, 97% test coverage enforcement, comprehensive security scanning (Bandit + Semgrep + Vulture), per-scenario temp database isolation for parallel Behave execution (#418 merged 2026-02-24), and CI concurrency groups with job timeouts (#452 merged 2026-02-26).
|
||||
|
||||
### What Remains To Be Done
|
||||
|
||||
The majority of the specification's domain models, services, CLI commands, and infrastructure modules are now implemented. The following areas still require completion or have only partial implementations:
|
||||
|
||||
- **MCP runtime adapter**: Live connection to MCP servers for external tool discovery and invocation at runtime. Aditya has active work on `develop-aditya-2` branch with PR #382 in review. Schema and domain models exist; the runtime bridge is pending. **This is the remaining M2 critical-path blocker** (actor compiler was merged 2026-02-24).
|
||||
- **Decision persistence**: Hamza has active work on `feature/m4-decision-persistence`. The domain model and context snapshots are now merged; the database persistence layer (tables, repositories, CRUD) is next.
|
||||
- **Decision recording service**: Wire decision recording into the strategize/execute phases so decisions are automatically captured during plan execution.
|
||||
- **Validation runner pipeline**: A dedicated module for executing required and informational validations attached to resources, with pass/fail gating on the apply phase.
|
||||
- **MCP runtime adapter**: Live connection to MCP servers for external tool discovery and invocation at runtime. Aditya's previous PR #382 merged the foundation; the agent skills loader (#160) and MCP adapter runtime (#159) remain. **This is the remaining M2 critical-path blocker.**
|
||||
- **Decision recording service**: Wire decision recording into the strategize/execute phases so decisions are automatically captured during plan execution (#172, Hamza).
|
||||
- **Invariant enforcement**: Runtime enforcement of invariant constraints with scoped precedence and reconciliation (#173, Jeff).
|
||||
- **Plan explain CLI**: Plan tree and explain commands for decision tree visualization (#174, Hamza).
|
||||
- **Skill persistence and CLI**: Persist flattened tool sets (#166, Jeff), skill CLI commands (#167, Aditya), MCP refresh hooks (#168, Aditya).
|
||||
- **Estimation actor logic**: The `estimation_actor` field is plumbed through Plan, Action, CLI, and service layers, but no actual estimator implementation exists to compute cost/risk estimates before execution.
|
||||
- **ACMS v1 full pipeline**: Context policy with phase-scoped views and the context service exist. Still pending: Universal Knowledge Ontology (UKO) with RDF-based resource representation, Context Request Protocol (CRP), pluggable context strategies, the full ten-component Context Assembly Pipeline, and hot/warm/cold tiered storage with per-actor scoped views.
|
||||
- **Large-project context management**: Indexing 10,000+ file codebases with bounded memory context assembly, skeleton compression for parent-to-child context propagation, and performance validation at scale.
|
||||
- **Sandbox merge/apply with validation gating**: The apply service exists but needs validation gating hooks and conflict resolution for the sandbox merge pipeline.
|
||||
- **E2E smoke test suites**: Per-milestone E2E verification suites (#402-#407) need to be written to validate milestone success criteria.
|
||||
- **E2E smoke test suites**: M5 (#406) and M6 (#407) E2E verification suites remain. M1-M4 suites are complete.
|
||||
- **FakeListLLM default removal**: Provider defaults cleanup (#323, Jeff).
|
||||
|
||||
The following areas are substantially implemented and are no longer blocking:
|
||||
|
||||
- Resource abstraction (types, registry, handlers with git-checkout and fs-directory, DAG metadata, CLI)
|
||||
- Sandbox strategies (git_worktree, copy-on-write, no-sandbox, factory, merge)
|
||||
- Tool system (runner, registry, built-in file/git/changeset tools, schema validation, lifecycle, router)
|
||||
- Security hardening (config scanner, sandboxed Jinja2 templates, input validation, credential redaction, secrets masking)
|
||||
- Apply pipeline (plan_apply_service with diff review, merge, changeset capture)
|
||||
- Decision domain model (12 decision types, context snapshots, influence DAG, frozen model helpers)
|
||||
- Security hardening (config scanner, sandboxed Jinja2 templates, input validation, credential redaction, secrets masking, template rendering hardening, exception handling enforcement, async resource cleanup)
|
||||
- Apply pipeline (plan_apply_service with validation gating, diff review, merge, changeset capture, DoD enforcement, error recovery patterns)
|
||||
- Decision system (12 decision types, context snapshots, influence DAG, frozen model helpers, database persistence)
|
||||
- Correction engine (revert/append modes, BFS impact analysis, dry-run reporting)
|
||||
- Invariant reconciliation (domain model with scopes, merge with precedence, enforcement service)
|
||||
- Subplan orchestration (domain models for config, status, merge strategies, failure handling)
|
||||
- Phase reversion (constrained apply -> back to strategize state machine)
|
||||
- Checkpointing (CheckpointScope, profile flags, cleanup pruning, integrated throughout)
|
||||
- Automation profiles (8 built-in profiles, guard logic, 4-level precedence service, CLI commands)
|
||||
- Agent Skills loader (registry, protocol, built-in skills, SKILL.md schema support)
|
||||
- Agent Skills discovery (registry, protocol, built-in skills, SKILL.md schema support)
|
||||
- Changeset persistence (database tables, repository, diff artifact storage)
|
||||
- Concurrency controls (plan/project advisory locks, plan resume with state recovery)
|
||||
- Provider controls (cost controls, fallback routing, rate limiting)
|
||||
- LSP integration (stub modules with registry, models, tool adapter — runtime deferred to server mode)
|
||||
- Server connectivity stubs (ACP HTTP transport stub, ACP facade, local-mode routing)
|
||||
|
||||
### Milestone Roadmap
|
||||
|
||||
#### Milestone 1: Minimal Local Source-Code Workflow (Target: Feb 15, ETA: ~Feb 27)
|
||||
#### Milestone 1: Minimal Local Source-Code Workflow (Target: Feb 15, ETA: Done)
|
||||
|
||||
**Goal**: A minimally usable local-mode flow where a user can register an action from YAML, link a git repository resource to a project, and run a plan end-to-end (`plan use` -> `plan execute` -> `plan diff` -> `plan apply`) with a sandboxed workspace and tool-based change capture.
|
||||
|
||||
**Current status**: ~96% of M1 tasks complete (6 open out of ~153 total M1 issues). Resource handler runtime (git-checkout, fs-directory) done. Actor runtime and tool-calling partially operational. Database parallelism fix merged today.
|
||||
**Current status**: **~99% complete** (1 open out of ~154 total M1 issues). Apply pipeline merged (#155). E2E M1 suite merged (#156, #402). Provider cost controls merged (#324).
|
||||
|
||||
**Key remaining work**:
|
||||
|
||||
- Sandbox merge/apply pipeline with conflict resolution and validation gating hooks (#155, Luis — active branch)
|
||||
- E2E source-code plan lifecycle smoke test suite (#156, Brent)
|
||||
- M1 success criteria verification (#402, Brent)
|
||||
- FakeListLLM default removal and provider cost controls (#323, #324 — reassigned to Jeff)
|
||||
- FakeListLLM default removal (#323, Jeff)
|
||||
|
||||
#### Milestone 2: Actor Compiler + Full LLM Integration (Target: Feb 22, ETA: ~Mar 1)
|
||||
|
||||
**Goal**: Actor YAML files compile into live LangGraph graphs. Custom actors (strategy, execution, estimation) are fully operational. The tool router normalizes calls across providers, the validation runner enforces resource-attached validations, and the MCP adapter connects to external tool servers.
|
||||
|
||||
**Current status**: ~63% of M2 tasks complete (17 closed out of ~48 total M2 issues). Actor compiler (#158) merged today. MCP adapter (#159) in review (PR #382). Agent skills loader (#160) in review (PR #416). Actor YAML hierarchy (#157) active.
|
||||
**Current status**: **~95% complete** (5 open out of ~97 total M2 issues). Actor compiler (#158), actor YAML hierarchy (#157), changeset persistence (#163), concurrency locks (#327), plan resume (#328), validation pipeline (#175, #176), M2 E2E suite (#169, #403), CI concurrency (#451) all merged. MCP adapter and agent skills loader remain as critical-path items.
|
||||
|
||||
**Key remaining work**:
|
||||
|
||||
- MCP adapter runtime (#159, Aditya — PR #382 in review)
|
||||
- Agent skills loader (#160, Aditya — PR #416 in review)
|
||||
- Actor YAML hierarchy extensions (#157, Aditya — active branch)
|
||||
- Changeset persistence and diff review (#163, #303 — Jeff after reassignment, #303 deferred to M3)
|
||||
- Validation runner with required/informational mode enforcement (#175, #176 — Jeff after reassignment)
|
||||
- M2 E2E actor integration suite (#403, Brent)
|
||||
- MCP adapter runtime (#159, Aditya)
|
||||
- Agent skills loader (#160, Aditya)
|
||||
- Skill persistence — persist flattened tool sets (#166, Jeff)
|
||||
- Skill CLI — tools and refresh commands (#167, Aditya)
|
||||
- MCP refresh hooks (#168, Aditya)
|
||||
|
||||
#### Milestone 3: Decisions + Validations + Invariants (Target: Feb 26, ETA: ~Mar 5)
|
||||
#### Milestone 3: Decisions + Validations + Invariants (Target: Feb 26, ETA: ~Mar 2)
|
||||
|
||||
**Goal**: Decisions are recorded during Strategize and Execute phases and persisted to the database. Users can view the decision tree (`plan tree`), inspect individual decisions (`plan explain`), manage invariants (`invariant add/list/remove`), and correct decisions (`plan correct --mode revert|append`) with selective subtree recomputation.
|
||||
|
||||
**Current status**: ~33% of M3 tasks complete (5 closed out of ~15 total M3 issues). Decision domain model and context snapshots merged. Decision persistence (#171) in review (PR #131, Hamza).
|
||||
**Current status**: **~75% complete** (3 open out of ~12 total M3 issues). Decision persistence merged (#171). Validation pipeline and gating merged (#175, #176). DoD gating merged (#178). Diff review artifacts merged (#303). M3 E2E suites merged (#179, #180, #404).
|
||||
|
||||
**Key remaining work**:
|
||||
|
||||
- Decision persistence service wiring (#171, Hamza — PR #131 in review)
|
||||
- Decision recording during strategize/execute phases (#172, Hamza)
|
||||
- Invariant enforcement and reconciliation (#173, Jeff)
|
||||
- Plan tree and explain CLI commands (#174, Hamza)
|
||||
- Diff review artifacts (#303, Luis — active branch, deferred from M2 to M3)
|
||||
- Invariant enforcement and reconciliation (#319-#322, Hamza after reassignment)
|
||||
- Validation runner and gating (#175, #176, Jeff after reassignment)
|
||||
|
||||
#### Milestone 4: Corrections + Subplans + Checkpoints (Target: Mar 2, ETA: ~Mar 8)
|
||||
#### Milestone 4: Corrections + Subplans + Checkpoints (Target: Mar 2, ETA: ~Mar 6)
|
||||
|
||||
**Goal**: Plans can spawn child plans (subplans) during execution. Subplans execute in parallel with configurable concurrency limits. Results are merged back using three-way merge strategies. Correction engine supports revert and append modes. Checkpointing enables rollback to previous plan states.
|
||||
|
||||
**Current status**: ~59% of M4 tasks complete (13 closed out of ~22 total M4 issues). Phase reversion landed. Subplan domain model done.
|
||||
**Current status**: **~86% complete** (3 open out of ~22 total M4 issues). DoD gating (#178), error recovery (#186), security hardening (#319, #320, #321), M4 E2E suites (#405, #187) all merged and closed.
|
||||
|
||||
**Key remaining work**:
|
||||
|
||||
- Correction engine — revert mode (#178, Jeff after reassignment)
|
||||
- Correction engine — append mode (#186, Jeff after reassignment)
|
||||
- Subplan orchestrator and scheduler (#201, Jeff after reassignment)
|
||||
- Parallel execution with max_parallel and fail-fast (#259, Jeff after reassignment)
|
||||
- Three-way merge of subplan changesets (#312, Jeff after reassignment)
|
||||
- Checkpoint persistence and rollback (#313, Jeff after reassignment)
|
||||
- CLI extension tests (PR #420, Brent — in review)
|
||||
- M4 E2E correction + subplan suite (#405, Brent)
|
||||
- Subplan orchestrator and scheduler (#183, Jeff)
|
||||
- Correction service runtime wiring (#184, Luis)
|
||||
- Invariant template hardening (#322, Hamza)
|
||||
|
||||
#### Milestone 5: ACMS v1 + Context Scaling (Target: Mar 6, ETA: ~Mar 11)
|
||||
#### Milestone 5: ACMS v1 + Context Scaling (Target: Mar 6, ETA: ~Mar 10)
|
||||
|
||||
**Goal**: The Advanced Context Management System v1 is operational. Projects with 10,000+ files can be indexed and queried. The context assembly pipeline produces scoped, budget-constrained context views for actors. Hot/warm/cold storage tiers manage context lifecycle.
|
||||
|
||||
**Current status**: ~21% of M5 tasks complete (4 closed out of ~19 total M5 issues). UKO/RDF groundwork started (Hamza). Config service foundations exist.
|
||||
**Current status**: ~7% of M5 tasks complete (14 open out of ~15 total M5 issues). UKO/RDF groundwork started (Hamza). Config service foundations exist.
|
||||
|
||||
**Key remaining work**:
|
||||
|
||||
- UKO ontology with RDF-based resource representation (#338, #342, #343, Jeff after reassignment)
|
||||
- CRP protocol for actor context requests (#199, Jeff after reassignment)
|
||||
- Context strategies — keyword, semantic, graph, temporal (#208, #209, Jeff after reassignment)
|
||||
- UKO ontology with RDF-based resource representation (#338, #342, #343, Jeff)
|
||||
- CRP protocol for actor context requests (#199, Jeff)
|
||||
- Context strategies — keyword, semantic, graph, temporal (#208, #209, Jeff)
|
||||
- Ten-component context assembly pipeline (Hamza)
|
||||
- Hot/warm/cold tiered storage with skeleton compression (Hamza)
|
||||
- M5 E2E ACMS integration suite (#406, Brent)
|
||||
|
||||
#### Milestone 6: Autonomy Hardening + Server Stubs (Target: Mar 10, ETA: ~Mar 13)
|
||||
#### Milestone 6: Autonomy Hardening + Server Stubs (Target: Mar 10, ETA: ~Mar 12)
|
||||
|
||||
**Goal**: The system can autonomously execute a large-scale task (e.g., porting a substantial codebase) using hierarchical plan decomposition with 4+ levels of subplans, decision correction with selective subtree recomputation, parallel execution scaling to 10+ concurrent subplans, and validation-gated apply. Client-side server stubs are in place for future connectivity.
|
||||
|
||||
**Current status**: ~26% of M6 tasks complete (5 closed out of ~19 total M6 issues). Foundation work from M3-M5 will accelerate M6.
|
||||
**Current status**: ~7% of M6 tasks complete (14 open out of ~15 total M6 issues). Foundation work from M3-M5 will accelerate M6.
|
||||
|
||||
**Key remaining work**:
|
||||
|
||||
- Hierarchical decomposition — recursive subplan planning (#335, #336, Jeff after reassignment)
|
||||
- Autonomous estimation — cost/risk/time (#337, Jeff after reassignment)
|
||||
- Performance tuning for large-project context assembly (#340, Jeff after reassignment)
|
||||
- Server connectivity client stubs (#323, #324, Jeff after reassignment)
|
||||
- Hierarchical decomposition — recursive subplan planning (#335, #336, Jeff)
|
||||
- Autonomous estimation — cost/risk/time (#337, Jeff)
|
||||
- Performance tuning for large-project context assembly (#340, Jeff)
|
||||
- Server connectivity client stubs (Jeff)
|
||||
- End-to-end porting run with validation gates (all)
|
||||
- M6 E2E autonomy integration suite (#407, Brent)
|
||||
|
||||
@@ -2140,9 +2141,9 @@ Final refinements to achieve the complete specification:
|
||||
|
||||
### Schedule Risk Summary
|
||||
|
||||
The project is currently running approximately **7-9 days behind** the original aggressive schedule. The primary causes are: (1) the scope of v2-to-v3 architectural transition was larger than anticipated, requiring significant model realignment and test rewriting; (2) CI/CD pipeline stabilization consumed more effort than planned due to container resource constraints and cross-environment compatibility issues; and (3) the execute/apply pipeline — the critical vertical slice — was deferred in favor of breadth-first foundation work.
|
||||
The project is currently running approximately **5-7 days behind** the original aggressive schedule, narrowed from 7-9 days at Day 16. The primary causes of the original delay were: (1) the scope of v2-to-v3 architectural transition was larger than anticipated; (2) CI/CD pipeline stabilization consumed more effort than planned; and (3) the execute/apply pipeline was deferred in favor of breadth-first foundation work.
|
||||
|
||||
The gap is expected to **narrow** in later milestones because: (a) foundational infrastructure (persistence, CLI patterns, quality gates, domain models) is now solid and reusable; (b) aggressive workload redistribution on Day 16 moved 25 issues from slower developers (Luis, Hamza) to Jeff (highest velocity), reducing bottleneck risk; and (c) each subsequent milestone builds on proven patterns rather than establishing new ones. Actor compiler merging today unblocks actor-dependent work across M2-M4.
|
||||
The gap has been **actively narrowing** since Day 16: (a) the workload redistribution moved 25 issues to Jeff and paid off with a 65-issue closure burst over Days 16-18; (b) the validation pipeline, apply pipeline, security hardening, and decision persistence all landed in a concentrated 2-day window; (c) M1 is essentially complete and M2/M3 are close behind with only 6 and 3 issues remaining respectively; (d) Brent's QA batch merges (M1-M4 E2E suites) eliminated the testing backlog through M4.
|
||||
|
||||
!!! note "Server Mode"
|
||||
|
||||
@@ -2979,3 +2980,94 @@ Note: Each cell is **completed/total story points** for that milestone/owner per
|
||||
| M6 | 13/92 | - | 0/39 | - | 24/30 | - | - | 37/161 |
|
||||
| M6+ | 0/64 | - | 0/24 | 0/29 | 0/5 | - | 8/8 | 8/130 |
|
||||
| **Total** | **403/681** | **177/222** | **66/163** | **29/145** | **125/176** | **0/0** | **108/108** | **908/1495** |
|
||||
|
||||
### 2026-02-26 (Day 18)
|
||||
|
||||
**Summary**
|
||||
|
||||
Status: Behind ~5-7d
|
||||
Deadline risk: HIGH (narrowing)
|
||||
Overall completion: 74.5% (~168/225 milestone issues closed, excluding Epics/Legendaries)
|
||||
|
||||
**Notes**
|
||||
|
||||
- **65 issues closed in 3 days** (Days 16-18) — the largest productivity burst of the project
|
||||
- M1 essentially complete: only #323 (FakeListLLM defaults) remains open
|
||||
- Apply pipeline + validation gating + diff review + DoD gating landed in a single batch (Luis PR #417)
|
||||
- Decision persistence merged (Hamza PR #131)
|
||||
- Actor YAML hierarchy merged (Aditya PR #432)
|
||||
- Security hardening batch: template rendering (#319), exception handling (#320), async cleanup (#321) — all merged
|
||||
- Brent QA batches merged: M1-M4 E2E suites (#156, #169, #179, #180, #326, #402-#405, #187)
|
||||
- Concurrency controls: locks (#327), plan resume (#328), provider cost controls (#324) merged
|
||||
- Changeset persistence (#163) and CI concurrency groups (#452) merged
|
||||
- Rui returns from leave tomorrow (Feb 27)
|
||||
- M3 target date is today; 3 issues remain (#172, #173, #174)
|
||||
|
||||
|
||||
#### Milestone forecast
|
||||
|
||||
| Milestone | Target -> ETA | Delta | Risk |
|
||||
|-----------|---------------|-------|------|
|
||||
| M1 (v3.0.0) | (2026-02-15) -> ETA Done | +11d actual | LOW — 1 issue remaining (#323) |
|
||||
| M2 (v3.1.0) | (2026-02-22) -> ETA 2026-03-01 | +7d | MED-HIGH — 5 open issues; MCP adapter + agent skills loader are blockers |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-03-02 | +4d | MEDIUM — 3 open issues; decision recording + invariant enforcement + plan explain |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-03-06 | +4d | MEDIUM — 3 open issues; subplan orchestrator + correction wiring |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-03-10 | +4d | MEDIUM — 14 open issues; ACMS pipeline + context scaling |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-03-12 | +2d | MEDIUM — 14 open issues; autonomy hardening + server stubs |
|
||||
|
||||
#### Track forecast
|
||||
|
||||
| Track | Status | ETA | Risk | Blocking |
|
||||
|-------|--------|-----|------|----------|
|
||||
| Track A (Plan lifecycle) | **essentially complete** | Done (config service deferred to M5) | LOW | none |
|
||||
| Track B (Resources + sandbox) | **complete** | Done | LOW | none |
|
||||
| Track C (Actors/tools/skills/MCP) | behind ~4-5d | ETA 2026-03-01 | MED-HIGH | MCP adapter (#159) + agent skills loader (#160) + skill persistence (#166) + skill CLI (#167, #168) |
|
||||
| Track D (Decisions/validations) | behind ~4d | ETA 2026-03-02 | MEDIUM | decision recording (#172) + invariant enforcement (#173) + plan explain (#174) |
|
||||
| Track E (Corrections/subplans) | behind ~4d | ETA 2026-03-06 | MEDIUM | subplan orchestrator (#183) + correction wiring (#184) |
|
||||
| Track F (ACMS/context) | not started | ETA 2026-03-10 | MEDIUM | dependent on M3 completion |
|
||||
| Track Q (Quality automation) | **complete** | Done | LOW | maintenance only |
|
||||
| Track T (Testing) | strong progress | ETA ongoing | LOW-MED | M1-M4 E2E suites done; M5/M6 remain; Rui returns Feb 27 |
|
||||
|
||||
#### Developer forecast
|
||||
|
||||
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|
||||
|------|-------------------|--------------|------|-------|
|
||||
| Jeff | +2d ahead (exceptional throughput; absorbing 25+ reassigned issues successfully) | available | MEDIUM | Invariant enforcement (#173), skill persistence (#166), FakeListLLM fix (#323), M5/M6 backlog |
|
||||
| Luis | -3d behind (8/19 closed = 42%; but validation/apply batch was substantial contribution) | available | MEDIUM | Correction wiring (#184), remaining M5/M6 items |
|
||||
| Hamza | on track (decision persistence landed; security batch landed) | available | MEDIUM | Decision recording (#172), plan explain CLI (#174), M5 ACMS items |
|
||||
| Aditya | -1d behind (MCP adapter and agent skills loader are M2 critical path) | available | MED-HIGH | MCP adapter (#159), agent skills loader (#160), skill CLI (#167, #168) |
|
||||
| Brent | +1d ahead (M1-M4 E2E suites all merged in 2 QA batches) | available | LOW | M5 E2E suite (#406), M6 E2E suite (#407), coverage maintenance |
|
||||
| Rui | N/A (returns Feb 27) | returning tomorrow | MEDIUM | Behave/Robot test suites after return |
|
||||
| Mike/Brian | N/A | standby | LOW | ASV runner fix merged (#388) |
|
||||
|
||||
#### Task inventory
|
||||
|
||||
Milestone per developer as of the current date.
|
||||
Note: Each cell is **completed/total issues** for that milestone/owner per Forgejo tracker. Epics and Legendaries excluded.
|
||||
|
||||
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | 26/27 | 12/12 | 2/2 | 4/4 | 10/10 | 0/0 | 97/97 | 151/152 |
|
||||
| M2 | 22/22 | 8/12 | 4/4 | 1/1 | 5/5 | 0/0 | 52/52 | 92/96 |
|
||||
| M3 | 5/6 | 0/0 | 2/2 | 1/3 | 3/3 | 0/0 | 0/0 | 11/14 |
|
||||
| M4 | 7/8 | 0/0 | 3/4 | 1/2 | 7/7 | 0/0 | 1/1 | 19/22 |
|
||||
| M5 | 1/8 | 0/1 | 0/1 | 0/5 | 1/3 | 0/0 | 2/2 | 4/20 |
|
||||
| M6 | 2/10 | 0/0 | 0/4 | 0/0 | 3/5 | 0/0 | 0/0 | 5/19 |
|
||||
| M6+ | 0/8 | 0/0 | 0/3 | 0/4 | 0/1 | 0/0 | 1/1 | 1/17 |
|
||||
| **Total** | **63/89** | **20/25** | **11/20** | **7/19** | **29/33** | **0/0** | **153/153** | **283/339** |
|
||||
|
||||
#### Story point allocation
|
||||
|
||||
Story points per developer per milestone.
|
||||
Note: Each cell is **completed/total story points** for that milestone/owner per Forgejo tracker. Issues without a `Points/X` label or milestone are excluded. Epics and Legendaries (organizational items) are excluded.
|
||||
|
||||
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | 180/188 | 128/128 | 16/16 | 19/19 | 71/71 | - | 95/95 | 509/517 |
|
||||
| M2 | 147/176 | 49/86 | 29/29 | 5/5 | 21/21 | - | - | 251/317 |
|
||||
| M3 | 45/58 | - | 21/21 | 13/23 | 11/11 | - | - | 90/113 |
|
||||
| M4 | 42/47 | - | 29/34 | 8/32 | 24/24 | - | 1/1 | 104/138 |
|
||||
| M5 | 5/61 | 0/8 | - | 0/37 | 8/14 | - | 4/4 | 17/124 |
|
||||
| M6 | 13/92 | - | 0/39 | - | 24/30 | - | - | 37/161 |
|
||||
| M6+ | 0/64 | - | 0/24 | 0/29 | 0/5 | - | 8/8 | 8/130 |
|
||||
| **Total** | **432/686** | **177/222** | **95/163** | **45/145** | **159/176** | **0/0** | **108/108** | **1016/1500** |
|
||||
|
||||