freemo
66c99db163
docs(timeline): update schedule adherence Day 95 (2026-04-05)
2026-04-05 02:40:40 +00:00
freemo
03334aaa3d
docs(timeline): update schedule adherence Day 54 (2026-04-03)
2026-04-04 19:17:58 +00:00
freemo
744abb9d62
docs(timeline): update schedule adherence Day 54 (2026-04-03)
2026-04-03 17:23:55 +00:00
freemo
72a9a17a67
docs(timeline): update schedule adherence Day 54 (2026-04-03)
...
Day 54 morning update. No merges overnight. Agents created 100+ new issues.
Key changes:
- Appended Day 54 schedule adherence entry
- Updated today marker to 2026-04-03 in both gantt charts
- Open bugs: 35 → 50 (+15 new bugs from agents overnight)
- Open PRs: 79 → 84 (+5 new fix/CI branches)
- Open issues: 400 → 500 (+100 new from agents overnight)
- M3 (v3.2.0): 82% → 75% (212/281, milestone grew 256→281)
- M4 (v3.3.0): 79% → 78% (99/127, milestone grew 126→127)
- M5 (v3.4.0): 88% → 87% (126/145, milestone grew 143→145)
- M6 (v3.5.0): 77% → 71% (172/241, milestone grew 221→241)
- M7 (v3.6.0): 73% → 68% (120/177, milestone grew 164→177)
- M8 (v3.7.0): 36% → 29% (54/185, milestone grew 152→185)
- M9 (v3.8.0): 40% → 26% (64/242, milestone grew 160→242)
2026-04-03 00:33:20 +00:00
freemo
ee1710dc3e
docs(timeline): update schedule adherence Day 53 (2026-04-02) night refresh
...
Night refresh after UAT/bug-hunt/CI agents created 50+ new issues.
Key changes:
- Open bugs: 6 → 35 (UAT/bug-hunt agents created 29 new bugs #1749-#1791)
- Open PRs: 74 → 79 (+5 new CI/security PRs)
- Open issues: 339 → 400 (+61 new from UAT/bug-hunt/CI agents)
- M3 (v3.2.0): 85% → 82% (211/256, milestone grew from 236→256)
- M4 (v3.3.0): 80% → 79% (99/126, milestone grew from 124→126)
- M5 (v3.4.0): 89% → 88% (126/143, milestone grew from 142→143)
- M6 (v3.5.0): 79% → 77% (171/221, milestone grew from 214→221)
- M7 (v3.6.0): 75% → 73% (120/164, milestone grew from 150→164)
- M8 (v3.7.0): 38% → 36% (55/152, milestone grew from 107→152)
- M9 (v3.8.0): 35% → 40% (64/160, milestone grew from 49→160)
- Critical: coverage at 37% (#1782 ), AmbiguousStep crash (#1791 )
2026-04-02 23:57:25 +00:00
freemo
f063bed3e6
docs(timeline): update schedule adherence Day 53 (2026-04-02)
...
End-of-day refresh after CLI fix wave merged 18 PRs.
Key changes:
- Open bugs: 143 → 6 (massive CLI fix wave resolved 137 bugs)
- Open PRs: 68 → 74 (6 net new after CLI fix wave)
- Open issues: 342 → 339
- M6 (v3.5.0): 77% → 79% (168/214 closed)
- M8 (v3.7.0): 44% → 38% (41/107 closed, milestone grew from 81→107)
- M9 (v3.8.0): 40% → 35% (17/49 closed, milestone grew from 42→49)
- Added end-of-day CLI fix wave bullet to What Has Been Completed
- Updated all sections with end-of-day data
2026-04-02 23:16:27 +00:00
freemo
d318d92d1f
docs(timeline): update schedule adherence Day 53 (2026-04-02)
...
Late-day refresh: Open PRs 50→68 (+18 new fix PRs for UAT findings),
open issues 362→342 (-20 closed), open bugs 155→143 (-12 fixed).
Milestones: M3 85% (197/231), M4 80% (99/124), M5 89% (126/142),
M6 77% (165/214), M7 75% (112/149), M8 44% (36/81), M9 40% (17/42).
Recent merges: #1498 (tool add YAML), #1481 (session checksum),
#1479 (TUI CSS), #1338 (persona export/import).
2026-04-02 20:54:36 +00:00
freemo
c81afea06b
docs(timeline): update schedule adherence Day 53 (2026-04-02)
...
End-of-day refresh: UAT supervisor fleet (cycles 11-131) discovered 100+
spec compliance bugs, surging open bug count from 50 to 155. M8 (v3.7.0)
net regression from 60% to 55% (36/65) due to 29 new UAT issues. Updated
milestone completion rates, gantt chart legend, risk register, current
status summary, and schedule adherence entry with end-of-day data.
Key changes:
- Open bugs: 50 → 155 (+105 UAT discoveries)
- Open PRs: 47 → 50 (+3 new UAT/bug PRs)
- Open issues: 289 → 362 (+73 new UAT/refactor/bug issues)
- M3 83% (190/227), M4 77% (89/115), M5 88% (126/143)
- M6 78% (165/211), M7 75% (114/152), M8 55% (36/65), M9 42% (17/40)
2026-04-02 19:50:26 +00:00
arch-guard
136c27a337
docs(timeline): update schedule adherence Day 53 (2026-04-02)
...
Mid-day refresh: 47 open PRs (+2), 289 open issues (+15 new UAT/refactor
issues in v3.7.0 backlog). v3.5.0 advanced to 78% (164/209, +2 closed).
v3.7.0 at 60% (36/60, +1 new issue). 50 open bugs stable.
Updated sections: Gantt chart update log, footer, risk register legend,
Current Status Summary, What Remains To Be Done, Day 53 schedule adherence
entry (task inventory with per-developer breakdown).
2026-04-02 19:04:05 +00:00
freemo
ed449f1b2b
docs(timeline): update schedule adherence Day 53 (2026-04-02)
...
- Update gantt charts: M3 85%, M4 78%, M5 89%, M6 78%, M7 76%, M8 61%, M9 42%
- Update footer: 50 open bugs, 45 open PRs (down from 65/86)
- Update GANTT UPDATE LOG: v3.7.0 push, 55+ PRs merged
- Update Current Status Summary: 45 open PRs, 274 open issues, 50 bugs
- Append v3.7.0 second merge wave bullet (10 additional PRs)
- Update What Remains: M8 61%, M9 42%, 45 open PRs, 50 bugs
- Update Milestone Roadmap: M3/M4/M5/M6/M8 status sections
- Update Schedule Risk Summary: 45 PRs, 50 bugs, M8 61%
- Update Day 53 schedule adherence entry: two merge waves, updated forecasts
2026-04-02 18:19:47 +00:00
freemo
3fe1974249
docs(timeline): update schedule adherence Day 53 (2026-04-02)
...
- Updated Day 53 entry with end-of-day data (32 PRs merged today)
- Open PRs: 119 → 86 (down 33)
- Open bugs: 40 → 65 (up 25, UAT testing discovered new issues)
- Milestone progress: M3 74%→79%, M4 74%→75%, M5 78%→87%, M6 69%→74%, M7 61%→71%, M8 50%→54%
- Updated gantt chart completion percentages and risk register
- Updated Current Status Summary with end-of-day figures
- Added Day 53 merge wave bullet to What Has Been Completed
- Updated What Remains To Be Done with current open counts
- Updated Schedule Risk Summary with UAT findings
2026-04-02 17:41:12 +00:00
freemo
82b9d927ab
docs(timeline): update schedule adherence Day 53 (2026-04-02)
...
- Update today marker to 2026-04-02 in both gantt charts
- Update gantt chart update log to Day 53 with Session 3 context
- Update risk register: M3-M9 completion percentages from Forgejo API
- Update footer: 40 open bugs, 119 open PRs, Session 3 active
- Update Current Status Summary: Day 53, 119 PRs, 114 issues, 40 bugs
- Update warning box: Session 3 launch with 16 workers / ~71 agents
- Update Parallel Workstreams: Testing track reflects current state
- Append What Has Been Completed: Day 50 reviewer blitz + Session 3 launch
- Update What Remains To Be Done: M8/M9 detail, 119 PRs, 40 bugs
- Update Schedule Risk Summary: Day 53 critical path blockers
- Append Day 53 Schedule Adherence entry with all required tables
2026-04-02 16:55:09 +00:00
freemo
8f104fab88
Docs: daily update to timeline
2026-03-30 22:12:17 -04:00
freemo
a3c3a5c530
Docs: daily update to timeline
2026-03-22 23:45:54 -04:00
freemo
5f5ef891a2
Docs: daily update to timeline
2026-03-22 17:29:19 -04:00
freemo
2413b97c52
Docs: Daily update to timeline
2026-03-19 10:58:11 -04:00
freemo
758dafd8fa
Docs: daily update to timeline
2026-03-17 14:45:41 -04:00
freemo
05503712ae
Docs: Daily update to timeline
2026-03-16 17:40:17 -04:00
freemo
af6340e732
Docs: Daily update to timeline
2026-03-14 18:26:20 -04:00
freemo
09f1d621bf
Docs: Daily update to timeline
2026-03-14 18:26:12 -04:00
freemo
9c8dc9edd2
Docs: Daily update to timeline
2026-03-12 17:31:04 -04:00
freemo
3959565723
Docs: Daily update to timeline
2026-03-11 16:47:22 -04:00
freemo
b16bd27667
Docs: daily update to timeline
2026-03-11 15:32:16 -04:00
freemo
d5b122d4a3
Docs: Updated to A2A and integrating rest standard
2026-03-11 13:19:55 -04:00
freemo
674c5b8a6b
Docs: Daily update to timeline
2026-03-11 10:05:25 -04:00
freemo
83f2f3a0a1
Docs: Daily update to timeline
2026-03-09 17:01:41 -04:00
freemo
e8d777825b
Docs: daily update to timeline
2026-03-09 15:29:48 -04:00
freemo
e5c0b10985
Docs: Fided some discrepencies in timeline
2026-03-09 10:43:38 -04:00
freemo
a4ac36cd50
Docs: Daily update to timeline
2026-03-07 18:37:05 -05:00
freemo
fde8618665
docs(timeline): Day 26 PM sweep — schedule adherence, PR status, spec gap analysis
...
Day 26 (2026-03-06) comprehensive PM update:
- Schedule adherence entry with milestone forecasts and developer status
- Updated Current Status Summary: 272 issues closed (77%), 1570/1922 SP (82%)
- PR #617 (UKO Layer 1) and #611 (domain analyzers) merged late Day 26
- Open PR count: 19 -> 15 (merge rate exceeding new PR rate for first time)
- Spec gap analysis: no major coverage gaps found across all 44K-line spec
- All 15 open PRs have PM status comments with action items and deadlines
- Updated milestone roadmap, track forecasts, developer forecasts, risk summary
- Workstream and completion sections updated with Day 26 merges
ISSUES CLOSED: none (PM/docs update only)
2026-03-06 23:43:34 +00:00
freemo
f40e76ad8e
Docs: Daily update to timeline
2026-03-04 22:47:38 -05:00
freemo
296431cfd6
Docs: Fixed another formatting issue with the documentation
2026-03-04 12:17:24 -05:00
freemo
10d5d9839d
Updated small inconsistency in section titles
2026-03-03 22:27:21 -05:00
freemo
8a02512572
Docs: daily update to timeline
2026-03-03 20:53:38 -05:00
freemo
656b8552f8
Docs: Updated daily timeline documentation
2026-03-02 11:40:17 -05:00
freemo
7190b282c7
Docs: Updated daily timeline documentation
2026-03-02 10:39:18 -05:00
freemo
ccc1617adf
Docs: Updated daily timeline documentation
2026-03-02 00:02:42 -05:00
freemo
edd739c169
Docs: Fixed broken ToC in timeline
2026-02-28 20:21:37 -05:00
freemo
e0836d6e1a
Docs: Updated timeline
2026-02-27 22:17:57 -05:00
freemo
c88b432beb
Docs: Daily timeline update
2026-02-26 14:32:59 -05:00
freemo
1282bc03b3
Docs: Updated timeline
2026-02-24 17:18:02 -05:00
freemo
23aa4280f2
Docs: fixed table values in timeline
2026-02-24 12:16:28 -05:00
freemo
5c66d718aa
Docs: Fixed bad formatting in implementation timeline documentation
2026-02-24 02:06:53 -05:00
freemo
b1637eb02e
Docs: Daily timeline update
2026-02-23 22:52:28 -05:00
freemo
09c2567d60
docs: Moved the last elements from implementation plan to their respective locations and deleted the plan from the repo
...
Refs: #408
2026-02-23 17:53:26 -05:00
freemo
69b99d49e6
docs: Moved the implementation timeline out to its own document
...
Refs: #408
2026-02-23 17:52:59 -05:00