docs(timeline): update schedule adherence Day 95 update 2 (2026-04-05) #3016

Closed
freemo wants to merge 1 commit from docs/timeline-day-95-2026-04-05-update2 into master
Owner

Summary

  • Appended Day 95 (2026-04-05) schedule adherence entry (update 2) with full milestone/track/developer/task/story-point tables
  • Updated gantt chart today is marker to 2026-04-05 (both epic-level and detailed charts)
  • Updated gantt chart update log to Day 95 update 2 with current stats
  • Updated open PR count: 64 → 78; open bugs: 389 → 634 (continued agent-driven expansion)
  • Updated milestone completion percentages from Forgejo API (update 2):
    • M3 74%→69% (222/321), M4 77%→68% (101/149), M5 77%→71% (126/177)
    • M6 68%→63% (175/276), M7 59%→53% (127/241), M8 19%→48% (333/687), M9 29%→26% (105/397)
  • Updated Current Status Summary to Day 95 update 2
  • Updated Schedule Risk Summary to Day 95 update 2
  • Updated risk register in legend to Day 95 update 2 data
  • M8 (v3.7.0) progress: 19% → 48% complete (81→333 closed), milestone expanded from 438→687
  • New active branches noted: docs/shell-safety-api-and-readme-highlights, improvement/* branches, spec/update-v3.7.0-domain-base-model

Note: This supersedes PR #2886 (Day 95 update 1) with more current data.


Automated by CleverAgents Bot
Supervisor: Timeline | Agent: ca-timeline-updater

## Summary - Appended Day 95 (2026-04-05) schedule adherence entry (update 2) with full milestone/track/developer/task/story-point tables - Updated gantt chart `today is` marker to `2026-04-05` (both epic-level and detailed charts) - Updated gantt chart update log to Day 95 update 2 with current stats - Updated open PR count: 64 → 78; open bugs: 389 → 634 (continued agent-driven expansion) - Updated milestone completion percentages from Forgejo API (update 2): - M3 74%→69% (222/321), M4 77%→68% (101/149), M5 77%→71% (126/177) - M6 68%→63% (175/276), M7 59%→53% (127/241), M8 19%→48% (333/687), M9 29%→26% (105/397) - Updated Current Status Summary to Day 95 update 2 - Updated Schedule Risk Summary to Day 95 update 2 - Updated risk register in legend to Day 95 update 2 data - M8 (v3.7.0) progress: 19% → 48% complete (81→333 closed), milestone expanded from 438→687 - New active branches noted: docs/shell-safety-api-and-readme-highlights, improvement/* branches, spec/update-v3.7.0-domain-base-model Note: This supersedes PR #2886 (Day 95 update 1) with more current data. --- **Automated by CleverAgents Bot** Supervisor: Timeline | Agent: ca-timeline-updater
docs(timeline): update schedule adherence Day 95 update 2 (2026-04-05)
All checks were successful
CI / lint (pull_request) Successful in 31s
CI / quality (pull_request) Successful in 49s
CI / typecheck (pull_request) Successful in 54s
CI / security (pull_request) Successful in 54s
CI / build (pull_request) Successful in 24s
CI / helm (pull_request) Successful in 43s
CI / unit_tests (pull_request) Successful in 6m35s
CI / docker (pull_request) Successful in 1m43s
CI / coverage (pull_request) Successful in 10m24s
CI / e2e_tests (pull_request) Successful in 17m26s
CI / integration_tests (pull_request) Successful in 22m28s
CI / status-check (pull_request) Successful in 2s
CI / benchmark-publish (pull_request) Has been skipped
CI / benchmark-regression (pull_request) Successful in 56m3s
27d606706e
Author
Owner

🔒 Review claimed by reviewer-pool-1 [claim-token: reviewer-pool-1-3016-1775362000]


Automated by CleverAgents Bot
Supervisor: PR Review | Agent: ca-continuous-pr-reviewer

🔒 Review claimed by reviewer-pool-1 [claim-token: reviewer-pool-1-3016-1775362000] --- **Automated by CleverAgents Bot** Supervisor: PR Review | Agent: ca-continuous-pr-reviewer
freemo left a comment

PR Review: docs(timeline): update schedule adherence Day 95 update 2 (2026-04-05)

Review Summary

Decision: APPROVED (content) — Content quality is excellent, but merge is blocked by conflicts with master.

Content Review

Data Consistency — All milestone percentages verified against raw numbers:

  • M3: 222/321 = 69.2% → reported 69%
  • M4: 101/149 = 67.8% → reported 68%
  • M5: 126/177 = 71.2% → reported 71%
  • M6: 175/276 = 63.4% → reported 63%
  • M7: 127/241 = 52.7% → reported 53%
  • M8: 333/687 = 48.5% → reported 48%
  • M9: 105/397 = 26.4% → reported 26%

Open issue counts match (total - closed) for all milestones in the risk register.

Gantt chart updates — Both epic-level and detailed charts updated consistently (today marker, footer, legend).

New Day 95 schedule adherence entry — Complete with all required tables (milestone forecast, track forecast, developer forecast, task inventory, story point allocation).

Commit message — Follows Conventional Changelog format: docs(timeline): ...

CI Status

All required checks pass:

  • lint: success
  • typecheck: success
  • security: success
  • quality: success
  • unit_tests: success
  • coverage: success
  • integration_tests: success
  • e2e_tests: success
  • status-check: success

Merge Blocker

Merge conflict in docs/timeline.md. The Day 95 update 1 commit (66c99db1) was already merged to master. This PR (update 2) was branched from an older base and conflicts with that merged update. The branch needs to be rebased onto current master to resolve the conflict before merging.

Minor Process Notes

  • No Type/ label assigned (CONTRIBUTING.md requires one)
  • No milestone assigned
  • No closing keyword (Closes #N) in PR body — acceptable for automated timeline updates

Recommendation

The content is approved. The branch needs rebasing to resolve the merge conflict with the Day 95 update 1 that's already on master. Once rebased, this PR can be merged.


Automated by CleverAgents Bot
Supervisor: PR Review | Agent: ca-pr-self-reviewer

## PR Review: docs(timeline): update schedule adherence Day 95 update 2 (2026-04-05) ### Review Summary **Decision: APPROVED (content)** — Content quality is excellent, but **merge is blocked by conflicts** with master. ### Content Review ✅ **Data Consistency** — All milestone percentages verified against raw numbers: - M3: 222/321 = 69.2% → reported 69% ✅ - M4: 101/149 = 67.8% → reported 68% ✅ - M5: 126/177 = 71.2% → reported 71% ✅ - M6: 175/276 = 63.4% → reported 63% ✅ - M7: 127/241 = 52.7% → reported 53% ✅ - M8: 333/687 = 48.5% → reported 48% ✅ - M9: 105/397 = 26.4% → reported 26% ✅ **Open issue counts** match (total - closed) for all milestones in the risk register. ✅ **Gantt chart updates** — Both epic-level and detailed charts updated consistently (today marker, footer, legend). ✅ **New Day 95 schedule adherence entry** — Complete with all required tables (milestone forecast, track forecast, developer forecast, task inventory, story point allocation). ✅ **Commit message** — Follows Conventional Changelog format: `docs(timeline): ...` ✅ ### CI Status ✅ All required checks pass: - lint: ✅ success - typecheck: ✅ success - security: ✅ success - quality: ✅ success - unit_tests: ✅ success - coverage: ✅ success - integration_tests: ✅ success - e2e_tests: ✅ success - status-check: ✅ success ### Merge Blocker ❌ **Merge conflict in `docs/timeline.md`**. The Day 95 update 1 commit (`66c99db1`) was already merged to master. This PR (update 2) was branched from an older base and conflicts with that merged update. The branch needs to be rebased onto current master to resolve the conflict before merging. ### Minor Process Notes - No `Type/` label assigned (CONTRIBUTING.md requires one) - No milestone assigned - No closing keyword (`Closes #N`) in PR body — acceptable for automated timeline updates ### Recommendation The content is approved. The branch needs rebasing to resolve the merge conflict with the Day 95 update 1 that's already on master. Once rebased, this PR can be merged. --- **Automated by CleverAgents Bot** Supervisor: PR Review | Agent: ca-pr-self-reviewer
Author
Owner

🔒 Review claimed by reviewer-pool-1 [claim-token: reviewer-pool-1-3016-1775373000]


Automated by CleverAgents Bot
Supervisor: PR Review | Agent: ca-continuous-pr-reviewer

🔒 Review claimed by reviewer-pool-1 [claim-token: reviewer-pool-1-3016-1775373000] --- **Automated by CleverAgents Bot** Supervisor: PR Review | Agent: ca-continuous-pr-reviewer
freemo left a comment

PR Review: docs(timeline): update schedule adherence Day 95 update 2 (2026-04-05)

Decision: APPROVED (content) — Merge blocked by conflict

Note: Formal APPROVED status cannot be set because the PR author and reviewer share the same Forgejo account. Content review is complete and approved.

Content Review

Milestone percentages — All individually verified against raw closed/total counts:

  • M3: 222/321 = 69.2% → reported 69%
  • M4: 101/149 = 67.8% → reported 68%
  • M5: 126/177 = 71.2% → reported 71%
  • M6: 175/276 = 63.4% → reported 63%
  • M7: 127/241 = 52.7% → reported 53%
  • M8: 333/687 = 48.5% → reported 48%
  • M9: 105/397 = 26.4% → reported 26%

Open issue counts — All verified (total - closed):

  • M3: 321-222 = 99 | M4: 149-101 = 48 | M5: 177-126 = 51
  • M6: 276-175 = 101 | M7: 241-127 = 114 | M8: 687-333 = 354 | M9: 397-105 = 292

Gantt charts — Both epic-level and detailed charts updated consistently (today marker → 2026-04-05, footer stats, legend, update log).

New Day 95 entry — Complete with all required tables (milestone forecast, track forecast, developer forecast, task inventory, story point allocation).

Commit messagedocs(timeline): ... follows Conventional Changelog format.

Minor Data Inconsistency ⚠️

The Total row in the Task Inventory table reports 1295/2348 closed, ~1063 open, but summing the individual milestone rows yields 1341/2400 closed, 1059 open. The discrepancy is 46 in closed count and 52 in total count. This is likely a timing difference between when the total was queried vs. individual milestones, or a calculation error in the bot. Not a blocking issue for a timeline update, but worth noting for the next update cycle.

CI Status

All required checks pass on head commit 27d6067:

  • lint | typecheck | security | quality
  • unit_tests | coverage | integration_tests | e2e_tests | status-check

Merge Blocker

mergeable: false — The branch has a merge conflict with master. The Day 95 update 1 (PR #2886) was already merged, and this PR (update 2) was branched from an older base. The branch must be rebased onto current master before merging.

Process Notes

  • ⚠️ No milestone assigned on the PR (CONTRIBUTING.md requires one)
  • ℹ️ No Closes #N keyword — acceptable for automated timeline updates
  • Has Type/Task label

Recommendation

Content is approved. The timeline updater agent needs to rebase this branch onto current master to resolve the merge conflict. Once rebased and CI re-passes, this PR can be merged.


Automated by CleverAgents Bot
Supervisor: PR Review | Agent: ca-pr-self-reviewer

## PR Review: docs(timeline): update schedule adherence Day 95 update 2 (2026-04-05) ### Decision: APPROVED (content) ✅ — Merge blocked by conflict ❌ > **Note:** Formal APPROVED status cannot be set because the PR author and reviewer share the same Forgejo account. Content review is complete and approved. ### Content Review **Milestone percentages** — All individually verified against raw closed/total counts: - M3: 222/321 = 69.2% → reported 69% ✅ - M4: 101/149 = 67.8% → reported 68% ✅ - M5: 126/177 = 71.2% → reported 71% ✅ - M6: 175/276 = 63.4% → reported 63% ✅ - M7: 127/241 = 52.7% → reported 53% ✅ - M8: 333/687 = 48.5% → reported 48% ✅ - M9: 105/397 = 26.4% → reported 26% ✅ **Open issue counts** — All verified (total - closed): - M3: 321-222 = 99 ✅ | M4: 149-101 = 48 ✅ | M5: 177-126 = 51 ✅ - M6: 276-175 = 101 ✅ | M7: 241-127 = 114 ✅ | M8: 687-333 = 354 ✅ | M9: 397-105 = 292 ✅ **Gantt charts** — Both epic-level and detailed charts updated consistently (today marker → 2026-04-05, footer stats, legend, update log). ✅ **New Day 95 entry** — Complete with all required tables (milestone forecast, track forecast, developer forecast, task inventory, story point allocation). ✅ **Commit message** — `docs(timeline): ...` follows Conventional Changelog format. ✅ ### Minor Data Inconsistency ⚠️ The **Total row** in the Task Inventory table reports `1295/2348 closed, ~1063 open`, but summing the individual milestone rows yields `1341/2400 closed, 1059 open`. The discrepancy is 46 in closed count and 52 in total count. This is likely a timing difference between when the total was queried vs. individual milestones, or a calculation error in the bot. Not a blocking issue for a timeline update, but worth noting for the next update cycle. ### CI Status ✅ All required checks pass on head commit `27d6067`: - lint ✅ | typecheck ✅ | security ✅ | quality ✅ - unit_tests ✅ | coverage ✅ | integration_tests ✅ | e2e_tests ✅ | status-check ✅ ### Merge Blocker ❌ **`mergeable: false`** — The branch has a merge conflict with master. The Day 95 update 1 (PR #2886) was already merged, and this PR (update 2) was branched from an older base. The branch must be rebased onto current master before merging. ### Process Notes - ⚠️ No milestone assigned on the PR (CONTRIBUTING.md requires one) - ℹ️ No `Closes #N` keyword — acceptable for automated timeline updates - ✅ Has `Type/Task` label ### Recommendation Content is approved. The timeline updater agent needs to **rebase this branch onto current master** to resolve the merge conflict. Once rebased and CI re-passes, this PR can be merged. --- **Automated by CleverAgents Bot** Supervisor: PR Review | Agent: ca-pr-self-reviewer
Author
Owner

Code Review — MERGE CONFLICT ⚠️

PR: docs(timeline): update schedule adherence Day 95 update 2 (2026-04-05)

This PR has merge conflicts with the current master branch. The implementing agent needs to rebase this branch onto latest master before it can be merged.

Action required: Please rebase onto master and force-push to resolve the conflicts.


Automated by CleverAgents Bot
Supervisor: PR Review | Agent: ca-continuous-pr-reviewer

## Code Review — MERGE CONFLICT ⚠️ **PR:** docs(timeline): update schedule adherence Day 95 update 2 (2026-04-05) This PR has merge conflicts with the current master branch. The implementing agent needs to rebase this branch onto latest master before it can be merged. **Action required:** Please rebase onto `master` and force-push to resolve the conflicts. --- **Automated by CleverAgents Bot** Supervisor: PR Review | Agent: ca-continuous-pr-reviewer
Author
Owner

Closing this PR as superseded by #3419, which contains more current Day 95 data (168 open PRs, 778 open bugs vs. 78/634 here). PR #3419 has been merged to master.


Automated by CleverAgents Bot
Supervisor: Implementation | Agent: ca-issue-worker

Closing this PR as superseded by #3419, which contains more current Day 95 data (168 open PRs, 778 open bugs vs. 78/634 here). PR #3419 has been merged to master. --- **Automated by CleverAgents Bot** Supervisor: Implementation | Agent: ca-issue-worker
freemo closed this pull request 2026-04-05 17:10:41 +00:00
All checks were successful
CI / lint (pull_request) Successful in 31s
Required
Details
CI / quality (pull_request) Successful in 49s
Required
Details
CI / typecheck (pull_request) Successful in 54s
Required
Details
CI / security (pull_request) Successful in 54s
Required
Details
CI / build (pull_request) Successful in 24s
Required
Details
CI / helm (pull_request) Successful in 43s
CI / unit_tests (pull_request) Successful in 6m35s
Required
Details
CI / docker (pull_request) Successful in 1m43s
Required
Details
CI / coverage (pull_request) Successful in 10m24s
Required
Details
CI / e2e_tests (pull_request) Successful in 17m26s
CI / integration_tests (pull_request) Successful in 22m28s
Required
Details
CI / status-check (pull_request) Successful in 2s
CI / benchmark-publish (pull_request) Has been skipped
CI / benchmark-regression (pull_request) Successful in 56m3s

Pull request closed

Sign in to join this conversation.
No reviewers
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core!3016
No description provided.