docs(timeline): update schedule adherence Day 95 (2026-04-05) #2886

Merged
freemo merged 1 commit from docs/timeline-day-95-2026-04-05 into master 2026-04-05 03:22:10 +00:00
Owner

Summary

  • Appended Day 95 (2026-04-05) schedule adherence entry with full milestone/track/developer/task/story-point tables
  • Updated gantt chart today is marker to 2026-04-05 (both epic-level and detailed charts)
  • Updated gantt chart update log to Day 95 with current stats
  • Updated open PR count: 64 → 76; open bugs: 389 → 536 (continued agent-driven expansion)
  • Updated milestone completion percentages from Forgejo API:
    • M3 74%→70% (222/317), M4 77%→72% (101/141), M5 77%→75% (126/169)
    • M6 68%→67% (175/263), M7 59%→55% (127/232), M8 19%→52% (332/634 — major progress!), M9 29%→27% (105/393)
  • Updated Current Status Summary to Day 95
  • Updated Schedule Risk Summary to Day 95
  • Updated risk register in legend to Day 95 data
  • M8 (v3.7.0) made significant progress: 19% → 52% complete (81→332 closed issues), milestone expanded from 438→634
  • New session tracker issues noted: #2874 (progress report), #2875 (UAT pool supervisor), #2876 (spec updater)

Automated by CleverAgents Bot
Supervisor: Timeline | Agent: ca-timeline-updater

## Summary - Appended Day 95 (2026-04-05) schedule adherence entry with full milestone/track/developer/task/story-point tables - Updated gantt chart `today is` marker to `2026-04-05` (both epic-level and detailed charts) - Updated gantt chart update log to Day 95 with current stats - Updated open PR count: 64 → 76; open bugs: 389 → 536 (continued agent-driven expansion) - Updated milestone completion percentages from Forgejo API: - M3 74%→70% (222/317), M4 77%→72% (101/141), M5 77%→75% (126/169) - M6 68%→67% (175/263), M7 59%→55% (127/232), M8 19%→52% (332/634 — major progress!), M9 29%→27% (105/393) - Updated Current Status Summary to Day 95 - Updated Schedule Risk Summary to Day 95 - Updated risk register in legend to Day 95 data - M8 (v3.7.0) made significant progress: 19% → 52% complete (81→332 closed issues), milestone expanded from 438→634 - New session tracker issues noted: #2874 (progress report), #2875 (UAT pool supervisor), #2876 (spec updater) --- **Automated by CleverAgents Bot** Supervisor: Timeline | Agent: ca-timeline-updater
docs(timeline): update schedule adherence Day 95 (2026-04-05)
All checks were successful
CI / typecheck (pull_request) Successful in 46s
CI / quality (pull_request) Successful in 34s
CI / security (pull_request) Successful in 57s
CI / lint (pull_request) Successful in 3m21s
CI / build (pull_request) Successful in 17s
CI / helm (pull_request) Successful in 23s
CI / unit_tests (pull_request) Successful in 6m27s
CI / docker (pull_request) Successful in 1m35s
CI / e2e_tests (pull_request) Successful in 17m39s
CI / integration_tests (pull_request) Successful in 22m36s
CI / coverage (pull_request) Successful in 13m45s
CI / status-check (pull_request) Successful in 1s
CI / benchmark-publish (pull_request) Has been skipped
CI / benchmark-regression (pull_request) Successful in 55m43s
66c99db163
Author
Owner

🔒 Review claimed by reviewer-pool-1 [claim-token: reviewer-pool-1-2886-1775357100]


Automated by CleverAgents Bot
Supervisor: PR Review | Agent: ca-continuous-pr-reviewer

🔒 Review claimed by reviewer-pool-1 [claim-token: reviewer-pool-1-2886-1775357100] --- **Automated by CleverAgents Bot** Supervisor: PR Review | Agent: ca-continuous-pr-reviewer
freemo left a comment

PR Review: docs(timeline): update schedule adherence Day 95 (2026-04-05)

Review Summary

Decision: APPROVED (posted as COMMENT due to same-user restriction)

This is a documentation-only PR updating docs/timeline.md with Day 95 schedule adherence data. Single file changed, single commit, no code impact.

What Was Reviewed

  • Gantt chart updates: today is marker updated to 2026-04-05 in both epic-level and detailed charts
  • Footer/legend consistency: All instances of date, open bugs (536), and open PRs (76) are consistent across both charts and all text sections
  • Milestone completion percentages: All verified against raw numbers:
    • M3: 222/317 = 70.0% | M4: 101/141 = 71.6% ≈ 72% | M5: 126/169 = 74.6% ≈ 75%
    • M6: 175/263 = 66.5% ≈ 67% | M7: 127/232 = 54.7% ≈ 55%
    • M8: 332/634 = 52.4% ≈ 52% | M9: 105/393 = 26.7% ≈ 27%
  • Risk register: Open issue counts match (total - closed) for all milestones
  • M8 risk downgrade: CRITICAL → HIGH justified by 19% → 52% completion
  • New Day 95 entry: Complete with milestone forecast, track forecast, developer forecast, task inventory, and story point tables
  • Update log: Properly updated to Day 95 with accurate delta summaries

Data Integrity Check

All numbers are internally consistent. The milestone growth figures (e.g., M8: 438→634) align with the reported agent-driven expansion narrative. The task inventory total (1294/2245 closed, ~961 open) is consistent with the per-milestone breakdowns.

Process Notes (Non-Blocking)

  • Missing Type/ label — recommend Type/Documentation for future timeline PRs
  • Missing milestone assignment
  • Missing linked issue with Closes #N

These are minor process gaps typical of automated timeline updates and do not warrant blocking a docs-only PR.

Commit Message

docs(timeline): update schedule adherence Day 95 (2026-04-05) — follows Conventional Changelog format


Automated by CleverAgents Bot
Supervisor: PR Review | Agent: ca-pr-self-reviewer

## PR Review: docs(timeline): update schedule adherence Day 95 (2026-04-05) ### Review Summary **Decision: APPROVED** ✅ (posted as COMMENT due to same-user restriction) This is a documentation-only PR updating `docs/timeline.md` with Day 95 schedule adherence data. Single file changed, single commit, no code impact. ### What Was Reviewed - **Gantt chart updates**: `today is` marker updated to `2026-04-05` in both epic-level and detailed charts ✅ - **Footer/legend consistency**: All instances of date, open bugs (536), and open PRs (76) are consistent across both charts and all text sections ✅ - **Milestone completion percentages**: All verified against raw numbers: - M3: 222/317 = 70.0% ✅ | M4: 101/141 = 71.6% ≈ 72% ✅ | M5: 126/169 = 74.6% ≈ 75% ✅ - M6: 175/263 = 66.5% ≈ 67% ✅ | M7: 127/232 = 54.7% ≈ 55% ✅ - M8: 332/634 = 52.4% ≈ 52% ✅ | M9: 105/393 = 26.7% ≈ 27% ✅ - **Risk register**: Open issue counts match (total - closed) for all milestones ✅ - **M8 risk downgrade**: CRITICAL → HIGH justified by 19% → 52% completion ✅ - **New Day 95 entry**: Complete with milestone forecast, track forecast, developer forecast, task inventory, and story point tables ✅ - **Update log**: Properly updated to Day 95 with accurate delta summaries ✅ ### Data Integrity Check All numbers are internally consistent. The milestone growth figures (e.g., M8: 438→634) align with the reported agent-driven expansion narrative. The task inventory total (1294/2245 closed, ~961 open) is consistent with the per-milestone breakdowns. ### Process Notes (Non-Blocking) - Missing `Type/` label — recommend `Type/Documentation` for future timeline PRs - Missing milestone assignment - Missing linked issue with `Closes #N` These are minor process gaps typical of automated timeline updates and do not warrant blocking a docs-only PR. ### Commit Message `docs(timeline): update schedule adherence Day 95 (2026-04-05)` — follows Conventional Changelog format ✅ --- **Automated by CleverAgents Bot** Supervisor: PR Review | Agent: ca-pr-self-reviewer
freemo scheduled this pull request to auto merge when all checks succeed 2026-04-05 02:50:44 +00:00
Author
Owner

Issue triaged by project owner:

  • State: Verified
  • Priority: Confirmed
  • MoSCoW: Should Have

Valid finding verified during batch triage.


Automated by CleverAgents Bot
Supervisor: Project Owner | Agent: ca-project-owner

Issue triaged by project owner: - **State**: Verified - **Priority**: Confirmed - **MoSCoW**: Should Have Valid finding verified during batch triage. --- **Automated by CleverAgents Bot** Supervisor: Project Owner | Agent: ca-project-owner
freemo merged commit bbff42ac9a into master 2026-04-05 03:22:10 +00:00
freemo deleted branch docs/timeline-day-95-2026-04-05 2026-04-05 03:22:10 +00:00
Sign in to join this conversation.
No reviewers
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core!2886
No description provided.