docs(timeline): update schedule adherence Day 95 update 2 (2026-04-05) #3016

Closed
freemo wants to merge 1 commits from docs/timeline-day-95-2026-04-05-update2 into master
+129 -41
View File
@@ -10,28 +10,24 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-03 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 389 open bugs | 64 open PRs | Session 3 active
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 634 open bugs | 78 open PRs | Session 3 active
Project starts 2026-02-03
saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-03
today is 2026-04-05
today is colored in #FF6666
' ================================================================
' GANTT CHART UPDATE LOG (Day 54 — 2026-04-03 end-of-day update 2)
' Changes: 16 PRs merged today (+#2399 noxfile DB template extension).
' Open PRs: 61→64 (+3 new PRs). Open bugs: 324→389 (+65 new bugs from agents).
' Open issues: ~2362→~2494+ (continued agent-driven expansion).
' M3 74% (218/296), M4 77% (100/130), M5 77% (126/163), M6 68% (175/259),
' M7 59% (125/213), M8 19% (81/438), M9 29% (105/359).
' PRs merged today: #2399 (noxfile DB template), #2181 (TUI docs), #2050 (CHANGELOG),
' #2014 (domain refactor), #1999 (aiohttp CVE fix), #1990 (A2A JSON-RPC rename),
' #1969 (actor add panels), #1865 (TLS fix), #1841 (SSE formatter), #1810 (flaky test fix),
' #1775 (CI script), #1733 (actor examples), #1644 (CI cache), #1633 (CI parallelize),
' #1584 (nox CI), #1577 (plan workflow fix).
' GANTT CHART UPDATE LOG (Day 95 — 2026-04-05 update 2)
' Changes: Day 95 update 2. Open PRs: 64→78 (+14). Open bugs: 389→634 (+245 agent-driven).
' Open issues: continued agent-driven expansion across all milestones.
' M3 69% (222/321), M4 68% (101/149), M5 71% (126/177), M6 63% (175/276),
' M7 53% (127/241), M8 48% (333/687), M9 26% (105/397).
' Session 3 active. UAT pool supervisor (#2875) and spec updater (#2876) running.
' New branches: docs/shell-safety-api-and-readme-highlights, improvement/* branches active.
' ================================================================
<style>
@@ -233,7 +229,7 @@ ganttDiagram {
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
[M3] starts at [M2]'s end
[M3] is 74% completed
[M3] is 69% completed
[M3] is colored in LightSkyBlue/SteelBlue
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
@@ -254,7 +250,7 @@ ganttDiagram {
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
[M4] starts at [M3]'s end
[M4] is 77% completed
[M4] is 68% completed
[M4] is colored in LightSkyBlue/SteelBlue
@@ -285,12 +281,12 @@ ganttDiagram {
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
[M5] starts at [M4]'s end
[M5] is 77% completed
[M5] is 71% completed
[M5] is colored in LightSkyBlue/SteelBlue
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
[M6] starts at [M5]'s end
[M6] is 68% completed
[M6] is 63% completed
[M6] is colored in LightSkyBlue/SteelBlue
[Subplans + Parallelism (#368)] as [SUBP] on {Luis} {Brent} requires 2 days
@@ -300,7 +296,7 @@ ganttDiagram {
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
[LARGE] starts 2026-03-17
[LARGE] is 59% completed
[LARGE] is 53% completed
[LARGE] is colored in LightSkyBlue/SteelBlue
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
@@ -402,15 +398,15 @@ legend right
| v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs |
| v3.6.0 | Mar 27 | 2 | 100 | Deferred work |
----
**Risk Register (Day 54 — end-of-day update 2)**
**Risk Register (Day 95 update 2 — 2026-04-05)**
|= Epic |= Completion |= Risk |= Blocker |
| M3 (#357) | 74% | **CRITICAL** | 78 open issues in v3.2.0 |
| M4 (#358) | 77% | **HIGH** | 30 open issues in v3.3.0 |
| M5 (#359) | 77% | **HIGH** | 37 open issues in v3.4.0 |
| M6 (#360) | 68% | **HIGH** | 84 open issues in v3.5.0 |
| M7 (#361) | 59% | **HIGH** | 88 open issues in v3.6.0 |
| M8 (#362) | 19% | **CRITICAL** | 357 open issues in v3.7.0 (agent expansion) |
| SEC (#363) | 29% | **HIGH** | 254 open issues in v3.8.0 (agent expansion) |
| M3 (#357) | 69% | **CRITICAL** | 99 open issues in v3.2.0 |
| M4 (#358) | 68% | **HIGH** | 48 open issues in v3.3.0 |
| M5 (#359) | 71% | **HIGH** | 51 open issues in v3.4.0 |
| M6 (#360) | 63% | **HIGH** | 101 open issues in v3.5.0 |
| M7 (#361) | 53% | **HIGH** | 114 open issues in v3.6.0 |
| M8 (#362) | 48% | **HIGH** | 354 open issues in v3.7.0 (agent expansion) |
| SEC (#363) | 26% | **HIGH** | 292 open issues in v3.8.0 (agent expansion) |
----
**Color Key**
|= Color |= Meaning |
@@ -418,11 +414,11 @@ legend right
| <back:LightSkyBlue> </back> | In Progress |
| <back:#E8E8E8> </back> | Not Started |
| <back:Gold> <> </back> | Milestone Target |
| <back:#FF6666> | </back> | Today (2026-04-03) |
| <back:#FF6666> | </back> | Today (2026-04-05) |
----
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
~1649 total story points | ~3300 estimated hours
**389 open bugs — 64 open PRs — Session 3 active (16 workers, ~71 agents)**
**634 open bugs — 78 open PRs — Session 3 active (16 workers, ~71 agents)**
end legend
@endgantt
@@ -446,7 +442,7 @@ saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-03
today is 2026-04-05
today is colored in #FF6666
<style>
@@ -1951,11 +1947,11 @@ legend right
| <back:LightSkyBlue> </back> | Issue: In Progress |
| <back:#E8E8E8> </back> | Issue: Not Started |
| <back:Gold> <> </back> | Milestone Target |
| <back:#FF6666> | </back> | Today (2026-04-03) |
| <back:#FF6666> | </back> | Today (2026-04-05) |
----
271 Issues | 29 Epics | 9 Legendaries | 7 Milestones
~1649 total story points | ~3300 estimated hours
**389 open bugs — 64 open PRs — Session 3 active (16 workers, ~71 agents)**
**634 open bugs — 78 open PRs — Session 3 active (16 workers, ~71 agents)**
end legend
@endgantt
@@ -1967,13 +1963,13 @@ This section provides a high-level overview of the CleverAgents implementation r
### Current Status Summary
As of Day 54 (2026-04-03, end-of-day update 2), the project has **64 open PRs** and **~2494+ open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. 16 PRs merged today (including #2399 noxfile DB template extension). Bug count is **389 open bugs** (continued agent-driven expansion). M8 (v3.7.0) is now **19% complete** (81/438 issues closed — milestone grew from 185→438). M9 (v3.8.0) is **29% complete** (105/359 issues closed — milestone grew from 242→359).
As of Day 95 (2026-04-05, update 2), the project has **78 open PRs** and **~2900+ open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **634 open bugs** (continued agent-driven expansion from 389). M8 (v3.7.0) is now **48% complete** (333/687 issues closed — milestone grew from 438→687). M9 (v3.8.0) is **26% complete** (105/397 issues closed).
**M1, M2 fully complete. M3 (v3.2.0)**: 74% complete (218/296), 78 open issues. **M4 (v3.3.0)**: 77% complete (100/130), 30 open issues. **M5 (v3.4.0)**: 77% complete (126/163), 37 open issues. **M6 (v3.5.0)**: 68% complete (175/259), 84 open issues. **M7 (v3.6.0)**: 59% complete (125/213), 88 open issues. **M8 (v3.7.0)**: 19% complete (81/438), 357 open issues. **M9 (v3.8.0)**: 29% complete (105/359), 254 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
**M1, M2 fully complete. M3 (v3.2.0)**: 69% complete (222/321), 99 open issues. **M4 (v3.3.0)**: 68% complete (101/149), 48 open issues. **M5 (v3.4.0)**: 71% complete (126/177), 51 open issues. **M6 (v3.5.0)**: 63% complete (175/276), 101 open issues. **M7 (v3.6.0)**: 53% complete (127/241), 114 open issues. **M8 (v3.7.0)**: 48% complete (333/687), 354 open issues. **M9 (v3.8.0)**: 26% complete (105/397), 292 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 389 Open Bugs — Session 3 Active (Day 54: Continued Agent Expansion)"
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 634 Open Bugs — Session 3 Active (Day 95 update 2: Continued Agent Expansion)"
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. 16 PRs merged today (A2A JSON-RPC, actor panels, TLS fix, CI improvements, aiohttp CVE, noxfile DB template). Open PRs at **64** (up from 61 — new PRs opened). Open bugs at **389** (continued agent-driven expansion from 324). M8 (v3.7.0) at 19% (81/438 closed — milestone grew from 185→438). M9 (v3.8.0) at 29% (105/359 closed — milestone grew from 242→359). **Current priorities**: (1) **Triage 389 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 64 open PRs** CLI fix wave, TUI features, security fixes. (3) **Continue M8 push**19% complete, 357 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 74% (78 open), M4 at 77% (30 open), M5 at 77% (37 open).
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **78** (up from 64). Open bugs at **634** (continued agent-driven expansion from 389). M8 (v3.7.0) at 48% (333/687 closed — milestone grew from 438→687). M9 (v3.8.0) at 26% (105/397 closed). UAT pool supervisor (#2875) and spec updater (#2876) agents running. **Current priorities**: (1) **Triage 634 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 78 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push**48% complete, 354 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 69% (99 open), M4 at 68% (48 open), M5 at 71% (51 open).
### Parallel Workstreams
@@ -2289,18 +2285,18 @@ Items without an assigned milestone represent backlog work to be addressed after
### Schedule Risk Summary
As of Day 54 (2026-04-03, end-of-day update 2), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. 16 PRs merged today. Open PRs now at **64** (up from 61 — new PRs opened). Open bugs at **389** (continued agent-driven expansion from 324). M8 (v3.7.0) at **19% complete** (81/438 closed — milestone grew from 185→438). M9 (v3.8.0) at **29% complete** (105/359 closed — milestone grew from 242→359). Critical path: 64 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 19% with 357 issues remaining; 389 open bugs need TDD counterparts and systematic triage.
As of Day 95 (2026-04-05, update 2), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **78** (up from 64). Open bugs at **634** (continued agent-driven expansion from 389). M8 (v3.7.0) at **48% complete** (333/687 closed — milestone grew from 438→687). M9 (v3.8.0) at **26% complete** (105/397 closed). Critical path: 78 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 48% with 354 issues remaining; 634 open bugs need TDD counterparts and systematic triage.
**Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry.
**Day 53 Session 3 actions**: (a) 16 parallel workers started. (b) 73+ PRs merged including ACMS UKO runtime (#1312), PermissionsScreen TUI (#1307), actor thought blocks (#1298), DatabaseResourceHandler (#1293), ACMS pipeline Phase 2 (#1287), DevcontainerHandler (#1286), async audit (#1279), serve CLI (#1272), LSP hover/definitions (#1240), domain event wiring (#1215), plan prompt command (#1212), M6 E2E tests (#1277), @tdd_expected_fail cleanup (#1229), persona export/import (#1338), first-run experience (#1391), session export/import (#1392). (c) UAT supervisor fleet (cycles 11-131) launched — discovered 100+ spec compliance bugs across CLI rich output, YAML config handling, and actor compiler. (d) Security bug-hunt PRs opened: #1412 (concurrency), #1409 (error handling), #1419 (hardcoded secrets). (e) Late-day: 4 more PRs merged (#1498, #1481, #1479, #1338), 18 new fix PRs opened (#1506-#1517) targeting UAT findings. (f) End-of-day CLI fix wave: 18 more PRs merged (#1574, #1573, #1570, #1569, #1567, #1566, #1565, #1563, #1562, #1558, #1556, #1554 and others) — open bugs reduced from **143 to 6**, open PRs at **74**.
**Critical path blockers** (ranked):
1. **64 open PRs need review**new PRs opened since morning. All require review before merge.
2. **389 open bugs need TDD counterparts** — agents created additional bugs throughout Day 54. Critical: #1782 (coverage 37%), #1791 (AmbiguousStep crash), #1789/#1768 (path traversal vulnerabilities).
3. **M3-M7 backlog**78+30+37+84+88 open issues across M3-M7. All milestones regressed as agents added new issues throughout Day 54.
4. **M8 (v3.7.0) at 19%** — 357 issues remaining (milestone grew from 185→438). Continued agent-driven expansion.
5. **M9 (v3.8.0) at 29%** — 254 issues remaining (milestone grew from 242→359). Significant expansion but 30 more issues closed.
1. **78 open PRs need review**continued agent-driven PR creation. All require review before merge.
2. **634 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued agent-driven expansion.
3. **M3-M7 backlog**99+48+51+101+114 open issues across M3-M7. All milestones regressed as agents added new issues.
4. **M8 (v3.7.0) at 48%** — 354 issues remaining (milestone grew from 438→687). Continued agent-driven expansion.
5. **M9 (v3.8.0) at 26%** — 292 issues remaining (milestone grew from 359→397). Significant expansion.
**Spec changes impact assessment (Day 31)**: ACP→A2A rename affects 10 source files, 13 classes, 640+ test references across 22 files. Zero A2A code exists — migration not started. All open PRs that touch ACP modules will need additional rebase work after #688/#689 merge. TUI spec adds ~1,500 lines with 18 ASCII mockups defining Textual-based UI — PR #667 was a placeholder that predates this spec. Server architecture adopts JSON-RPC 2.0 standard — PR #676 used custom protocol, now obsolete.
@@ -4943,3 +4939,95 @@ Story points per developer per milestone.
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
### 2026-04-05 (Day 95)
**Summary**
Status: Behind 20+d
Deadline risk: HIGH
**Notes**
- Day 95 update 2. Open PRs increased from 64 → 78 (+14 new PRs). Open bugs increased from 389 → 634 (+245 agent-driven expansion).
- Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. Session tracker issues: #2874 (autonomous build progress report), #2875 (UAT pool supervisor v3.7.0), #2876 (spec updater).
- Milestone totals continued to grow due to agent-driven issue creation: M3 (296→321), M4 (130→149), M5 (163→177), M6 (259→276), M7 (213→241), M8 (438→687), M9 (359→397).
- Milestone completions (Day 95 update 2): M3 69% (222/321), M4 68% (101/149), M5 71% (126/177), M6 63% (175/276), M7 53% (127/241), M8 48% (333/687), M9 26% (105/397).
- M8 (v3.7.0) progress: 19% → 48% complete (81→333 closed issues), though milestone also expanded from 438→687 total issues.
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
- New branches active: docs/shell-safety-api-and-readme-highlights, improvement/agent-ca-pr-reviewer-skip-unchanged, improvement/agent-ca-subtask-loop-meaningful-change-check, improvement/agent-ca-test-infra-improver-worker-api-mode, improvement/agent-ca-uat-tester-progress-report-fix, spec/update-v3.7.0-domain-base-model.
#### Milestone forecast
| Milestone | Target -> ETA | Delta | Risk |
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-04-28 | +61d | CRITICAL |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-02 | +61d | HIGH |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-02 | +57d | HIGH |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-10 | +61d | HIGH |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-05-25 | +58d | HIGH |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-06-20 | N/A | HIGH |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-10 | N/A | MEDIUM |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-02 | MEDIUM | 51 open issues in v3.4.0; continued agent-driven expansion |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-02 | HIGH | 48 open issues in v3.3.0; UAT spec compliance bugs ongoing |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-04-28 | HIGH | 99 open issues in v3.2.0; agent-driven expansion |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 634 open bugs; continued agent-driven bug creation |
| Track T (Testing) | Active | Ongoing | HIGH | 78 open PRs need review; UAT pool supervisor active (#2875) |
#### Developer forecast
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|------|-------------------|--------------|------|-------|
| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance |
| Luis | -21d behind | active | HIGH | M6 (v3.5.0) features; security hardening; audit session |
| Hamza | -21d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource |
| Aditya | -21d behind | active | HIGH | M5 features; TDD counterparts; domain model work |
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 634 open bugs triage |
| Rui | -21d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt |
| Mike/Brian | N/A | standby | LOW | N/A |
#### Task inventory
Milestone per developer as of Day 95 update 2 (2026-04-05).
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 99 open | 222/321 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 48 open | 101/149 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 51 open | 126/177 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 101 open | 175/276 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 114 open | 127/241 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 354 open | 333/687 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 292 open | 105/397 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1063 open** | **1295/2348 closed** |
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 update 2. Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M8 grew from 438→687, M9 grew from 359→397 due to continued agent activity.
#### Story point allocation
Story points per developer per milestone.
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~172 SP |
| M2 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~208 SP |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~104 SP |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~126 SP |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~129 SP |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~151 SP |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~100 SP |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |