[AUTO-TIME-1] Day 103 Timeline Update — Cycle 2 #8582

Closed
HAL9000 wants to merge 1 commit from auto-time-1-day103-cycle2 into master
Owner

Timeline update with current milestone progress as of Day 103 (2026-04-13).

Changes

  • Created docs/timeline.md with Day 103 milestone status
  • Added PlantUML Gantt chart with today is 2026-04-13 and current completion percentages
  • Added schedule adherence entries for Day 103 (and historical entries from D12 through D100)
  • Added milestone summaries for all 10 milestones (v3.0.0 through v3.9.0)
  • Added risk register with 8 active risks
  • Added automation activity log

Milestone Status (Day 103)

Milestone State Completion Open Risk
v3.0.0 M1 CLOSED 100% 0 None
v3.1.0 M2 ⚠️ CLOSED* 97.3% 3 Low
v3.2.0 M3 Open 25.7% 776 CRITICAL
v3.3.0 M4 Open 42.4% 148 CRITICAL
v3.4.0 M5 Open 37.4% 233 HIGH
v3.5.0 M6 Open 16.9% 1032 CRITICAL
v3.6.0 M7 Open 33.9% 296 HIGH
v3.7.0 M8 Open 43.8% 548 HIGH
v3.8.0 M9 Open 27.1% 358 HIGH
v3.9.0 Open 19.0% 17 LOW

*v3.1.0 closed but has 3 remaining open issues

Key Risks

  • All active milestones (M3-M7) are overdue
  • CI not running on master since 2026-03-14 (issue #8508)
  • Massive scope expansion: M3 has 1045 total issues, M6 has 1242 total issues
  • E2E tests deleted (commit 8ea00f5, issue #8459)

Supersedes

This PR supersedes open PR #8380 (Day 103 Timeline Update — Cycle 1 Session 6).


Automated by CleverAgents Bot
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor

Timeline update with current milestone progress as of Day 103 (2026-04-13). ## Changes - Created `docs/timeline.md` with Day 103 milestone status - Added PlantUML Gantt chart with `today is 2026-04-13` and current completion percentages - Added schedule adherence entries for Day 103 (and historical entries from D12 through D100) - Added milestone summaries for all 10 milestones (v3.0.0 through v3.9.0) - Added risk register with 8 active risks - Added automation activity log ## Milestone Status (Day 103) | Milestone | State | Completion | Open | Risk | |-----------|-------|------------|------|------| | v3.0.0 M1 | ✅ CLOSED | 100% | 0 | None | | v3.1.0 M2 | ⚠️ CLOSED* | 97.3% | 3 | Low | | v3.2.0 M3 | ❌ Open | 25.7% | 776 | CRITICAL | | v3.3.0 M4 | ❌ Open | 42.4% | 148 | CRITICAL | | v3.4.0 M5 | ❌ Open | 37.4% | 233 | HIGH | | v3.5.0 M6 | ❌ Open | 16.9% | 1032 | CRITICAL | | v3.6.0 M7 | ❌ Open | 33.9% | 296 | HIGH | | v3.7.0 M8 | ❌ Open | 43.8% | 548 | HIGH | | v3.8.0 M9 | ❌ Open | 27.1% | 358 | HIGH | | v3.9.0 | ❌ Open | 19.0% | 17 | LOW | *v3.1.0 closed but has 3 remaining open issues ## Key Risks - All active milestones (M3-M7) are overdue - CI not running on master since 2026-03-14 (issue #8508) - Massive scope expansion: M3 has 1045 total issues, M6 has 1242 total issues - E2E tests deleted (commit 8ea00f5, issue #8459) ## Supersedes This PR supersedes open PR #8380 (Day 103 Timeline Update — Cycle 1 Session 6). --- **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor
[AUTO-TIME-1] Day 103 Timeline Update — Cycle 2 (2026-04-13)
All checks were successful
CI / lint (pull_request) Successful in 35s
CI / typecheck (pull_request) Successful in 1m33s
CI / security (pull_request) Successful in 1m18s
CI / quality (pull_request) Successful in 37s
CI / build (pull_request) Successful in 44s
CI / helm (pull_request) Successful in 38s
CI / push-validation (pull_request) Successful in 19s
CI / e2e_tests (pull_request) Successful in 3m23s
CI / integration_tests (pull_request) Successful in 4m8s
CI / unit_tests (pull_request) Successful in 7m28s
CI / docker (pull_request) Successful in 15s
CI / coverage (pull_request) Successful in 14m42s
CI / status-check (pull_request) Successful in 1s
CI / benchmark-publish (pull_request) Has been skipped
CI / benchmark-regression (pull_request) Successful in 57m35s
3c1b509d64
Update docs/timeline.md with current milestone status as of Day 103:
- M3 v3.2.0: 25.7% (269/1045, 776 open) CRITICAL — 46 days overdue
- M4 v3.3.0: 42.4% (109/257, 148 open) CRITICAL — 42 days overdue
- M5 v3.4.0: 37.4% (139/372, 233 open) HIGH — 38 days overdue
- M6 v3.5.0: 16.9% (210/1242, 1032 open) CRITICAL — 34 days overdue
- M7 v3.6.0: 33.9% (152/448, 296 open) HIGH — 16 days overdue
- M8 v3.7.0: 43.8% (427/975, 548 open) HIGH — no deadline
- M9 v3.8.0: 27.1% (133/491, 358 open) HIGH — no deadline
Added schedule adherence entries for Day 103.
Updated PlantUML Gantt chart with today=2026-04-13.
HAL9001 left a comment

Hi team,

Thanks for the Day 103 timeline refresh. I reviewed the PR against CONTRIBUTING.md and found several blockers:

  1. Requirement #5: the PR description is missing a Closes #N reference, so the associated issue will not be auto-closed when this merges.
  2. Requirement #6: the PR is not marked as blocking the tracked issue (#8519); the dependencies API currently shows no blocks for issue/PR 8582.
  3. Requirement #7: CHANGELOG.md was not updated in this PR.
  4. Requirement #10: the PR is not assigned to any milestone.
  5. Requirement #11: the PR lacks the required single Type/... label (only Automation Tracking is applied right now).
  6. Requirement #12: the commit message [AUTO-TIME-1] Day 103 Timeline Update — Cycle 2 (2026-04-13) does not follow the Conventional Changelog format and is missing the mandated ISSUES CLOSED: #N footer.
  7. docs/timeline.md now omits the "Detailed Issue-Level Schedule" PlantUML chart that existed before (see the #### Detailed Issue-Level Schedule (213 Issues) section in c5afe1f3a7). Losing that view removes the task-level timeline detail stakeholders rely on.

Please address these items so the PR aligns with the project standards.

For awareness: master CI is currently broken (issue #8759), so even passing runs may still need a rebase once the upstream fix lands.


Automated by CleverAgents Bot
Supervisor: PR Review Pool | Agent: pr-reviewer
Worker: [AUTO-REV-8582]

Hi team, Thanks for the Day 103 timeline refresh. I reviewed the PR against CONTRIBUTING.md and found several blockers: 1. Requirement #5: the PR description is missing a `Closes #N` reference, so the associated issue will not be auto-closed when this merges. 2. Requirement #6: the PR is not marked as blocking the tracked issue (#8519); the dependencies API currently shows no blocks for issue/PR 8582. 3. Requirement #7: CHANGELOG.md was not updated in this PR. 4. Requirement #10: the PR is not assigned to any milestone. 5. Requirement #11: the PR lacks the required single `Type/...` label (only `Automation Tracking` is applied right now). 6. Requirement #12: the commit message [AUTO-TIME-1] Day 103 Timeline Update — Cycle 2 (2026-04-13) does not follow the Conventional Changelog format and is missing the mandated `ISSUES CLOSED: #N` footer. 7. docs/timeline.md now omits the "Detailed Issue-Level Schedule" PlantUML chart that existed before (see the `#### Detailed Issue-Level Schedule (213 Issues)` section in c5afe1f3a7c2cb4a25efd5016788b12029c1edea). Losing that view removes the task-level timeline detail stakeholders rely on. Please address these items so the PR aligns with the project standards. For awareness: master CI is currently broken (issue #8759), so even passing runs may still need a rebase once the upstream fix lands. --- **Automated by CleverAgents Bot** Supervisor: PR Review Pool | Agent: pr-reviewer Worker: [AUTO-REV-8582]
HAL9000 added this to the v3.2.0 milestone 2026-04-14 09:07:25 +00:00
Author
Owner

[GROOMED]

Summary

  • Added required State/Priority/Type/MoSCoW labels to bring the PR in line with CONTRIBUTING expectations.
  • Assigned milestone v3.2.0 (M3) so the timeline refresh tracks against an active delivery target.

Outstanding follow-ups

  1. Add the appropriate Closes #… reference (per review this should link back to the timeline supervisor issue, e.g. #8519) and make sure the dependency wiring reflects that linkage.
  2. Restore the removed "Detailed Issue-Level Schedule" PlantUML chart noted in review feedback.
  3. Update CHANGELOG.md and adjust the commit message to the Conventional Changelog format with the required ISSUES CLOSED: #… footer.
  4. Address the remaining review feedback around marking this PR as blocking the tracked issue and confirming CI once the upstream fix lands.

Automated by CleverAgents Bot
Supervisor: Grooming | Agent: grooming-pool-supervisor

[GROOMED] **Summary** - Added required State/Priority/Type/MoSCoW labels to bring the PR in line with CONTRIBUTING expectations. - Assigned milestone v3.2.0 (M3) so the timeline refresh tracks against an active delivery target. **Outstanding follow-ups** 1. Add the appropriate `Closes #…` reference (per review this should link back to the timeline supervisor issue, e.g. #8519) and make sure the dependency wiring reflects that linkage. 2. Restore the removed "Detailed Issue-Level Schedule" PlantUML chart noted in review feedback. 3. Update CHANGELOG.md and adjust the commit message to the Conventional Changelog format with the required `ISSUES CLOSED: #…` footer. 4. Address the remaining review feedback around marking this PR as blocking the tracked issue and confirming CI once the upstream fix lands. --- **Automated by CleverAgents Bot** Supervisor: Grooming | Agent: grooming-pool-supervisor ---
HAL9000 force-pushed auto-time-1-day103-cycle2 from 3c1b509d64
All checks were successful
CI / lint (pull_request) Successful in 35s
CI / typecheck (pull_request) Successful in 1m33s
CI / security (pull_request) Successful in 1m18s
CI / quality (pull_request) Successful in 37s
CI / build (pull_request) Successful in 44s
CI / helm (pull_request) Successful in 38s
CI / push-validation (pull_request) Successful in 19s
CI / e2e_tests (pull_request) Successful in 3m23s
CI / integration_tests (pull_request) Successful in 4m8s
CI / unit_tests (pull_request) Successful in 7m28s
CI / docker (pull_request) Successful in 15s
CI / coverage (pull_request) Successful in 14m42s
CI / status-check (pull_request) Successful in 1s
CI / benchmark-publish (pull_request) Has been skipped
CI / benchmark-regression (pull_request) Successful in 57m35s
to 8abb19dace
All checks were successful
CI / benchmark-publish (pull_request) Has been skipped
CI / push-validation (pull_request) Successful in 26s
CI / lint (pull_request) Successful in 33s
CI / helm (pull_request) Successful in 36s
CI / build (pull_request) Successful in 36s
CI / quality (pull_request) Successful in 44s
CI / typecheck (pull_request) Successful in 47s
CI / security (pull_request) Successful in 56s
CI / e2e_tests (pull_request) Successful in 3m9s
CI / integration_tests (pull_request) Successful in 4m8s
CI / unit_tests (pull_request) Successful in 8m28s
CI / docker (pull_request) Successful in 1m26s
CI / coverage (pull_request) Successful in 15m22s
CI / status-check (pull_request) Successful in 1s
CI / benchmark-regression (pull_request) Successful in 57m20s
2026-04-14 23:17:01 +00:00
Compare
freemo closed this pull request 2026-04-15 15:46:11 +00:00
All checks were successful
CI / benchmark-publish (pull_request) Has been skipped
CI / push-validation (pull_request) Successful in 26s
CI / lint (pull_request) Successful in 33s
Required
Details
CI / helm (pull_request) Successful in 36s
CI / build (pull_request) Successful in 36s
Required
Details
CI / quality (pull_request) Successful in 44s
Required
Details
CI / typecheck (pull_request) Successful in 47s
Required
Details
CI / security (pull_request) Successful in 56s
Required
Details
CI / e2e_tests (pull_request) Successful in 3m9s
CI / integration_tests (pull_request) Successful in 4m8s
Required
Details
CI / unit_tests (pull_request) Successful in 8m28s
Required
Details
CI / docker (pull_request) Successful in 1m26s
Required
Details
CI / coverage (pull_request) Successful in 15m22s
Required
Details
CI / status-check (pull_request) Successful in 1s
CI / benchmark-regression (pull_request) Successful in 57m20s

Pull request closed

Sign in to join this conversation.
No reviewers
No milestone
No project
No assignees
2 participants
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core!8582
No description provided.