[AUTO-TIME] Status: Timeline Update Pool Supervisor (Cycle 1) #8519

Closed
opened 2026-04-13 20:35:12 +00:00 by HAL9000 · 3 comments
Owner

Mission

Timeline Update Pool Supervisor — monitors project milestone progress and dispatches workers to update docs/timeline.md with current status, schedule adherence entries, and PlantUML Gantt chart updates.

Cycle 1 — Mon Apr 13, 2026 (Day 103)

Milestone Status Assessment

Milestone State Open Closed Completion Risk
v3.0.0 (M1) Closed 0 163 100% None
v3.1.0 (M2) ⚠️ Closed* 3 108 97.3% Low
v3.2.0 (M3) Open 776 269 25.7% CRITICAL
v3.3.0 (M4) Open 148 109 42.4% CRITICAL
v3.4.0 (M5) Open 233 139 37.4% HIGH
v3.5.0 (M6) Open 1032 210 16.9% CRITICAL
v3.6.0 (M7) Open 296 152 33.9% HIGH
v3.7.0 (M8) Open 548 427 43.8% HIGH
v3.8.0 (M9) Open 358 133 27.1% HIGH
v3.9.0 Open 17 4 19.0% LOW

*v3.1.0 closed but has 3 remaining open issues

Actions Taken

  • Dispatching AUTO-TIME-1 worker to update docs/timeline.md
  • Open PR #8380 (Day 103 Timeline Update) is mergeable but unmerged — worker will merge and create fresh update

Next Cycle

  • Cycle 2 in ~60 minutes

Automated by CleverAgents Bot
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor


Automated by CleverAgents Bot
Agent: automation-tracking-manager

## Mission Timeline Update Pool Supervisor — monitors project milestone progress and dispatches workers to update `docs/timeline.md` with current status, schedule adherence entries, and PlantUML Gantt chart updates. ## Cycle 1 — Mon Apr 13, 2026 (Day 103) ### Milestone Status Assessment | Milestone | State | Open | Closed | Completion | Risk | |-----------|-------|------|--------|------------|------| | v3.0.0 (M1) | ✅ Closed | 0 | 163 | 100% | None | | v3.1.0 (M2) | ⚠️ Closed* | 3 | 108 | 97.3% | Low | | v3.2.0 (M3) | ❌ Open | 776 | 269 | 25.7% | CRITICAL | | v3.3.0 (M4) | ❌ Open | 148 | 109 | 42.4% | CRITICAL | | v3.4.0 (M5) | ❌ Open | 233 | 139 | 37.4% | HIGH | | v3.5.0 (M6) | ❌ Open | 1032 | 210 | 16.9% | CRITICAL | | v3.6.0 (M7) | ❌ Open | 296 | 152 | 33.9% | HIGH | | v3.7.0 (M8) | ❌ Open | 548 | 427 | 43.8% | HIGH | | v3.8.0 (M9) | ❌ Open | 358 | 133 | 27.1% | HIGH | | v3.9.0 | ❌ Open | 17 | 4 | 19.0% | LOW | *v3.1.0 closed but has 3 remaining open issues ### Actions Taken - Dispatching AUTO-TIME-1 worker to update docs/timeline.md - Open PR #8380 (Day 103 Timeline Update) is mergeable but unmerged — worker will merge and create fresh update ### Next Cycle - Cycle 2 in ~60 minutes --- **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor --- **Automated by CleverAgents Bot** Agent: automation-tracking-manager
Author
Owner

Cycle 1 — Completion Report (Mon Apr 13, 2026 21:01 UTC)

Worker Results

Worker Branch PR Status
AUTO-TIME-1 auto-time-1-day103-cycle2 #8582 Complete

Timeline Update Summary

Content Added

  • PlantUML Gantt chart with today is 2026-04-13 and all 10 milestones
  • Schedule adherence table (23 entries, D12 through D103)
  • Milestone summaries for v3.0.0 through v3.9.0
  • Risk register (8 active risks)
  • Automation activity log

Next Cycle

  • Cycle 2 starts in ~60 minutes (~22:01 UTC)
  • Will check for milestone progress changes and dispatch AUTO-TIME-2

Automated by CleverAgents Bot
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor

## Cycle 1 — Completion Report (Mon Apr 13, 2026 21:01 UTC) ### Worker Results | Worker | Branch | PR | Status | |--------|--------|----|--------| | AUTO-TIME-1 | `auto-time-1-day103-cycle2` | #8582 | ✅ Complete | ### Timeline Update Summary - **File**: `docs/timeline.md` created/updated on branch `auto-time-1-day103-cycle2` - **PR**: [#8582 — [AUTO-TIME-1] Day 103 Timeline Update — Cycle 2](https://git.cleverthis.com/cleveragents/cleveragents-core/pulls/8582) - **Mergeable**: Yes - **Supersedes**: PR #8380 (Day 103 Timeline Update — Cycle 1 Session 6) ### Content Added - PlantUML Gantt chart with `today is 2026-04-13` and all 10 milestones - Schedule adherence table (23 entries, D12 through D103) - Milestone summaries for v3.0.0 through v3.9.0 - Risk register (8 active risks) - Automation activity log ### Next Cycle - Cycle 2 starts in ~60 minutes (~22:01 UTC) - Will check for milestone progress changes and dispatch AUTO-TIME-2 --- **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor
Author
Owner

Cycle 2 — Completion Report (Mon Apr 13, 2026 ~22:07 UTC)

Worker Results

Worker Branch PR Status
AUTO-TIME-2 auto-time-2-day103-cycle3 #8673 Complete

Milestone Changes Detected (Cycle 2 → Cycle 3, 60-min window)

CRITICAL ALERT: Scope expanding faster than closing!

Milestone Open C2 Open C3 Δ Open Closed C2 Closed C3 Δ Closed
v3.1.0 M2 3 5 +2 108 108 0
v3.2.0 M3 776 802 +26 269 269 0
v3.3.0 M4 148 157 +9 109 109 0
v3.4.0 M5 233 242 +9 139 139 0
v3.5.0 M6 1032 1052 +20 210 212 +2
v3.6.0 M7 296 314 +18 152 152 0
v3.7.0 M8 548 574 +26 427 427 0

Total: +110 new open issues in 60 min, only +2 closed

Timeline Update Summary

Next Cycle

  • Cycle 3 starts in ~60 minutes (~23:07 UTC)
  • Will check for further milestone changes and dispatch AUTO-TIME-3

Automated by CleverAgents Bot
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor

## Cycle 2 — Completion Report (Mon Apr 13, 2026 ~22:07 UTC) ### Worker Results | Worker | Branch | PR | Status | |--------|--------|----|--------| | AUTO-TIME-2 | `auto-time-2-day103-cycle3` | #8673 | ✅ Complete | ### Milestone Changes Detected (Cycle 2 → Cycle 3, 60-min window) **CRITICAL ALERT: Scope expanding faster than closing!** | Milestone | Open C2 | Open C3 | Δ Open | Closed C2 | Closed C3 | Δ Closed | |-----------|---------|---------|--------|-----------|-----------|---------| | v3.1.0 M2 | 3 | 5 | **+2** | 108 | 108 | 0 | | v3.2.0 M3 | 776 | 802 | **+26** | 269 | 269 | 0 | | v3.3.0 M4 | 148 | 157 | **+9** | 109 | 109 | 0 | | v3.4.0 M5 | 233 | 242 | **+9** | 139 | 139 | 0 | | v3.5.0 M6 | 1032 | 1052 | **+20** | 210 | 212 | +2 | | v3.6.0 M7 | 296 | 314 | **+18** | 152 | 152 | 0 | | v3.7.0 M8 | 548 | 574 | **+26** | 427 | 427 | 0 | **Total: +110 new open issues in 60 min, only +2 closed** ### Timeline Update Summary - **File**: `docs/timeline.md` updated on branch `auto-time-2-day103-cycle3` - **PR**: [#8673 — [AUTO-TIME-2] Day 103 Timeline Update — Cycle 3](https://git.cleverthis.com/cleveragents/cleveragents-core/pulls/8673) - **Mergeable**: Yes - **New sections**: Scope Expansion Alert, Cycle 3 schedule adherence entries ### Next Cycle - Cycle 3 starts in ~60 minutes (~23:07 UTC) - Will check for further milestone changes and dispatch AUTO-TIME-3 --- **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor
Author
Owner

Superseded by Cycle 4

Superseded by Cycle 4
Sign in to join this conversation.
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core#8519
No description provided.