[AUTO-TIME] Status: Timeline Update Pool Supervisor (Cycle 2) #8680

Closed
opened 2026-04-13 22:11:25 +00:00 by HAL9000 · 1 comment
Owner

Mission

Timeline Update Pool Supervisor — monitors project milestone progress and dispatches workers to update docs/timeline.md with current status, schedule adherence entries, and PlantUML Gantt chart updates.

Cycle 2 — Mon Apr 13, 2026 ~22:07 UTC (Day 103)

Milestone Status Assessment (Cycle 3 data)

Milestone State Open Closed Completion Risk
v3.0.0 (M1) Closed 0 163 100% None
v3.1.0 (M2) ⚠️ Closed* 5 108 94.7% ALERT
v3.2.0 (M3) Open 802 269 25.1% CRITICAL
v3.3.0 (M4) Open 157 109 41.0% CRITICAL
v3.4.0 (M5) Open 242 139 36.5% HIGH
v3.5.0 (M6) Open 1052 212 16.8% CRITICAL
v3.6.0 (M7) Open 314 152 32.6% HIGH
v3.7.0 (M8) Open 574 427 42.6% HIGH
v3.8.0 (M9) Open 358 133 27.1% HIGH
v3.9.0 Open 17 4 19.0% LOW

*v3.1.0 closed but scope expanding (was 3 open, now 5)

CRITICAL: Scope Expansion Alert

In the 60-minute window between Cycle 2 and Cycle 3:

  • +110 new open issues added across all milestones
  • Only +2 issues closed
  • All milestones gaining scope faster than being resolved

Actions Taken

  • Cycle 1: AUTO-TIME-1 dispatched → PR #8582 created (branch: auto-time-1-day103-cycle2)
  • Cycle 2: AUTO-TIME-2 dispatched → PR #8673 created (branch: auto-time-2-day103-cycle3)
  • Scope expansion alert added to timeline

Open PRs

  • PR #8380: Day 103 Timeline Update (Cycle 1 Session 6) — superseded
  • PR #8582: Day 103 Timeline Update — Cycle 2 — open, mergeable
  • PR #8673: Day 103 Timeline Update — Cycle 3 (Scope Expansion Alert) — open, mergeable

Next Cycle

  • Cycle 3 starts in ~60 minutes (~23:07 UTC)
  • Will dispatch AUTO-TIME-3

Automated by CleverAgents Bot
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor

## Mission Timeline Update Pool Supervisor — monitors project milestone progress and dispatches workers to update `docs/timeline.md` with current status, schedule adherence entries, and PlantUML Gantt chart updates. ## Cycle 2 — Mon Apr 13, 2026 ~22:07 UTC (Day 103) ### Milestone Status Assessment (Cycle 3 data) | Milestone | State | Open | Closed | Completion | Risk | |-----------|-------|------|--------|------------|------| | v3.0.0 (M1) | ✅ Closed | 0 | 163 | 100% | None | | v3.1.0 (M2) | ⚠️ Closed* | 5 | 108 | 94.7% | ALERT | | v3.2.0 (M3) | ❌ Open | 802 | 269 | 25.1% | CRITICAL | | v3.3.0 (M4) | ❌ Open | 157 | 109 | 41.0% | CRITICAL | | v3.4.0 (M5) | ❌ Open | 242 | 139 | 36.5% | HIGH | | v3.5.0 (M6) | ❌ Open | 1052 | 212 | 16.8% | CRITICAL | | v3.6.0 (M7) | ❌ Open | 314 | 152 | 32.6% | HIGH | | v3.7.0 (M8) | ❌ Open | 574 | 427 | 42.6% | HIGH | | v3.8.0 (M9) | ❌ Open | 358 | 133 | 27.1% | HIGH | | v3.9.0 | ❌ Open | 17 | 4 | 19.0% | LOW | *v3.1.0 closed but scope expanding (was 3 open, now 5) ### CRITICAL: Scope Expansion Alert In the 60-minute window between Cycle 2 and Cycle 3: - **+110 new open issues** added across all milestones - **Only +2 issues closed** - All milestones gaining scope faster than being resolved ### Actions Taken - Cycle 1: AUTO-TIME-1 dispatched → PR #8582 created (branch: auto-time-1-day103-cycle2) - Cycle 2: AUTO-TIME-2 dispatched → PR #8673 created (branch: auto-time-2-day103-cycle3) - Scope expansion alert added to timeline ### Open PRs - PR #8380: Day 103 Timeline Update (Cycle 1 Session 6) — superseded - PR #8582: Day 103 Timeline Update — Cycle 2 — open, mergeable - PR #8673: Day 103 Timeline Update — Cycle 3 (Scope Expansion Alert) — open, mergeable ### Next Cycle - Cycle 3 starts in ~60 minutes (~23:07 UTC) - Will dispatch AUTO-TIME-3 --- **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor
Author
Owner

Superseded by the next AUTO-TIME tracking cycle for the Day 104 timeline update. Closing this status issue in favor of the new cycle.

Automated by CleverAgents Bot
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor

Superseded by the next AUTO-TIME tracking cycle for the Day 104 timeline update. Closing this status issue in favor of the new cycle. --- **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor
Sign in to join this conversation.
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core#8680
No description provided.