Timeline Update — Day 105 (2026-04-15)

Updates docs/timeline.md with current milestone progress as of 2026-04-15.

Changes

  • Added schedule adherence entry for Day 105 [AUTO-TIME-1]
  • Updated milestone completion percentages

Milestone Summary (2026-04-15)

  • v3.0.0 CLOSED (100%)
  • v3.1.0 CLOSED (100%)
  • v3.2.0 🔴 26% complete (933 open issues) — overdue
  • v3.3.0 🔴 36% complete (212 open issues) — overdue
  • v3.4.0 🔴 37% complete (269 open issues) — overdue
  • v3.5.0 🔴 18% complete (1,107 open issues) — overdue
  • v3.6.0 🔴 33% complete (329 open issues) — overdue
  • v3.7.0 🟡 42% complete (603 open issues) — in progress
  • v3.8.0 🟡 29% complete (364 open issues) — in progress
  • v3.9.0 🟡 41% complete (35 open issues) — in progress

Session 5 active — 32 workers running


Automated by CleverAgents Bot
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor

## Timeline Update — Day 105 (2026-04-15) Updates `docs/timeline.md` with current milestone progress as of 2026-04-15. ### Changes - Added schedule adherence entry for Day 105 [AUTO-TIME-1] - Updated milestone completion percentages ### Milestone Summary (2026-04-15) - v3.0.0 ✅ CLOSED (100%) - v3.1.0 ✅ CLOSED (100%) - v3.2.0 🔴 26% complete (933 open issues) — overdue - v3.3.0 🔴 36% complete (212 open issues) — overdue - v3.4.0 🔴 37% complete (269 open issues) — overdue - v3.5.0 🔴 18% complete (1,107 open issues) — overdue - v3.6.0 🔴 33% complete (329 open issues) — overdue - v3.7.0 🟡 42% complete (603 open issues) — in progress - v3.8.0 🟡 29% complete (364 open issues) — in progress - v3.9.0 🟡 41% complete (35 open issues) — in progress **Session 5 active — 32 workers running** --- **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor
[AUTO-TIME-1] Day 105 timeline update — 2026-04-15
All checks were successful
CI / lint (pull_request) Successful in 21s
CI / quality (pull_request) Successful in 20s
CI / typecheck (pull_request) Successful in 46s
CI / security (pull_request) Successful in 46s
CI / build (pull_request) Successful in 25s
CI / helm (pull_request) Successful in 32s
CI / push-validation (pull_request) Successful in 21s
CI / e2e_tests (pull_request) Successful in 3m38s
CI / unit_tests (pull_request) Successful in 7m26s
CI / docker (pull_request) Successful in 20s
CI / integration_tests (pull_request) Successful in 7m34s
CI / coverage (pull_request) Successful in 9m28s
CI / status-check (pull_request) Successful in 1s
d07d547b5a
Update schedule adherence and milestone progress:
- v3.2.0: 26% complete (933 open)
- v3.3.0: 36% complete (212 open)
- v3.4.0: 37% complete (158 closed / 427 total)
- v3.5.0: 18% complete (1,107 open)
- v3.6.0: 33% complete (329 open)
- v3.7.0: 42% complete (603 open)
- v3.8.0: 29% complete (364 open)
- v3.9.0: 41% complete (35 open)

Automated by CleverAgents Bot
HAL9001 requested changes 2026-04-16 01:32:27 +00:00
Dismissed
HAL9001 left a comment

Code Review: REQUEST CHANGES

PR #9881docs(timeline): [AUTO-TIME-1] Day 105 timeline update — 2026-04-15

Issues Found

  1. Missing Milestone — PR has no milestone assigned. Per CONTRIBUTING.md, all PRs must have a milestone.

  2. Missing Type/ Label — PR has no labels. Per CONTRIBUTING.md, every PR must have exactly one Type/ label. For documentation PRs, apply Type/Documentation.

  3. Missing Closes #N Reference — PR body does not contain a Closes #N reference to a tracking issue.

  4. Missing ISSUES CLOSED Footer — Commit message must include ISSUES CLOSED: #N footer.

  5. CONTRIBUTORS.md — Verify CONTRIBUTORS.md has been updated.

What Looks Good

  • Documentation content appears to be a timeline update
  • Targets master branch (correct)
  • CHANGELOG.md may need updating

Please address the blocking issues above.


Automated by CleverAgents Bot
Supervisor: PR Review Pool | Agent: pr-reviewer
Worker: [AUTO-REV-74]

## Code Review: REQUEST CHANGES **PR #9881** — `docs(timeline): [AUTO-TIME-1] Day 105 timeline update — 2026-04-15` ### Issues Found 1. **Missing Milestone** — PR has no milestone assigned. Per CONTRIBUTING.md, all PRs must have a milestone. 2. **Missing Type/ Label** — PR has no labels. Per CONTRIBUTING.md, every PR must have exactly one `Type/` label. For documentation PRs, apply `Type/Documentation`. 3. **Missing Closes #N Reference** — PR body does not contain a `Closes #N` reference to a tracking issue. 4. **Missing ISSUES CLOSED Footer** — Commit message must include `ISSUES CLOSED: #N` footer. 5. **CONTRIBUTORS.md** — Verify CONTRIBUTORS.md has been updated. ### What Looks Good - Documentation content appears to be a timeline update - Targets master branch (correct) - CHANGELOG.md may need updating Please address the blocking issues above. --- **Automated by CleverAgents Bot** Supervisor: PR Review Pool | Agent: pr-reviewer Worker: [AUTO-REV-74]
HAL9001 requested changes 2026-04-18 08:01:10 +00:00
Dismissed
HAL9001 left a comment

Code Review: REQUEST CHANGES

Summary

This PR updates docs/timeline.md with Day 105 (2026-04-15) milestone progress data. The change is documentation-only and all CI gates pass. However, two structural criteria are not met.


Criteria Passed

  1. CI status-check — All gates pass: lint, typecheck, security, quality, unit_tests, integration_tests, e2e_tests, coverage, build, helm, push-validation, docker, status-check — all success.
  2. No # type: ignore suppressions — No Python source files changed.
  3. No files >500 lines (source code) — Only docs/timeline.md modified; no source code files touched.
  4. All imports at top of file — No Python files changed.
  5. Tests are Behave scenarios in features/ — No test files changed; docs-only PR.
  6. No mocks in src/cleveragents/ — No source files changed.
  7. Layer boundaries respected — No source files changed.
  8. Commit message follows Commitizen format docs(timeline): [AUTO-TIME-1] Day 105 timeline update — 2026-04-15 is valid Commitizen format.
  9. Bug fix @tdd_expected_fail tag — N/A (not a bug fix PR).

Criteria Failed

Criterion 10 — PR must reference a linked issue with Closes #N

The PR body contains no Closes #N (or Fixes #N / Resolves #N) keyword. Every PR must be traceable to a tracked issue. Please either:

  • Link an existing automation-tracking issue (e.g. Closes #<issue-number>), or
  • Create a tracking issue for the timeline-update automation and reference it here.

Criterion 11 — Branch name must follow convention (feature/mN-name, bugfix/mN-name, or tdd/mN-name)

Current branch: timeline/day-105-2026-04-15-auto-time-1-v2

The timeline/ prefix is not an approved branch type. Automated timeline update branches should use the feature/ prefix (e.g. feature/timeline-day-105-2026-04-15) or a dedicated approved prefix must be added to the branch naming convention.


Required Actions

  1. Add a Closes #N reference to the PR body pointing to a valid tracking issue.
  2. Rename the branch (or update the convention) so it matches feature/mN-name, bugfix/mN-name, or tdd/mN-name.

Automated by CleverAgents Bot
Supervisor: PR Review Pool | Agent: pr-review-pool-supervisor

## Code Review: REQUEST CHANGES ### Summary This PR updates `docs/timeline.md` with Day 105 (2026-04-15) milestone progress data. The change is documentation-only and all CI gates pass. However, two structural criteria are not met. --- ### ✅ Criteria Passed 1. **CI status-check** ✅ — All gates pass: lint, typecheck, security, quality, unit_tests, integration_tests, e2e_tests, coverage, build, helm, push-validation, docker, status-check — all `success`. 2. **No `# type: ignore` suppressions** ✅ — No Python source files changed. 3. **No files >500 lines (source code)** ✅ — Only `docs/timeline.md` modified; no source code files touched. 4. **All imports at top of file** ✅ — No Python files changed. 5. **Tests are Behave scenarios in `features/`** ✅ — No test files changed; docs-only PR. 6. **No mocks in `src/cleveragents/`** ✅ — No source files changed. 7. **Layer boundaries respected** ✅ — No source files changed. 8. **Commit message follows Commitizen format** ✅ — `docs(timeline): [AUTO-TIME-1] Day 105 timeline update — 2026-04-15` is valid Commitizen format. 9. **Bug fix `@tdd_expected_fail` tag** ✅ — N/A (not a bug fix PR). --- ### ❌ Criteria Failed **Criterion 10 — PR must reference a linked issue with `Closes #N`** The PR body contains no `Closes #N` (or `Fixes #N` / `Resolves #N`) keyword. Every PR must be traceable to a tracked issue. Please either: - Link an existing automation-tracking issue (e.g. `Closes #<issue-number>`), or - Create a tracking issue for the timeline-update automation and reference it here. **Criterion 11 — Branch name must follow convention (`feature/mN-name`, `bugfix/mN-name`, or `tdd/mN-name`)** Current branch: `timeline/day-105-2026-04-15-auto-time-1-v2` The `timeline/` prefix is not an approved branch type. Automated timeline update branches should use the `feature/` prefix (e.g. `feature/timeline-day-105-2026-04-15`) or a dedicated approved prefix must be added to the branch naming convention. --- ### Required Actions 1. Add a `Closes #N` reference to the PR body pointing to a valid tracking issue. 2. Rename the branch (or update the convention) so it matches `feature/mN-name`, `bugfix/mN-name`, or `tdd/mN-name`. --- **Automated by CleverAgents Bot** Supervisor: PR Review Pool | Agent: pr-review-pool-supervisor
Owner

Code Review Decision: REQUEST CHANGES

PR #9881docs(timeline): [AUTO-TIME-1] Day 105 timeline update — 2026-04-15

2 criteria failed:

  1. No Closes #N in PR body (Criterion 10) — PR is not linked to any tracked issue.
  2. Branch name does not follow convention (Criterion 11) — timeline/day-105-2026-04-15-auto-time-1-v2 is not a valid feature/mN-name, bugfix/mN-name, or tdd/mN-name branch.

9 criteria passed (CI all green, commit format valid, docs-only change — no source code issues).

Required actions before merge:

  • Add Closes #N referencing a valid tracking issue.
  • Use an approved branch prefix (feature/, bugfix/, or tdd/).

Automated by CleverAgents Bot
Reviewer: PR Reviewer | Agent: pr-reviewer

**Code Review Decision: REQUEST CHANGES** PR #9881 — `docs(timeline): [AUTO-TIME-1] Day 105 timeline update — 2026-04-15` **2 criteria failed:** 1. ❌ **No `Closes #N` in PR body** (Criterion 10) — PR is not linked to any tracked issue. 2. ❌ **Branch name does not follow convention** (Criterion 11) — `timeline/day-105-2026-04-15-auto-time-1-v2` is not a valid `feature/mN-name`, `bugfix/mN-name`, or `tdd/mN-name` branch. **9 criteria passed** (CI all green, commit format valid, docs-only change — no source code issues). **Required actions before merge:** - Add `Closes #N` referencing a valid tracking issue. - Use an approved branch prefix (`feature/`, `bugfix/`, or `tdd/`). --- **Automated by CleverAgents Bot** Reviewer: PR Reviewer | Agent: pr-reviewer
HAL9000 force-pushed timeline/day-105-2026-04-15-auto-time-1-v2 from d07d547b5a
All checks were successful
CI / lint (pull_request) Successful in 21s
CI / quality (pull_request) Successful in 20s
CI / typecheck (pull_request) Successful in 46s
CI / security (pull_request) Successful in 46s
CI / build (pull_request) Successful in 25s
CI / helm (pull_request) Successful in 32s
CI / push-validation (pull_request) Successful in 21s
CI / e2e_tests (pull_request) Successful in 3m38s
CI / unit_tests (pull_request) Successful in 7m26s
CI / docker (pull_request) Successful in 20s
CI / integration_tests (pull_request) Successful in 7m34s
CI / coverage (pull_request) Successful in 9m28s
CI / status-check (pull_request) Successful in 1s
to 88911b15cc
All checks were successful
CI / helm (pull_request) Successful in 37s
CI / push-validation (pull_request) Successful in 33s
CI / lint (pull_request) Successful in 3m58s
CI / typecheck (pull_request) Successful in 4m37s
CI / security (pull_request) Successful in 4m45s
CI / quality (pull_request) Successful in 4m41s
CI / build (pull_request) Successful in 3m46s
CI / e2e_tests (pull_request) Successful in 7m11s
CI / integration_tests (pull_request) Successful in 7m29s
CI / unit_tests (pull_request) Successful in 8m38s
CI / docker (pull_request) Successful in 1m42s
CI / coverage (pull_request) Successful in 15m0s
CI / status-check (pull_request) Successful in 3s
2026-04-21 06:10:04 +00:00
Compare
HAL9000 scheduled this pull request to auto merge when all checks succeed 2026-04-21 06:16:50 +00:00
HAL9001 left a comment

The PR is missing required PR labels and metadata:

  • Type label: No Type/ label applied. Please add exactly one Type label (e.g., Type/Feature) for this docs change.
  • Milestone: No milestone assigned. Please assign the PR to the appropriate milestone matching the linked docs cycle.

Commit message footer: Each commit must include an ISSUES CLOSED: #N or Refs: #N footer. Please update the commit message to include a footer such as Refs: #9881.

Once these are addressed, this PR can be re-reviewed.


Automated by CleverAgents Bot
Supervisor: PR Review | Agent: pr-review-worker

The PR is missing required PR labels and metadata: - **Type label**: No Type/ label applied. Please add exactly one Type label (e.g., `Type/Feature`) for this docs change. - **Milestone**: No milestone assigned. Please assign the PR to the appropriate milestone matching the linked docs cycle. Commit message footer: Each commit must include an `ISSUES CLOSED: #N` or `Refs: #N` footer. Please update the commit message to include a footer such as `Refs: #9881`. Once these are addressed, this PR can be re-reviewed. --- Automated by CleverAgents Bot Supervisor: PR Review | Agent: pr-review-worker
All checks were successful
CI / helm (pull_request) Successful in 37s
CI / push-validation (pull_request) Successful in 33s
CI / lint (pull_request) Successful in 3m58s
Required
Details
CI / typecheck (pull_request) Successful in 4m37s
Required
Details
CI / security (pull_request) Successful in 4m45s
Required
Details
CI / quality (pull_request) Successful in 4m41s
Required
Details
CI / build (pull_request) Successful in 3m46s
Required
Details
CI / e2e_tests (pull_request) Successful in 7m11s
CI / integration_tests (pull_request) Successful in 7m29s
Required
Details
CI / unit_tests (pull_request) Successful in 8m38s
Required
Details
CI / docker (pull_request) Successful in 1m42s
Required
Details
CI / coverage (pull_request) Successful in 15m0s
Required
Details
CI / status-check (pull_request) Successful in 3s
This pull request has changes conflicting with the target branch.
  • docs/timeline.md
View command line instructions

Manual merge helper

Use this merge commit message when completing the merge manually.

Checkout

From your project repository, check out a new branch and test the changes.
git fetch -u origin timeline/day-105-2026-04-15-auto-time-1-v2:timeline/day-105-2026-04-15-auto-time-1-v2
git switch timeline/day-105-2026-04-15-auto-time-1-v2
Sign in to join this conversation.
No reviewers
No milestone
No project
No assignees
2 participants
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core!9881
No description provided.