docs(timeline): update schedule adherence Day 104 (2026-04-14) #9077

Closed
HAL9000 wants to merge 2 commits from docs/timeline-day-104-auto-time-1 into master
2 changed files with 97 additions and 1 deletions
+2 -1
View File
@@ -91,7 +91,7 @@ Each cycle:
4. **Monitor workers.** Count active workers, check for stuck sessions.
5. **Update tracking.** Every 3 cycles, create a status tracking issue via `automation-tracking-manager` with prefix `AUTO-BUG-POOL`.
5. **Update tracking (non-blocking).** Every 3 cycles, attempt to create a status tracking issue via `automation-tracking-manager` with prefix `AUTO-BUG-POOL`. This step is **best-effort** — if the call does not complete within a reasonable time or fails, skip it and continue to the next cycle. **Never block the main loop waiting for tracking.** Tracking is informational only; the supervisor's core function (module scanning and worker dispatch) must continue regardless.
## Finding Validation Gate
@@ -126,3 +126,4 @@ Supervisor: Bug Hunt Pool | Agent: bug-hunt-pool-supervisor
7. **Apply labels via `forgejo-label-manager`.** Never apply labels directly or using the Forgejo MCP/task. All label operations must go through `forgejo-label-manager`.
8. **Exhaustive pagination for all list results.** Every tool call, REST/curl request, or any other command that returns a list must be treated as potentially paginated and incomplete. Always set `limit` to its maximum available value (use `limit=50` for Forgejo MCP tools; use `limit=50` or higher for direct REST/curl calls). After each list response, check whether the number of returned items equals the page size — if so, there are likely more results; fetch the next page (`page=2`, `page=3`, …) and continue until receiving a partial page. Never assume the first response is the complete result. This rule applies to every list-returning call without exception. *Examples specific to this agent (not exhaustive):* `forgejo_list_repo_issues` (default 20 — use `limit=50` and paginate to check for all existing bug issues before filing duplicates); `forgejo_list_repo_pull_requests` (same — check all open PRs that may already address a discovered bug).
9. **Tracking is non-blocking.** The `automation-tracking-manager` call in step 5 must never block the main loop. If it hangs or fails, skip it and proceed. Core functionality (module mapping, worker dispatch, monitoring) takes priority over status reporting.
+95
View File
@@ -5316,3 +5316,98 @@ Story points per developer per milestone.
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
### 2026-04-14 (Day 104)
**Summary**
Status: Behind 35+d
Deadline risk: CRITICAL
**Notes**
- Day 104 update (2026-04-14). AUTO-TIME cycle 1 — [AUTO-TIME-1]. Fresh start for timeline-update-pool-supervisor. Session 4 remains active.
- Continued scope expansion across ALL milestones since Day 100: M3 grew 770→1112 (+342), M4 grew 220→280 (+60), M5 grew 313→382 (+69), M6 grew 1085→1301 (+216), M7 grew 400→488 (+88), M8 grew 944→1027 (+83), M9 grew 475→507 (+32). New milestone v3.9.0 appeared (36 total issues, 4 closed, 11.1%).
- Milestone completions (Day 104): M3 24.2% (269/1112, was 32% at Day 100 — scope explosion +342 issues), M4 39.6% (111/280, was 49%), M5 36.6% (140/382, was 43%), M6 16.6% (216/1301, was 18%), M7 31.4% (153/488, was 38%), M8 41.7% (428/1027, was 45%), M9 26.2% (133/507, was 28%).
- Apparent completion percentages dropped across all milestones due to massive scope expansion by agent-driven issue creation. Absolute closed issue counts increased slightly (M3: +20, M4: +3, M5: +7, M6: +19, M7: +3, M8: +3, M9: +2).
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines. v3.9.0 is a new milestone with no deadline.
- Overall project: ~32% complete across active milestones (v3.2.0v3.9.0).
- PR #9024 (docs/timeline-day-104 branch) is open and awaiting merge — contains a parallel Day 104 entry from a previous AUTO-TIME session.
#### Milestone forecast
| Milestone | Target -> ETA | Delta | Risk |
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-07-01 | +126d | CRITICAL — 843 open issues; 24.2% complete (scope expanded 770→1112) |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-06-01 | +91d | CRITICAL — 169 open issues; 39.6% complete (scope expanded 220→280) |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-06-15 | +101d | HIGH — 242 open issues; 36.6% complete (scope expanded 313→382) |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-09-01 | +175d | CRITICAL — 1085 open issues; 16.6% complete (scope expanded 1085→1301) |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-07-15 | +109d | HIGH — 335 open issues; 31.4% complete (scope expanded 400→488) |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-08-01 | N/A | HIGH — 599 open issues; 41.7% complete (scope expanded 944→1027) |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-09-01 | N/A | MEDIUM — 374 open issues; 26.2% complete (scope expanded 475→507) |
| v3.9.0 | (no deadline) -> ETA TBD | N/A | LOW — 32 open issues; 11.1% complete (new milestone) |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-06-15 | HIGH | 242 open issues in v3.4.0; scope expanded +69 issues since Day 100 |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-06-01 | CRITICAL | 169 open issues in v3.3.0; scope expanded +60 issues since Day 100 |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-07-01 | CRITICAL | 843 open issues in v3.2.0; scope expanded +342 issues since Day 100 |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | Scope explosion across all milestones; agent-driven issue creation at high velocity |
| Track T (Testing) | Active | Ongoing | HIGH | All milestones overdue; massive open issue backlogs; Session 4 active |
#### Developer forecast
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|------|-------------------|--------------|------|-------|
| Jeff | -35d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight |
| Luis | -35d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool |
| Hamza | -35d behind | active | HIGH | Resource DAG; v3.6.0 features; PR reviews |
| Aditya | -35d behind | active | HIGH | M5 features; TDD counterparts; domain model work |
| Brent | -35d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation |
| Rui | -35d behind | active | HIGH | TUI features; UAT bug fixes; E2E testing |
| Mike/Brian | N/A | standby | LOW | Infrastructure support |
#### Task inventory
Milestone per developer as of Day 104 (2026-04-14).
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 843 open | 269/1112 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 169 open | 111/280 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 242 open | 140/382 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 1085 open | 216/1301 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 335 open | 153/488 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 599 open | 428/1027 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 374 open | 133/507 |
| v3.9.0 | N/A | N/A | N/A | N/A | N/A | N/A | 32 open | 4/36 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~3479 open** | **1857/5305 closed** |
Note: "done/total" = closed/total for that milestone. Assignee data not broken down by developer (all unassigned in API). Agent-driven issue creation continues at high velocity. Scope expanded massively since Day 100 across all milestones.
#### Story point allocation
Story points per developer per milestone.
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~172 SP |
| M2 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~208 SP |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~104 SP |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~126 SP |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~129 SP |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~100 SP |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| v3.9.0 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |