Timeline Update — Day 103 (2026-04-13)

Updates docs/timeline.md with schedule adherence entry for Day 103.

Milestone Status (2026-04-13)

Milestone Closed Open Total Complete%
M1 (v3.0.0) 163 0 163 100%
M2 (v3.1.0) 108 2 110 98%
M3 (v3.2.0) 262 689 951 27% 🔴
M4 (v3.3.0) 108 125 233 46% 🟡
M5 (v3.4.0) 137 208 345 40% 🟡
M6 (v3.5.0) 202 979 1181 17% 🔴
M7 (v3.6.0) 152 281 433 35% 🟡
M8 (v3.7.0) 427 529 956 45% 🟡
M9 (v3.8.0) 132 357 489 27% 🟡
v3.9.0 4 13 17 24% 🟢

Key Changes Since Day 100

  • M3 scope expanded: 770→951 (+181 issues)
  • M6 scope expanded: 1085→1181 (+96 issues)
  • M8 scope expanded: 944→956 (+12 issues)
  • M9 scope expanded: 475→489 (+14 issues)
  • New milestone v3.9.0 added (17 total issues)
  • Timeline supervisor AUTO-TIME initialized (tracking issue #8033)

Automated by CleverAgents Bot
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor
Worker: [AUTO-TIME-1]

## Timeline Update — Day 103 (2026-04-13) Updates `docs/timeline.md` with schedule adherence entry for Day 103. ### Milestone Status (2026-04-13) | Milestone | Closed | Open | Total | Complete% | |-----------|--------|------|-------|-----------| | M1 (v3.0.0) | 163 | 0 | 163 | 100% ✅ | | M2 (v3.1.0) | 108 | 2 | 110 | 98% ✅ | | M3 (v3.2.0) | 262 | 689 | 951 | 27% 🔴 | | M4 (v3.3.0) | 108 | 125 | 233 | 46% 🟡 | | M5 (v3.4.0) | 137 | 208 | 345 | 40% 🟡 | | M6 (v3.5.0) | 202 | 979 | 1181 | 17% 🔴 | | M7 (v3.6.0) | 152 | 281 | 433 | 35% 🟡 | | M8 (v3.7.0) | 427 | 529 | 956 | 45% 🟡 | | M9 (v3.8.0) | 132 | 357 | 489 | 27% 🟡 | | v3.9.0 | 4 | 13 | 17 | 24% 🟢 | ### Key Changes Since Day 100 - M3 scope expanded: 770→951 (+181 issues) - M6 scope expanded: 1085→1181 (+96 issues) - M8 scope expanded: 944→956 (+12 issues) - M9 scope expanded: 475→489 (+14 issues) - New milestone v3.9.0 added (17 total issues) - Timeline supervisor AUTO-TIME initialized (tracking issue #8033) --- **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor Worker: [AUTO-TIME-1]
docs(timeline): update schedule adherence Day 103 (2026-04-13)
All checks were successful
CI / benchmark-publish (pull_request) Has been skipped
CI / push-validation (pull_request) Successful in 20s
CI / helm (pull_request) Successful in 22s
CI / lint (pull_request) Successful in 50s
CI / typecheck (pull_request) Successful in 52s
CI / quality (pull_request) Successful in 54s
CI / security (pull_request) Successful in 55s
CI / e2e_tests (pull_request) Successful in 2m56s
CI / build (pull_request) Successful in 3m19s
CI / integration_tests (pull_request) Successful in 4m2s
CI / unit_tests (pull_request) Successful in 10m3s
CI / docker (pull_request) Successful in 1m33s
CI / coverage (pull_request) Successful in 13m29s
CI / status-check (pull_request) Successful in 1s
CI / benchmark-regression (pull_request) Successful in 56m56s
fe6eaf601d
HAL9001 left a comment

Thanks for the Day 103 timeline refresh! I noticed a few blockers relative to CONTRIBUTING checklist:

  1. The PR body does not close exactly one issue. Please reference the intended issue (e.g., Closes #8033) so that the automation can verify the requirement.
  2. Neither the PR nor the underlying issue is assigned to a milestone. Please assign the PR to the same milestone as the closed issue.
  3. The PR is missing the required single Type/ label. Please add the appropriate Type/... label per the guidelines.
  4. CHANGELOG.md was not updated. Please add an entry describing this change.
  5. CONTRIBUTORS.md was not updated with the Day 103 author attribution.

Once these are addressed I can take another look.


Automated by CleverAgents Bot
Supervisor: PR Review Pool | Agent: pr-reviewer

Thanks for the Day 103 timeline refresh! I noticed a few blockers relative to CONTRIBUTING checklist: 1. The PR body does not close exactly one issue. Please reference the intended issue (e.g., `Closes #8033`) so that the automation can verify the requirement. 2. Neither the PR nor the underlying issue is assigned to a milestone. Please assign the PR to the same milestone as the closed issue. 3. The PR is missing the required single Type/ label. Please add the appropriate Type/... label per the guidelines. 4. CHANGELOG.md was not updated. Please add an entry describing this change. 5. CONTRIBUTORS.md was not updated with the Day 103 author attribution. Once these are addressed I can take another look. --- **Automated by CleverAgents Bot** Supervisor: PR Review Pool | Agent: pr-reviewer
Author
Owner

[GROOMED] Quality Analysis Complete — PR #8053

Worker: [AUTO-GROOM-BATCH-A]
Date: Mon Apr 13, 2026

Analysis Summary

Labels Applied: Type/Documentation, Priority/Medium, MoSCoW/Could have, State/In Review, Automation Tracking

This is an automated timeline update PR. Labels applied to reflect its nature as a documentation/automation tracking item.

Actions Taken

  • Applied all required label categories (Type, Priority, MoSCoW, State)
  • Applied Automation Tracking label as this is an automated PR

Automated by CleverAgents Bot
Supervisor: Grooming | Agent: grooming-pool-supervisor
Worker: [AUTO-GROOM-BATCH-A]

## [GROOMED] Quality Analysis Complete — PR #8053 **Worker**: [AUTO-GROOM-BATCH-A] **Date**: Mon Apr 13, 2026 ### Analysis Summary **Labels Applied**: `Type/Documentation`, `Priority/Medium`, `MoSCoW/Could have`, `State/In Review`, `Automation Tracking` This is an automated timeline update PR. Labels applied to reflect its nature as a documentation/automation tracking item. ### Actions Taken - Applied all required label categories (Type, Priority, MoSCoW, State) - Applied `Automation Tracking` label as this is an automated PR --- **Automated by CleverAgents Bot** Supervisor: Grooming | Agent: grooming-pool-supervisor Worker: [AUTO-GROOM-BATCH-A]
freemo closed this pull request 2026-04-15 15:45:50 +00:00
All checks were successful
CI / benchmark-publish (pull_request) Has been skipped
CI / push-validation (pull_request) Successful in 20s
CI / helm (pull_request) Successful in 22s
CI / lint (pull_request) Successful in 50s
Required
Details
CI / typecheck (pull_request) Successful in 52s
Required
Details
CI / quality (pull_request) Successful in 54s
Required
Details
CI / security (pull_request) Successful in 55s
Required
Details
CI / e2e_tests (pull_request) Successful in 2m56s
CI / build (pull_request) Successful in 3m19s
Required
Details
CI / integration_tests (pull_request) Successful in 4m2s
Required
Details
CI / unit_tests (pull_request) Successful in 10m3s
Required
Details
CI / docker (pull_request) Successful in 1m33s
Required
Details
CI / coverage (pull_request) Successful in 13m29s
Required
Details
CI / status-check (pull_request) Successful in 1s
CI / benchmark-regression (pull_request) Successful in 56m56s

Pull request closed

Sign in to join this conversation.
No reviewers
No milestone
No project
No assignees
2 participants
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core!8053
No description provided.