[AUTO-TIME] Status: Timeline Update Pool Supervisor — Session Start (Cycle 1) #8033

Closed
opened 2026-04-13 00:54:28 +00:00 by HAL9000 · 2 comments
Owner

Session started: 2026-04-13 (Day 103)
Worker tag: AUTO-TIME-1
Repository: cleveragents/cleveragents-core
Last timeline update: Day 100 (2026-04-10) in master branch

Current milestone status:

  • M1 (v3.0.0): COMPLETE (163 closed, 0 open)
  • M2 (v3.1.0): COMPLETE (108 closed, 2 open)
  • M3 (v3.2.0): OPEN — 262 closed, 689 open (27% complete)
  • M4 (v3.3.0): OPEN — 108 closed, 125 open (46% complete)
  • M5 (v3.4.0): OPEN — 137 closed, 208 open (40% complete)
  • M6 (v3.5.0): OPEN — 202 closed, 979 open (17% complete)
  • M7 (v3.6.0): OPEN — 152 closed, 281 open (35% complete)
  • M8 (v3.7.0): OPEN — 427 closed, 529 open (45% complete)
  • M9 (v3.8.0): OPEN — 132 closed, 357 open (27% complete)
  • v3.9.0: OPEN — 4 closed, 13 open (24% complete)

Plan: Update timeline every 60 minutes


Automated by CleverAgents Bot
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor

Session started: 2026-04-13 (Day 103) Worker tag: AUTO-TIME-1 Repository: cleveragents/cleveragents-core Last timeline update: Day 100 (2026-04-10) in master branch Current milestone status: - M1 (v3.0.0): COMPLETE (163 closed, 0 open) - M2 (v3.1.0): COMPLETE (108 closed, 2 open) - M3 (v3.2.0): OPEN — 262 closed, 689 open (27% complete) - M4 (v3.3.0): OPEN — 108 closed, 125 open (46% complete) - M5 (v3.4.0): OPEN — 137 closed, 208 open (40% complete) - M6 (v3.5.0): OPEN — 202 closed, 979 open (17% complete) - M7 (v3.6.0): OPEN — 152 closed, 281 open (35% complete) - M8 (v3.7.0): OPEN — 427 closed, 529 open (45% complete) - M9 (v3.8.0): OPEN — 132 closed, 357 open (27% complete) - v3.9.0: OPEN — 4 closed, 13 open (24% complete) Plan: Update timeline every 60 minutes --- **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor
Author
Owner

This is an automation tracking issue created by the Timeline Update supervisor. Automation tracking issues are not product work items and are closed here to keep the issue tracker clean.


Automated by CleverAgents Bot
Supervisor: Project Owner | Agent: project-owner-pool-supervisor [AUTO-OWNR-1]

This is an automation tracking issue created by the Timeline Update supervisor. Automation tracking issues are not product work items and are closed here to keep the issue tracker clean. --- **Automated by CleverAgents Bot** Supervisor: Project Owner | Agent: project-owner-pool-supervisor [AUTO-OWNR-1]
Author
Owner

Cycle 1 Complete — Day 103 Timeline Update

Status: Success
Time: 2026-04-13

Worker AUTO-TIME-1 Results

  • Cloned repository to /tmp/auto-time-1-clone
  • Created branch timeline/day-103-2026-04-13
  • Appended Day 103 schedule adherence entry to docs/timeline.md
  • Updated gantt chart today is date to 2026-04-13
  • Committed: fe6eaf601deea1ab951941df059fbb45bd541a53
  • PR #8053 created: #8053

Milestone Status at Cycle 1

Milestone Closed Open Total Complete%
M1 (v3.0.0) 163 0 163 100%
M2 (v3.1.0) 108 2 110 98%
M3 (v3.2.0) 262 689 951 27% 🔴
M4 (v3.3.0) 108 125 233 46% 🟡
M5 (v3.4.0) 137 208 345 40% 🟡
M6 (v3.5.0) 202 979 1181 17% 🔴
M7 (v3.6.0) 152 281 433 35% 🟡
M8 (v3.7.0) 427 529 956 45% 🟡
M9 (v3.8.0) 132 357 489 27% 🟡
v3.9.0 4 13 17 24% 🟢

Next Cycle

  • Cycle 2 scheduled in ~60 minutes
  • Will check for PR merge status and gather updated milestone data
  • Will dispatch AUTO-TIME-2 worker if timeline needs updating

Automated by CleverAgents Bot
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor

## Cycle 1 Complete — Day 103 Timeline Update **Status:** ✅ Success **Time:** 2026-04-13 ### Worker AUTO-TIME-1 Results - ✅ Cloned repository to `/tmp/auto-time-1-clone` - ✅ Created branch `timeline/day-103-2026-04-13` - ✅ Appended Day 103 schedule adherence entry to `docs/timeline.md` - ✅ Updated gantt chart `today is` date to `2026-04-13` - ✅ Committed: `fe6eaf601deea1ab951941df059fbb45bd541a53` - ✅ PR #8053 created: https://git.cleverthis.com/cleveragents/cleveragents-core/pulls/8053 ### Milestone Status at Cycle 1 | Milestone | Closed | Open | Total | Complete% | |-----------|--------|------|-------|-----------| | M1 (v3.0.0) | 163 | 0 | 163 | 100% ✅ | | M2 (v3.1.0) | 108 | 2 | 110 | 98% ✅ | | M3 (v3.2.0) | 262 | 689 | 951 | 27% 🔴 | | M4 (v3.3.0) | 108 | 125 | 233 | 46% 🟡 | | M5 (v3.4.0) | 137 | 208 | 345 | 40% 🟡 | | M6 (v3.5.0) | 202 | 979 | 1181 | 17% 🔴 | | M7 (v3.6.0) | 152 | 281 | 433 | 35% 🟡 | | M8 (v3.7.0) | 427 | 529 | 956 | 45% 🟡 | | M9 (v3.8.0) | 132 | 357 | 489 | 27% 🟡 | | v3.9.0 | 4 | 13 | 17 | 24% 🟢 | ### Next Cycle - Cycle 2 scheduled in ~60 minutes - Will check for PR merge status and gather updated milestone data - Will dispatch AUTO-TIME-2 worker if timeline needs updating --- **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor
Sign in to join this conversation.
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core#8033
No description provided.