docs(timeline): update schedule adherence Day 95 (2026-04-05) #3588

Merged
freemo merged 2 commits from docs/timeline-day95-update-2026-04-05-v2 into master 2026-04-05 21:06:24 +00:00
+59 -58
View File
@@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 866 open bugs | 179 open PRs | Session 3 active
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 878 open bugs | 183 open PRs | Session 3 active
Project starts 2026-02-03
saturday are closed
@@ -22,10 +22,11 @@ today is colored in #FF6666
' ================================================================
' GANTT CHART UPDATE LOG (Day 95 — 2026-04-05)
' Changes: Day 95 end-of-day refresh. Open PRs: 170→179 (+9). Open bugs: 809→866 (+57).
' 5 PRs merged today (plan rollback panels, actor remove, session fix, providers fix, plan apply).
' M3 62% (228/366), M4 60% (104/174), M5 67% (126/189), M6 55% (178/323),
' M7 41% (131/317), M8 43% (350/822), M9 25% (117/462).
' Changes: Day 95 cycle-2 refresh. Open PRs: 181→183 (+2). Open bugs: 853→878 (+25 new UAT bugs).
' M3 61% (228/376), M4 57% (104/183), M5 64% (126/196), M6 55% (180/325),
' M7 41% (138/335), M8 41% (359/880), M9 25% (118/465).
' Milestone totals grew significantly: M3 371→376, M4 179→183, M5 191→196, M6 323→325,
' M7 327→335, M8 830→880 (+50 new issues!), M9 464→465.
' Session 3 active. Session tracker issue: #3377.
' ================================================================
@@ -228,7 +229,7 @@ ganttDiagram {
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
[M3] starts at [M2]'s end
[M3] is 70% completed
[M3] is 61% completed
[M3] is colored in LightSkyBlue/SteelBlue
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
@@ -249,7 +250,7 @@ ganttDiagram {
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
[M4] starts at [M3]'s end
[M4] is 72% completed
[M4] is 57% completed
[M4] is colored in LightSkyBlue/SteelBlue
@@ -280,12 +281,12 @@ ganttDiagram {
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
[M5] starts at [M4]'s end
[M5] is 75% completed
[M5] is 64% completed
[M5] is colored in LightSkyBlue/SteelBlue
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
[M6] starts at [M5]'s end
[M6] is 67% completed
[M6] is 55% completed
[M6] is colored in LightSkyBlue/SteelBlue
[Subplans + Parallelism (#368)] as [SUBP] on {Luis} {Brent} requires 2 days
@@ -295,7 +296,7 @@ ganttDiagram {
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
[LARGE] starts 2026-03-17
[LARGE] is 55% completed
[LARGE] is 41% completed
[LARGE] is colored in LightSkyBlue/SteelBlue
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
@@ -399,13 +400,13 @@ legend right
----
**Risk Register (Day 95 — 2026-04-05 end-of-day)**
|= Epic |= Completion |= Risk |= Blocker |
| M3 (#357) | 62% | **CRITICAL** | 138 open issues in v3.2.0 |
| M4 (#358) | 60% | **CRITICAL** | 70 open issues in v3.3.0 |
| M5 (#359) | 67% | **HIGH** | 63 open issues in v3.4.0 |
| M3 (#357) | 61% | **CRITICAL** | 148 open issues in v3.2.0 |
| M4 (#358) | 57% | **CRITICAL** | 79 open issues in v3.3.0 |
| M5 (#359) | 64% | **HIGH** | 70 open issues in v3.4.0 |
| M6 (#360) | 55% | **HIGH** | 145 open issues in v3.5.0 |
| M7 (#361) | 41% | **HIGH** | 186 open issues in v3.6.0 |
| M8 (#362) | 43% | **HIGH** | 472 open issues in v3.7.0 (agent expansion) |
| SEC (#363) | 25% | **HIGH** | 345 open issues in v3.8.0 (agent expansion) |
| M7 (#361) | 41% | **HIGH** | 197 open issues in v3.6.0 |
| M8 (#362) | 41% | **HIGH** | 521 open issues in v3.7.0 (agent expansion) |
| SEC (#363) | 25% | **HIGH** | 347 open issues in v3.8.0 (agent expansion) |
----
**Color Key**
|= Color |= Meaning |
@@ -417,7 +418,7 @@ legend right
----
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
~1649 total story points | ~3300 estimated hours
**866 open bugs — 179 open PRs — Session 3 active (16 workers, ~71 agents)**
**878 open bugs — 183 open PRs — Session 3 active (16 workers, ~71 agents)**
end legend
@endgantt
@@ -1950,7 +1951,7 @@ legend right
----
271 Issues | 29 Epics | 9 Legendaries | 7 Milestones
~1649 total story points | ~3300 estimated hours
**809 open bugs — 170 open PRs — Session 3 active (16 workers, ~71 agents)**
**878 open bugs — 183 open PRs — Session 3 active (16 workers, ~71 agents)**
end legend
@endgantt
@@ -1962,13 +1963,13 @@ This section provides a high-level overview of the CleverAgents implementation r
### Current Status Summary
As of Day 95 (2026-04-05), the project has **179 open PRs** and **~1419 open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **866 open bugs** (continued agent-driven expansion from 809). M8 (v3.7.0) is now **43% complete** (350/822 issues closed — milestone grew from 796→822). M9 (v3.8.0) is **25% complete** (117/462 issues closed).
As of Day 95 (2026-04-05), the project has **183 open PRs** and **~1465 open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **878 open bugs** (up from 853 — continued agent-driven UAT bug creation). M8 (v3.7.0) is now **41% complete** (359/880 issues closed — milestone grew dramatically from 830→880, +50 new issues). M9 (v3.8.0) is **25% complete** (118/465 issues closed). M3 (v3.2.0) at **61%** (228/376), M4 (v3.3.0) at **57%** (104/183), M5 (v3.4.0) at **64%** (126/196), M6 (v3.5.0) at **55%** (180/325), M7 (v3.6.0) at **41%** (138/335).
**M1, M2 fully complete. M3 (v3.2.0)**: 62% complete (228/366), 138 open issues. **M4 (v3.3.0)**: 60% complete (104/174), 70 open issues. **M5 (v3.4.0)**: 67% complete (126/189), 63 open issues. **M6 (v3.5.0)**: 55% complete (178/323), 145 open issues. **M7 (v3.6.0)**: 41% complete (131/317), 186 open issues. **M8 (v3.7.0)**: 43% complete (350/822), 472 open issues. **M9 (v3.8.0)**: 25% complete (117/462), 345 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
**M1, M2 fully complete. M3 (v3.2.0)**: 61% complete (228/376), 148 open issues. **M4 (v3.3.0)**: 57% complete (104/183), 79 open issues. **M5 (v3.4.0)**: 64% complete (126/196), 70 open issues. **M6 (v3.5.0)**: 55% complete (180/325), 145 open issues. **M7 (v3.6.0)**: 41% complete (138/335), 197 open issues. **M8 (v3.7.0)**: 41% complete (359/880), 521 open issues. **M9 (v3.8.0)**: 25% complete (118/465), 347 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 866 Open Bugs — Session 3 Active (Day 95: Continued Agent Expansion)"
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 878 Open Bugs — Session 3 Active (Day 95: Continued Agent Expansion)"
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **179** (up from 170). Open bugs at **866** (continued agent-driven expansion from 809). Session tracker issue: #3377. **Current priorities**: (1) **Triage 866 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 179 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push** — 43% complete, 472 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 62% (138 open), M4 at 60% (70 open), M5 at 67% (63 open).
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **183** (up from 181). Open bugs at **878** (up from 853 — continued agent-driven UAT bug creation). Session tracker issue: #3377. **Current priorities**: (1) **Triage 878 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 183 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push** — 41% complete, 521 issues remaining (milestone grew +50 in 30 min). (4) **Clear M3/M4/M5 backlogs** — M3 at 61% (148 open), M4 at 57% (79 open), M5 at 64% (70 open).
### Parallel Workstreams
@@ -2285,18 +2286,18 @@ Items without an assigned milestone represent backlog work to be addressed after
### Schedule Risk Summary
As of Day 95 (2026-04-05), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **179** (up from 170). Open bugs at **866** (continued agent-driven expansion from 809). M8 (v3.7.0) at **43% complete** (350/822 closed — milestone grew from 796→822). M9 (v3.8.0) at **25% complete** (117/462 closed). Session tracker: #3377. Critical path: 179 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 43% with 472 issues remaining; 866 open bugs need TDD counterparts and systematic triage.
As of Day 95 (2026-04-05), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **183** (up from 181). Open bugs at **878** (up from 853 — continued agent-driven UAT bug creation). M8 (v3.7.0) at **41% complete** (359/880 closed — milestone grew dramatically from 830→880, +50 new issues in 30 min). M9 (v3.8.0) at **25% complete** (118/465 closed). Session tracker: #3377. Critical path: 183 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 41% with 521 issues remaining; 878 open bugs need TDD counterparts and systematic triage.
**Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry.
**Day 53 Session 3 actions**: (a) 16 parallel workers started. (b) 73+ PRs merged including ACMS UKO runtime (#1312), PermissionsScreen TUI (#1307), actor thought blocks (#1298), DatabaseResourceHandler (#1293), ACMS pipeline Phase 2 (#1287), DevcontainerHandler (#1286), async audit (#1279), serve CLI (#1272), LSP hover/definitions (#1240), domain event wiring (#1215), plan prompt command (#1212), M6 E2E tests (#1277), @tdd_expected_fail cleanup (#1229), persona export/import (#1338), first-run experience (#1391), session export/import (#1392). (c) UAT supervisor fleet (cycles 11-131) launched — discovered 100+ spec compliance bugs across CLI rich output, YAML config handling, and actor compiler. (d) Security bug-hunt PRs opened: #1412 (concurrency), #1409 (error handling), #1419 (hardcoded secrets). (e) Late-day: 4 more PRs merged (#1498, #1481, #1479, #1338), 18 new fix PRs opened (#1506-#1517) targeting UAT findings. (f) End-of-day CLI fix wave: 18 more PRs merged (#1574, #1573, #1570, #1569, #1567, #1566, #1565, #1563, #1562, #1558, #1556, #1554 and others) — open bugs reduced from **143 to 6**, open PRs at **74**.
**Critical path blockers** (ranked):
1. **179 open PRs need review** — continued agent-driven PR creation. All require review before merge.
2. **866 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued agent-driven expansion.
3. **M3-M7 backlog** — 138+70+63+145+186 open issues across M3-M7. All milestones regressed as agents added new issues.
4. **M8 (v3.7.0) at 43%**472 issues remaining (milestone grew from 796→822). Continued agent-driven expansion.
5. **M9 (v3.8.0) at 25%** — 345 issues remaining (milestone grew from 393→462). Significant expansion.
1. **183 open PRs need review** — continued agent-driven PR creation. All require review before merge.
2. **878 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued expansion (853→878).
3. **M3-M7 backlog** — 148+79+70+145+197 open issues across M3-M7. All milestones regressed as agents added new issues.
4. **M8 (v3.7.0) at 41%**521 issues remaining (milestone grew dramatically from 830→880, +50 in 30 min). Rapid agent-driven expansion.
5. **M9 (v3.8.0) at 25%** — 347 issues remaining (milestone grew from 464→465). Continued expansion.
**Spec changes impact assessment (Day 31)**: ACP→A2A rename affects 10 source files, 13 classes, 640+ test references across 22 files. Zero A2A code exists — migration not started. All open PRs that touch ACP modules will need additional rebase work after #688/#689 merge. TUI spec adds ~1,500 lines with 18 ASCII mockups defining Textual-based UI — PR #667 was a placeholder that predates this spec. Server architecture adopts JSON-RPC 2.0 standard — PR #676 used custom protocol, now obsolete.
@@ -4949,15 +4950,15 @@ Deadline risk: HIGH
**Notes**
- Day 95 end-of-day refresh (2026-04-05). Open PRs: 170→179 (+9 new agent PRs). Open bugs: 809→866 (+57 new UAT/bug-hunt bugs). Total open issues: ~1419. Session tracker issue: #3377.
- Day 95 cycle-2 refresh (2026-04-05). Open PRs: 181→183 (+2 new PRs). Open bugs: 853→878 (+25 new UAT bugs). Total open issues: ~1465. Session tracker issue: #3377.
- Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. UAT pool supervisor, PR reviewer pool, implementation pool, and spec updater agents all running.
- 5 PRs merged today (post-prior-entry): plan rollback panels (#3279), plan apply panels (#3460), actor remove impact counts (#3463), session field fix (#3461), providers type fix (#3459).
- Milestone totals continued to grow due to agent-driven issue creation: M3 (360→366), M5 (184→189), M6 (320→323), M7 (308→317), M8 (796→822).
- Milestone completions (Day 95 end-of-day): M3 62% (228/366), M4 60% (104/174), M5 67% (126/189), M6 55% (178/323), M7 41% (131/317), M8 43% (350/822), M9 25% (117/462).
- All milestone completion percentages continue to decline as agent-driven issue creation outpaces closures.
- 5 PRs merged earlier today: plan rollback panels (#3279), plan apply panels (#3460), actor remove impact counts (#3463), session field fix (#3461), providers type fix (#3459). Additional PRs opened: 183 total open.
- Milestone totals continued to grow rapidly due to agent-driven issue creation: M3 (371→376), M4 (179→183), M5 (191→196), M6 (323→325), M7 (327→335), M8 (830→880, +50 new issues!), M9 (464→465).
- Milestone completions (Day 95 cycle-2): M3 61% (228/376), M4 57% (104/183), M5 64% (126/196), M6 55% (180/325), M7 41% (138/335), M8 41% (359/880), M9 25% (118/465).
- M8 dropped from 43% to 41% as 50 new issues were added in ~30 minutes — rapid agent-driven expansion. M7 also declined (42%→41%) as 8 new issues were added.
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
- UAT pool supervisor and spec updater agents are running autonomously, continuing to discover and file spec compliance issues.
- New UAT bugs filed: #3444 (TUI HelpPanelOverlay keybinding mismatch), #3445 (plan rollback Rich output format incomplete), plus 57 additional bugs from continued agent activity.
- UAT pool supervisor and spec updater agents are running autonomously, continuing to discover and file spec compliance issues at high velocity.
- New UAT bugs filed include: #3560 (PlanExecutor no subplan spawning), #3561 (SkeletonCompressor not invoked), #3563 (ACMSPipeline single-strategy), #3564 (InvariantReconciliationActor 4-tier vs 3-tier), #3565 (project list format), #3566 (InvariantService DI bypass), #3567 (SubplanService validate_spawn), #3568 (NodeDefinition actor_ref ignored), #3569 (DecisionService dependencies not persisted), #3570 (project show format), #3571 (invariant add scope flag), plus 25+ additional bugs in cycle 2.
#### Milestone forecast
@@ -4966,34 +4967,34 @@ Deadline risk: HIGH
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-08 | +71d | CRITICAL — 138 open issues; agent-driven expansion outpacing closures |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-10 | +69d | CRITICAL — 70 open issues; completion at 60% |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-10 | +65d | HIGH — 63 open issues; 67% complete |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-22 | +73d | HIGH — 145 open issues; 55% complete |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-10 | +74d | HIGH — 186 open issues; 41% complete |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-05 | N/A | HIGH — 472 open issues; 43% complete |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-20 | N/A | MEDIUM — 345 open issues; 25% complete |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-12 | +75d | CRITICAL — 148 open issues; agent-driven expansion outpacing closures |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-14 | +73d | CRITICAL — 79 open issues; completion at 57% |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-14 | +69d | HIGH — 70 open issues; 64% complete |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-24 | +75d | HIGH — 145 open issues; 55% complete |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-15 | +79d | HIGH — 197 open issues; 41% complete |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-15 | N/A | HIGH — 521 open issues; 41% complete (milestone grew +50 in 30 min) |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-22 | N/A | MEDIUM — 347 open issues; 25% complete |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-10 | MEDIUM | 63 open issues in v3.4.0; continued agent-driven expansion |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-10 | CRITICAL | 70 open issues in v3.3.0; UAT spec compliance bugs ongoing; completion at 60% |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-08 | CRITICAL | 138 open issues in v3.2.0; agent-driven expansion outpacing closures |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 866 open bugs; continued agent-driven bug creation |
| Track T (Testing) | Active | Ongoing | HIGH | 179 open PRs need review; UAT pool supervisor active (#3377) |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-14 | MEDIUM | 70 open issues in v3.4.0; continued agent-driven expansion |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-14 | CRITICAL | 79 open issues in v3.3.0; UAT spec compliance bugs ongoing; completion at 57% |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-12 | CRITICAL | 148 open issues in v3.2.0; agent-driven expansion outpacing closures |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 878 open bugs; continued agent-driven bug creation (+25 in 30 min) |
| Track T (Testing) | Active | Ongoing | HIGH | 183 open PRs need review; UAT pool supervisor active (#3377) |
#### Developer forecast
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|------|-------------------|--------------|------|-------|
| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance; 179 open PRs |
| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance; 183 open PRs |
| Luis | -21d behind | active | HIGH | M6 (v3.5.0) features; security hardening; audit session; PR review pool |
| Hamza | -21d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews |
| Aditya | -21d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 866 open bugs triage |
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 878 open bugs triage |
| Rui | -21d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
| Mike/Brian | N/A | standby | LOW | N/A |
@@ -5005,16 +5006,16 @@ Milestone per developer as of Day 95 end-of-day (2026-04-05).
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 138 open | 228/366 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 70 open | 104/174 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 63 open | 126/189 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 145 open | 178/323 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 186 open | 131/317 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 472 open | 350/822 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 345 open | 117/462 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1419 open** | **1234/2749 closed** |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 148 open | 228/376 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 79 open | 104/183 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 70 open | 126/196 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 145 open | 180/325 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 197 open | 138/335 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 521 open | 359/880 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 347 open | 118/465 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1465 open** | **1249/2814 closed** |
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 end-of-day (2026-04-05). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M3 grew from 360→366, M5 grew from 184→189, M6 grew from 320→323, M7 grew from 308→317, M8 grew from 796→822 due to continued agent activity. 5 additional PRs merged today after prior entry.
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 cycle-2 refresh (2026-04-05). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues at high velocity across all milestones. M3 grew from 371→376, M4 grew from 179→183, M5 grew from 191→196, M6 grew from 323→325, M7 grew from 327→335, M8 grew dramatically from 830→880 (+50 new issues in ~30 min), M9 grew from 464→465. Open bugs increased from 853→878 (+25 new UAT bugs).
#### Story point allocation