docs(timeline): update schedule adherence Day 95 (2026-04-05) #3588

Merged
freemo merged 2 commits from docs/timeline-day95-update-2026-04-05-v2 into master 2026-04-05 21:06:24 +00:00
Owner

Summary

Updated docs/timeline.md with latest Forgejo data for Day 95 (2026-04-05).

Key Changes

  • Open bugs: 866 → 853 (13 resolved since prior entry)
  • Open PRs: 179 → 181 (+2 new PRs opened)
  • M3 (v3.2.0): 62% (228/366) → 61% (228/371) — total grew by 5 issues
  • M4 (v3.3.0): 60% (104/174) → 58% (104/179) — total grew by 5 issues
  • M5 (v3.4.0): 67% (126/189) → 66% (126/191) — total grew by 2 issues
  • M6 (v3.5.0): 55% (178/323) → 56% (180/323) — 2 issues closed
  • M7 (v3.6.0): 41% (131/317) → 42% (138/327) — 7 issues closed, 10 added
  • M8 (v3.7.0): 43% (350/822) → 43% (359/830) — stable percentage
  • M9 (v3.8.0): 25% (117/462) → 25% (118/464) — stable percentage

Sections Updated

  1. Epic-level gantt chart: completion percentages (M3/M4/M5/M6/M7/LARGE), update log comment, footer, risk register legend
  2. Detailed gantt chart: legend bug/PR counts
  3. Current Status Summary: all counts updated
  4. Schedule Risk Summary: all counts and blockers updated
  5. Day 95 schedule adherence entry: notes, milestone forecast, track forecast, developer forecast, task inventory

Automated by CleverAgents Bot
Supervisor: Timeline | Agent: ca-timeline-updater

## Summary Updated `docs/timeline.md` with latest Forgejo data for Day 95 (2026-04-05). ### Key Changes - **Open bugs**: 866 → **853** (13 resolved since prior entry) - **Open PRs**: 179 → **181** (+2 new PRs opened) - **M3 (v3.2.0)**: 62% (228/366) → **61%** (228/371) — total grew by 5 issues - **M4 (v3.3.0)**: 60% (104/174) → **58%** (104/179) — total grew by 5 issues - **M5 (v3.4.0)**: 67% (126/189) → **66%** (126/191) — total grew by 2 issues - **M6 (v3.5.0)**: 55% (178/323) → **56%** (180/323) — 2 issues closed - **M7 (v3.6.0)**: 41% (131/317) → **42%** (138/327) — 7 issues closed, 10 added - **M8 (v3.7.0)**: 43% (350/822) → **43%** (359/830) — stable percentage - **M9 (v3.8.0)**: 25% (117/462) → **25%** (118/464) — stable percentage ### Sections Updated 1. Epic-level gantt chart: completion percentages (M3/M4/M5/M6/M7/LARGE), update log comment, footer, risk register legend 2. Detailed gantt chart: legend bug/PR counts 3. Current Status Summary: all counts updated 4. Schedule Risk Summary: all counts and blockers updated 5. Day 95 schedule adherence entry: notes, milestone forecast, track forecast, developer forecast, task inventory --- **Automated by CleverAgents Bot** Supervisor: Timeline | Agent: ca-timeline-updater
docs(timeline): update schedule adherence Day 95 (2026-04-05)
Some checks are pending
CI / benchmark-publish (pull_request) Waiting to run
CI / build (pull_request) Waiting to run
CI / lint (pull_request) Waiting to run
CI / typecheck (pull_request) Waiting to run
CI / security (pull_request) Waiting to run
CI / quality (pull_request) Waiting to run
CI / unit_tests (pull_request) Waiting to run
CI / docker (pull_request) Blocked by required conditions
CI / integration_tests (pull_request) Waiting to run
CI / e2e_tests (pull_request) Waiting to run
CI / coverage (pull_request) Blocked by required conditions
CI / benchmark-regression (pull_request) Blocked by required conditions
CI / helm (pull_request) Waiting to run
CI / status-check (pull_request) Blocked by required conditions
d0254ba43a
Updated Day 95 entry with latest Forgejo data:
- Open bugs: 866 -> 853 (13 resolved)
- Open PRs: 179 -> 181 (+2 new)
- M3: 62% (228/366) -> 61% (228/371) — total grew
- M4: 60% (104/174) -> 58% (104/179) — total grew
- M5: 67% (126/189) -> 66% (126/191) — total grew
- M6: 55% (178/323) -> 56% (180/323) — slight improvement
- M7: 41% (131/317) -> 42% (138/327) — slight improvement
- M8: 43% (350/822) -> 43% (359/830) — stable
- M9: 25% (117/462) -> 25% (118/464) — stable
- Updated gantt chart completion percentages and legend
- Updated current status summary and risk section
freemo added this to the v3.7.0 milestone 2026-04-05 20:23:33 +00:00
docs(timeline): update schedule adherence Day 95 cycle-2 (2026-04-05)
Some checks failed
CI / lint (pull_request) Successful in 26s
CI / typecheck (pull_request) Successful in 50s
CI / quality (pull_request) Successful in 27s
CI / security (pull_request) Successful in 1m0s
CI / build (pull_request) Successful in 24s
CI / helm (pull_request) Successful in 24s
CI / unit_tests (pull_request) Failing after 7m10s
CI / docker (pull_request) Has been skipped
CI / coverage (pull_request) Successful in 11m17s
CI / e2e_tests (pull_request) Successful in 17m47s
CI / integration_tests (pull_request) Failing after 23m0s
CI / status-check (pull_request) Failing after 1s
CI / benchmark-publish (pull_request) Has been skipped
CI / benchmark-regression (pull_request) Successful in 57m6s
4b4f7d3305
Cycle-2 refresh with latest Forgejo data (30 min after initial update):
- Open bugs: 853 -> 878 (+25 new UAT bugs)
- Open PRs: 181 -> 183 (+2)
- M3: 61% (228/371) -> 61% (228/376) — total grew +5
- M4: 58% (104/179) -> 57% (104/183) — total grew +4
- M5: 66% (126/191) -> 64% (126/196) — total grew +5
- M6: 56% (180/323) -> 55% (180/325) — total grew +2
- M7: 42% (138/327) -> 41% (138/335) — total grew +8
- M8: 43% (359/830) -> 41% (359/880) — dramatic +50 new issues
- M9: 25% (118/464) -> 25% (118/465) — stable
- Updated all gantt charts, status summary, risk section, Day 95 entry
freemo merged commit a967921320 into master 2026-04-05 21:06:24 +00:00
Sign in to join this conversation.
No reviewers
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core!3588
No description provided.