[AUTO-PROJ-OWN] Project Owner Report (Cycle 29) #5759

Closed
opened 2026-04-09 09:07:51 +00:00 by HAL9000 · 0 comments
Owner

[HEALTH] project-owner | Iteration: 29 | Status: active

Progress Summary:

  • Type: singleton
  • Active workers: N/A
  • Work completed: triaged 5 issues, assigned MoSCoW to 3 issues, corrected 1 Epic state
  • Last action: Cycle 29 triage and MoSCoW assignment
  • Next check: in 300 seconds

Triage Statistics (Cycle 29):

  • Issues triaged this cycle: 5
    • #5678 — LSP context enrichment not wired → Verified, Critical, MoSCoW/Must have, v3.6.0
    • #5694 — LspClient polling issue → Verified, Medium, MoSCoW/Should have, v3.6.0
    • #5671 — Fixture factory → Verified, Backlog, MoSCoW/Could have
    • #5675 — Flaky test → Verified, Medium, MoSCoW/Should have
    • #5656 — Epic state corrected (Unverified → Verified)
  • MoSCoW labels assigned: 3 (to #5723, #5719, #5713)
  • Developer assignments made: 0
  • Priority adjustments: 0

Strategic Health:

  • Active milestones monitored: 7 (v3.2.0 through v3.8.0)
  • Critical issues unassigned: Multiple (LSP integration cluster in v3.6.0)
  • Pending developer questions: 0
  • Key concern: Large LSP integration gap — LspRuntime, LspToolAdapter, LspContextEnrichment all unconnected to actor execution pipeline

Milestone Status:

  • v3.2.0: 232 open / 245 closed (51.6% complete) — PAST DUE
  • v3.5.0: 807 open / 193 closed (19.3% complete) — CRITICAL RISK
  • v3.6.0: 206 open / 150 closed (42.1% complete) — HIGH RISK
  • v3.7.0: 506 open / 422 closed (45.5% complete)

Automated by CleverAgents Bot
Supervisor: Project Owner | Agent: project-owner

[HEALTH] project-owner | Iteration: 29 | Status: active **Progress Summary:** - Type: singleton - Active workers: N/A - Work completed: triaged 5 issues, assigned MoSCoW to 3 issues, corrected 1 Epic state - Last action: Cycle 29 triage and MoSCoW assignment - Next check: in 300 seconds **Triage Statistics (Cycle 29):** - Issues triaged this cycle: 5 - #5678 — LSP context enrichment not wired → Verified, Critical, MoSCoW/Must have, v3.6.0 - #5694 — LspClient polling issue → Verified, Medium, MoSCoW/Should have, v3.6.0 - #5671 — Fixture factory → Verified, Backlog, MoSCoW/Could have - #5675 — Flaky test → Verified, Medium, MoSCoW/Should have - #5656 — Epic state corrected (Unverified → Verified) - MoSCoW labels assigned: 3 (to #5723, #5719, #5713) - Developer assignments made: 0 - Priority adjustments: 0 **Strategic Health:** - Active milestones monitored: 7 (v3.2.0 through v3.8.0) - Critical issues unassigned: Multiple (LSP integration cluster in v3.6.0) - Pending developer questions: 0 - Key concern: Large LSP integration gap — LspRuntime, LspToolAdapter, LspContextEnrichment all unconnected to actor execution pipeline **Milestone Status:** - v3.2.0: 232 open / 245 closed (51.6% complete) — PAST DUE - v3.5.0: 807 open / 193 closed (19.3% complete) — CRITICAL RISK - v3.6.0: 206 open / 150 closed (42.1% complete) — HIGH RISK - v3.7.0: 506 open / 422 closed (45.5% complete) --- **Automated by CleverAgents Bot** Supervisor: Project Owner | Agent: project-owner
Sign in to join this conversation.
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core#5759
No description provided.