Implementation Timeline

Gantt Charts

Epic-Level Schedule

The following chart shows all milestones across the CleverAgents project with current completion status, risk levels, and schedule adherence tracking. Updated Day 103 Cycle 3 (2026-04-13 ~22:02 UTC) by AUTO-TIME supervisor.

@startgantt

title CleverAgents Core — Milestone Schedule (Day 103, Cycle 3)
footer Generated 2026-04-13 ~22:02 UTC | Day 103 | Cycle 3 | AUTO-TIME supervisor active

Project starts 2026-02-03
saturday are closed
sunday are closed
printscale weekly zoom 2

today is 2026-04-13
today is colored in #FF6666

' ============================================================
'  GANTT CHART UPDATE LOG (Day 103 Cycle 3 — 2026-04-13 ~22:02 UTC)
'  Changes: Cycle 3 refresh. Scope expansion detected in 60-min window.
'  Tracking issue: #8519
'  M1 v3.0.0: CLOSED 100% (163/163)
'  M2 v3.1.0: CLOSED 94.7% (108/113, 5 open — was 3, scope expanding!)
'  M3 v3.2.0: 25.1% (269/1071, 802 open) CRITICAL — 46 days overdue
'  M4 v3.3.0: 41.0% (109/266, 157 open) CRITICAL — 42 days overdue
'  M5 v3.4.0: 36.5% (139/381, 242 open) HIGH — 38 days overdue
'  M6 v3.5.0: 16.8% (212/1264, 1052 open) CRITICAL — 34 days overdue
'  M7 v3.6.0: 32.6% (152/466, 314 open) HIGH — 16 days overdue
'  M8 v3.7.0: 42.6% (427/1001, 574 open) HIGH — no deadline
'  M9 v3.8.0: 27.1% (133/491, 358 open) HIGH — no deadline
'  v3.9.0: 19.0% (4/21, 17 open) LOW — no deadline
'  ALERT: +110 new open issues in 60 min, only +2 closed!
'  CI not running on master since 2026-03-14 (issue #8508).
'  AUTO-TIME supervisor active. Tracking issue #8519.
' ============================================================

-- Completed Milestones --
[v3.0.0 M1: Local Source-Code Workflow] lasts 10 days and is 100% complete
[v3.0.0 M1: Local Source-Code Workflow] is colored in #00AA00
note bottom
  CLOSED 2026-03-16
  163/163 issues closed (100%)
  Due: 2026-02-15 (29 days late)
end note

[v3.1.0 M2: Actor Compiler + LLM Integration] lasts 7 days and is 95% complete
[v3.1.0 M2: Actor Compiler + LLM Integration] is colored in #AACC00
note bottom
  CLOSED 2026-03-16 (5 open issues remain — was 3!)
  108/113 issues closed (94.7%)
  Due: 2026-02-22 (22 days late)
  ALERT: Scope expanding in closed milestone
end note

-- Active Milestones (CRITICAL RISK) --
[v3.2.0 M3: Decisions + Validations + Invariants] lasts 21 days and is 25% complete
[v3.2.0 M3: Decisions + Validations + Invariants] is colored in #FF0000
note bottom
  CRITICAL RISK — 802 open issues (was 776, +26 in 60 min)
  269/1071 issues closed (25.1%)
  Due: 2026-02-26 (46 days overdue)
end note

[v3.3.0 M4: Corrections + Subplans + Checkpoints] lasts 14 days and is 41% complete
[v3.3.0 M4: Corrections + Subplans + Checkpoints] is colored in #FF4400
note bottom
  CRITICAL RISK — 157 open issues (was 148, +9 in 60 min)
  109/266 issues closed (41.0%)
  Due: 2026-03-02 (42 days overdue)
end note

[v3.5.0 M6: Autonomy Hardening] lasts 14 days and is 17% complete
[v3.5.0 M6: Autonomy Hardening] is colored in #FF0000
note bottom
  CRITICAL RISK — 1052 open issues (was 1032, +20 in 60 min)
  212/1264 issues closed (16.8%)
  Due: 2026-03-10 (34 days overdue)
end note

-- Active Milestones (HIGH RISK) --
[v3.4.0 M5: ACMS v1 + Context Scaling] lasts 14 days and is 37% complete
[v3.4.0 M5: ACMS v1 + Context Scaling] is colored in #FF6600
note bottom
  HIGH RISK — 242 open issues (was 233, +9 in 60 min)
  139/381 issues closed (36.5%)
  Due: 2026-03-06 (38 days overdue)
end note

[v3.6.0 M7: Advanced Concepts] lasts 18 days and is 33% complete
[v3.6.0 M7: Advanced Concepts] is colored in #FF8800
note bottom
  HIGH RISK — 314 open issues (was 296, +18 in 60 min)
  152/466 issues closed (32.6%)
  Due: 2026-03-28 (16 days overdue)
end note

[v3.7.0 M8: TUI Implementation] lasts 21 days and is 43% complete
[v3.7.0 M8: TUI Implementation] is colored in #FF8800
note bottom
  HIGH RISK — 574 open issues (was 548, +26 in 60 min)
  427/1001 issues closed (42.6%)
  No deadline assigned
end note

-- Future Milestones --
[v3.8.0 M9: Server Implementation] lasts 21 days and is 27% complete
[v3.8.0 M9: Server Implementation] is colored in #FFAA00
note bottom
  HIGH RISK — 358 open issues
  133/491 issues closed (27.1%)
  No deadline assigned
end note

[v3.9.0: Documentation + Feature Updates] lasts 7 days and is 19% complete
[v3.9.0: Documentation + Feature Updates] is colored in #FFCC00
note bottom
  LOW RISK — 17 open issues
  4/21 issues closed (19.0%)
  No deadline assigned
end note

@endgantt

Schedule Adherence

Date Day Cycle Milestone Planned % Actual % Delta Risk Notes
2026-02-15 D12 v3.0.0 M1 100% 0% -100% CRITICAL M1 not started by due date
2026-02-22 D19 v3.1.0 M2 100% 0% -100% CRITICAL M2 not started by due date
2026-02-26 D23 v3.2.0 M3 100% 0% -100% CRITICAL M3 not started by due date
2026-03-02 D27 v3.3.0 M4 100% 0% -100% CRITICAL M4 not started by due date
2026-03-06 D31 v3.4.0 M5 100% 0% -100% CRITICAL M5 not started by due date
2026-03-10 D35 v3.5.0 M6 100% 0% -100% CRITICAL M6 not started by due date
2026-03-16 D41 v3.0.0 M1 100% DONE M1 closed (29 days late)
2026-03-16 D41 v3.1.0 M2 97.3% PARTIAL M2 closed with 3 open issues (22 days late)
2026-03-28 D53 v3.6.0 M7 100% 0% -100% CRITICAL M7 not started by due date
2026-04-09 D99 v3.2.0 M3 100% 24.8% -75.2% CRITICAL Day 99: 260/1047 closed
2026-04-09 D99 v3.3.0 M4 100% 41.2% -58.8% CRITICAL Day 99: 108/262 closed
2026-04-09 D99 v3.4.0 M5 100% 36.9% -63.1% CRITICAL Day 99: 138/374 closed
2026-04-09 D99 v3.5.0 M6 100% 16.7% -83.3% CRITICAL Day 99: 208/1247 closed
2026-04-09 D99 v3.6.0 M7 100% 33.5% -66.5% CRITICAL Day 99: 151/451 closed
2026-04-09 D99 v3.7.0 M8 43.6% HIGH Day 99: 426/977 closed
2026-04-10 D100 v3.2.0 M3 100% 25.7% -74.3% CRITICAL Day 100: 269/1045 closed
2026-04-10 D100 v3.3.0 M4 100% 42.4% -57.6% CRITICAL Day 100: 109/257 closed
2026-04-10 D100 v3.4.0 M5 100% 37.4% -62.6% CRITICAL Day 100: 139/372 closed
2026-04-10 D100 v3.5.0 M6 100% 16.9% -83.1% CRITICAL Day 100: 210/1242 closed
2026-04-10 D100 v3.6.0 M7 100% 33.9% -66.1% CRITICAL Day 100: 152/448 closed
2026-04-10 D100 v3.7.0 M8 43.8% HIGH Day 100: 427/975 closed
2026-04-12 D101 v3.2.0 M3 100% 27.8% -72.2% CRITICAL Day 101: 258/926 closed, 664 open (+119)
2026-04-12 D101 v3.3.0 M4 100% 47.0% -53.0% CRITICAL Day 101: 108/230 closed, 122 open (+12)
2026-04-12 D101 v3.4.0 M5 100% 40.2% -59.8% CRITICAL Day 101: 137/341 closed, 204 open (+35)
2026-04-12 D101 v3.5.0 M6 100% 17.0% -83.0% CRITICAL Day 101: 201/1178 closed, 977 open (+135)
2026-04-12 D101 v3.6.0 M7 100% 35.2% -64.8% CRITICAL Day 101: 152/432 closed, 280 open (+48)
2026-04-12 D101 v3.7.0 M8 44.8% HIGH Day 101: 427/953 closed, 526 open (+28)
2026-04-12 D101 v3.8.0 M9 27.0% HIGH Day 101: 132/489 closed, 357 open (+29)
2026-04-13 D103 C2 v3.2.0 M3 100% 25.7% -74.3% CRITICAL Cycle 2: 269/1045 closed, 776 open
2026-04-13 D103 C2 v3.3.0 M4 100% 42.4% -57.6% CRITICAL Cycle 2: 109/257 closed, 148 open
2026-04-13 D103 C2 v3.4.0 M5 100% 37.4% -62.6% CRITICAL Cycle 2: 139/372 closed, 233 open
2026-04-13 D103 C2 v3.5.0 M6 100% 16.9% -83.1% CRITICAL Cycle 2: 210/1242 closed, 1032 open
2026-04-13 D103 C2 v3.6.0 M7 100% 33.9% -66.1% CRITICAL Cycle 2: 152/448 closed, 296 open
2026-04-13 D103 C2 v3.7.0 M8 43.8% HIGH Cycle 2: 427/975 closed, 548 open
2026-04-13 D103 C2 v3.8.0 M9 27.1% HIGH Cycle 2: 133/491 closed, 358 open
2026-04-13 D103 C2 v3.9.0 19.0% LOW Cycle 2: 4/21 closed, 17 open
2026-04-13 D103 C3 v3.1.0 M2 94.7% ALERT Cycle 3: 108/113 closed, 5 open (scope expanding in closed MS!)
2026-04-13 D103 C3 v3.2.0 M3 100% 25.1% -74.9% CRITICAL Cycle 3: 269/1071 closed, 802 open (+26 in 60 min)
2026-04-13 D103 C3 v3.3.0 M4 100% 41.0% -59.0% CRITICAL Cycle 3: 109/266 closed, 157 open (+9 in 60 min)
2026-04-13 D103 C3 v3.4.0 M5 100% 36.5% -63.5% CRITICAL Cycle 3: 139/381 closed, 242 open (+9 in 60 min)
2026-04-13 D103 C3 v3.5.0 M6 100% 16.8% -83.2% CRITICAL Cycle 3: 212/1264 closed, 1052 open (+20 in 60 min)
2026-04-13 D103 C3 v3.6.0 M7 100% 32.6% -67.4% CRITICAL Cycle 3: 152/466 closed, 314 open (+18 in 60 min)
2026-04-13 D103 C3 v3.7.0 M8 42.6% HIGH Cycle 3: 427/1001 closed, 574 open (+26 in 60 min)
2026-04-13 D103 C3 v3.8.0 M9 27.1% HIGH Cycle 3: 133/491 closed, 358 open (unchanged)

Scope Expansion Alert (Cycle 2 → Cycle 3, ~60 min window)

CRITICAL: In the 60-minute window between Cycle 2 and Cycle 3, all active milestones gained new open issues with minimal closures:

Milestone Open C2 Open C3 Delta Closed C2 Closed C3 Delta
v3.1.0 M2 3 5 +2 108 108 0
v3.2.0 M3 776 802 +26 269 269 0
v3.3.0 M4 148 157 +9 109 109 0
v3.4.0 M5 233 242 +9 139 139 0
v3.5.0 M6 1032 1052 +20 210 212 +2
v3.6.0 M7 296 314 +18 152 152 0
v3.7.0 M8 548 574 +26 427 427 0

Total new open issues in 60 min: +110 | Total new closed issues in 60 min: +2

Milestone Summaries

v3.0.0 (M1) — CLOSED

  • Status: Complete
  • Closed: 2026-03-16 (29 days after due date 2026-02-15)
  • Issues: 163/163 closed (100%)
  • Notes: First milestone completed. Established local source-code workflow, git worktree sandbox, SQLite persistence, actor-based LLM path.

v3.1.0 (M2) — CLOSED (scope expanding!)

  • Status: Closed but scope expanding — 5 open issues (was 3 at Cycle 2)
  • Closed: 2026-03-16 (22 days after due date 2026-02-22)
  • Issues: 108/113 closed (94.7%) — 5 open
  • Notes: Actor compiler and LLM integration complete. Open issue count growing despite milestone closure. LangGraph StateGraph compilation, MCP adapter, tool router operational.

v3.2.0 (M3) — CRITICAL RISK

  • Status: Open — 46 days overdue (due 2026-02-26)
  • Issues: 269/1071 closed (25.1%) — 802 open (+26 in 60 min)
  • Scope: Massively expanded (was ~300 issues, now 1071 and growing)
  • Blockers: Decision recording system, invariant management, plan correction engine (revert/append modes)
  • Key features: plan tree, plan explain, invariant add/list/remove, plan correct
  • Notes: CI not running on master since 2026-03-14. E2E tests deleted (commit 8ea00f5). Scope growing faster than issues are being closed.

v3.3.0 (M4) — CRITICAL RISK

  • Status: Open — 42 days overdue (due 2026-03-02)
  • Issues: 109/266 closed (41.0%) — 157 open (+9 in 60 min)
  • Blockers: Subplan spawning during execution, parallel subplan execution, three-way merge strategy, checkpoint creation and rollback
  • Key features: plan rollback, parallel execution with max_parallel, parent plan tracking
  • Notes: Depends on M3 completion for correction flow.

v3.4.0 (M5) — HIGH RISK

  • Status: Open — 38 days overdue (due 2026-03-06)
  • Issues: 139/381 closed (36.5%) — 242 open (+9 in 60 min)
  • Blockers: ACMS v1 pipeline, context window management (hot/warm/cold tiers), 10k+ file indexing without timeout
  • Key features: context list/add/show/clear, budget enforcement, context assembly CLI
  • Notes: Context scaling is a major technical challenge. Budget constraints (max_file_size, max_total_size).

v3.5.0 (M6) — CRITICAL RISK

  • Status: Open — 34 days overdue (due 2026-03-10)
  • Issues: 212/1264 closed (16.8%) — 1052 open (+20 in 60 min)
  • Scope: Massively expanded (was ~200 issues, now 1264 and growing)
  • Blockers: A2A facade session/plan lifecycle, event queue pub/sub, guard enforcement, autonomy hardening
  • Key features: Hierarchical decomposition (4+ levels), parallel execution (10+ concurrent), realistic porting task
  • Notes: Server stubs moved to M9 (ADR-047, ADR-048). TUI features moved to M8. Largest milestone by scope.

v3.6.0 (M7) — HIGH RISK

  • Status: Open — 16 days overdue (due 2026-03-28)
  • Issues: 152/466 closed (32.6%) — 314 open (+18 in 60 min)
  • Blockers: Advanced context strategies, additional LLM backends, container tool execution, pluggable scope chain
  • Key features: ACP→A2A rename, cost/session budgets, safety profiles, E2E workflow spec tests
  • Notes: Advanced concepts milestone. Abstraction layers for TUI/Server included.

v3.7.0 (M8) — HIGH RISK

  • Status: Open — No deadline assigned
  • Issues: 427/1001 closed (42.6%) — 574 open (+26 in 60 min)
  • Blockers: Textual TUI MainScreen, persona system (YAML-based), reference/command input (@, /, ! modes)
  • Key features: TuiMaterializer A2A integration, session persistence (SQLite), Dracula theme, multi-session tabs
  • Notes: TUI features moved here from M6. Highest absolute completion count (427 closed). ADR-044, ADR-045, ADR-046.

v3.8.0 (M9) — HIGH RISK

  • Status: Open — No deadline assigned
  • Issues: 133/491 closed (27.1%) — 358 open (unchanged)
  • Blockers: A2A JSON-RPC 2.0 wire format, stdio/HTTP transports, LangGraph Platform RemoteGraph, FastAPI + A2A SDK
  • Key features: Authentication/authorization (API tokens, RBAC), entity sync, PostgreSQL backend, Docker/K8s/Helm
  • Notes: Server implementation. ADR-047 (A2A adoption), ADR-048 (server architecture). No deadline.

v3.9.0 — LOW RISK

  • Status: Open — No deadline assigned
  • Issues: 4/21 closed (19.0%) — 17 open (unchanged)
  • Notes: Documentation and feature updates. Lowest priority milestone.

Risk Register

Risk Severity Milestones Affected Status Mitigation
All active milestones overdue CRITICAL M3-M7 Active Increase automation, parallel workers
Scope expanding faster than closing (+110 open in 60 min) CRITICAL All ESCALATING Scope freeze, prioritization
CI not running on master (since 2026-03-14) CRITICAL All Open (#8508) Fix CI trigger configuration
Massive scope expansion (M3: 1071, M6: 1264 issues) CRITICAL M3, M6 Active Scope management, prioritization
802 open issues in M3 alone CRITICAL M3 Active Focus automation on M3
1052 open issues in M6 CRITICAL M6 Active Parallel worker pools
E2E tests deleted (commit 8ea00f5, issue #8459) HIGH All Open Restore E2E test suite
Open PR #8380 unmerged (Day 103 Timeline Update) MEDIUM Timeline Open Superseded by PR #8582
v3.1.0 closed with 5 open issues (growing) MEDIUM M2 ESCALATING Resolve remaining issues, prevent scope creep

Timeline Update — 2026-04-16 (Cycle 2 Verification)

Schedule Adherence Updates

Date Day Cycle Milestone Planned % Actual % Delta Risk Notes
2026-04-14 D104 C2 v3.2.0 M3 100% 25.7% -74.3% CRITICAL Day 104: 269/1045 closed, 776 open
2026-04-14 D104 C2 v3.3.0 M4 100% 42.4% -57.6% CRITICAL Day 104: 109/257 closed, 148 open
2026-04-14 D104 C2 v3.4.0 M5 100% 37.4% -62.6% CRITICAL Day 104: 139/372 closed, 233 open
2026-04-14 D104 C2 v3.5.0 M6 100% 16.9% -83.1% CRITICAL Day 104: 210/1242 closed, 1032 open
2026-04-14 D104 C2 v3.6.0 M7 100% 33.9% -66.1% CRITICAL Day 104: 152/448 closed, 296 open
2026-04-14 D104 C2 v3.7.0 M8 43.8% HIGH Day 104: 427/975 closed, 548 open
2026-04-14 D104 C2 v3.8.0 M9 27.1% HIGH Day 104: 133/491 closed, 358 open
2026-04-15 D105 C2 v3.2.0 M3 100% 25.7% -74.3% CRITICAL Day 105: no changes detected
2026-04-15 D105 C2 v3.3.0 M4 100% 42.4% -57.6% CRITICAL Day 105: no changes detected
2026-04-15 D105 C2 v3.4.0 M5 100% 37.4% -62.6% CRITICAL Day 105: no changes detected
2026-04-15 D105 C2 v3.5.0 M6 100% 16.9% -83.1% CRITICAL Day 105: no changes detected
2026-04-15 D105 C2 v3.6.0 M7 100% 33.9% -66.1% CRITICAL Day 105: no changes detected
2026-04-15 D105 C2 v3.7.0 M8 43.8% HIGH Day 105: no changes detected
2026-04-15 D105 C2 v3.8.0 M9 27.1% HIGH Day 105: no changes detected
2026-04-16 D106 C2 v3.2.0 M3 100% 25.7% -74.3% CRITICAL Cycle 2 verification: no milestone changes since Day 104
2026-04-16 D106 C2 v3.3.0 M4 100% 42.4% -57.6% CRITICAL Cycle 2 verification: no milestone changes since Day 104
2026-04-16 D106 C2 v3.4.0 M5 100% 37.4% -62.6% CRITICAL Cycle 2 verification: no milestone changes since Day 104
2026-04-16 D106 C2 v3.5.0 M6 100% 16.9% -83.1% CRITICAL Cycle 2 verification: no milestone changes since Day 104
2026-04-16 D106 C2 v3.6.0 M7 100% 33.9% -66.1% CRITICAL Cycle 2 verification: no milestone changes since Day 104
2026-04-16 D106 C2 v3.7.0 M8 43.8% HIGH Cycle 2 verification: no milestone changes since Day 104
2026-04-16 D106 C2 v3.8.0 M9 27.1% HIGH Cycle 2 verification: no milestone changes since Day 104

Verification Summary (Cycle 2)

  • Snapshot: Milestone data verified -- no changes since Cycle 1
  • Milestones at risk: v3.2.0 (OVERDUE 49d), v3.3.0 (OVERDUE 45d), v3.4.0 (OVERDUE 41d), v3.5.0 (OVERDUE 37d), v3.6.0 (OVERDUE 19d)
  • Notes: All M3-M7 milestones remain overdue. No milestone closures detected. PR #10062 (Day 106 update) pending merge.

Automation Activity Log

Date Day Cycle Agent Action
2026-04-13 D103 C1 AUTO-TIME Supervisor started, tracking issue #8519 created
2026-04-13 D103 C2 AUTO-TIME-1 Timeline updated on branch auto-time-1-day103-cycle2, PR #8582 created
2026-04-13 D103 C3 AUTO-TIME-2 Timeline updated on branch auto-time-2-day103-cycle3, scope expansion alert added
2026-04-16 D106 C2 AUTO-TIME-3 Timeline verified on branch auto-time-3-day106-cycle2, PR #10062 created

Automated by CleverAgents Bot Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor