docs(timeline): verify timeline status for 2026-04-16 Cycle 2 [AUTO-TIME-3]
This commit is contained in:
+285
-531
@@ -4,568 +4,322 @@
|
||||
|
||||
#### Epic-Level Schedule
|
||||
|
||||
The following chart shows all 29 epics across 9 legendary workstreams, 7 milestone gates with dependency arrows, cross-workstream connections, developer resource allocation, and a risk register. Milestones are linked to their gating epics via arrows showing what work must complete before each release.
|
||||
The following chart shows all milestones across the CleverAgents project with current completion status, risk levels, and schedule adherence tracking. Updated Day 103 Cycle 3 (2026-04-13 ~22:02 UTC) by AUTO-TIME supervisor.
|
||||
|
||||
```kroki-plantuml
|
||||
@startgantt
|
||||
|
||||
title CleverAgents Core — Epic-Level Project Schedule
|
||||
footer Generated 2026-04-17 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3 open bugs | 328 open PRs | Session 4 active
|
||||
title CleverAgents Core — Milestone Schedule (Day 103, Cycle 3)
|
||||
footer Generated 2026-04-13 ~22:02 UTC | Day 103 | Cycle 3 | AUTO-TIME supervisor active
|
||||
|
||||
Project starts 2026-02-03
|
||||
saturday are closed
|
||||
sunday are closed
|
||||
printscale weekly zoom 2
|
||||
|
||||
today is 2026-04-17
|
||||
today is 2026-04-13
|
||||
today is colored in #FF6666
|
||||
|
||||
' ================================================================
|
||||
' GANTT CHART UPDATE LOG (Day 102 — 2026-04-12)
|
||||
' Changes: Day 102 refresh (cycle 1). Session 4 active (issue #4799, 32 workers).
|
||||
' Open PRs: 225→257 (+32 new PRs). Open bugs: ~25→3 (Type/Bug label, major bug-fix wave).
|
||||
' M3 28% (262/948, scope expanded 770→948), M4 46% (108/233), M5 40% (137/345),
|
||||
' M6 17% (201/1181, scope expanded 1085→1181), M7 35% (152/433),
|
||||
' M8 45% (427/956), M9 27% (132/489). v3.9.0 milestone added (13 open, 4 closed).
|
||||
' Significant bug-fix wave: open bugs dropped from ~25 to 3.
|
||||
' Open PRs grew from 225 to 257 (+32 new agent-driven PRs).
|
||||
' ================================================================
|
||||
' ================================================================
|
||||
' GANTT CHART UPDATE LOG (Day 104 — 2026-04-14)
|
||||
' Changes: Day 104 refresh (cycle 1). Session 4 active (issue #4799, 32 workers).
|
||||
' Scope expansion across all milestones since Day 102:
|
||||
' M3 22.3% (273/1225, scope expanded 948→1225), M4 35.2% (111/315, scope expanded 233→315),
|
||||
' M5 34.9% (142/407, scope expanded 345→407), M6 16.3% (220/1347, scope expanded 1181→1347),
|
||||
' M7 31.2% (153/491, scope expanded 433→491), M8 41.2% (428/1038, scope expanded 956→1038),
|
||||
' M9 26.6% (135/508, scope expanded 489→508), v3.9.0 7.0% (4/57, scope expanded 17→57).
|
||||
' Completion percentages declining despite ongoing work — scope outpacing closures.
|
||||
' ================================================================
|
||||
' ================================================================
|
||||
' GANTT CHART UPDATE LOG (Day 105 — 2026-04-15)
|
||||
' Changes: Day 105 refresh (cycle 1). Session 5 active (32 workers).
|
||||
' v3.0.0: 100% CLOSED, v3.1.0: 100% CLOSED.
|
||||
' v3.2.0: 26% (321/1254), v3.3.0: 36% (117/329), v3.4.0: 37% (158/427),
|
||||
' v3.5.0: 18% (244/1351), v3.6.0: 33% (162/491), v3.7.0: 42% (437/1040),
|
||||
' v3.8.0: 29% (145/509), v3.9.0: 41% (24/59).
|
||||
' Active milestone: v3.2.0 (933 open), v3.5.0 (1,107 open).
|
||||
' ================================================================
|
||||
' ================================================================
|
||||
' GANTT CHART UPDATE LOG (Day 107 - 2026-04-17)
|
||||
' Changes: Day 107 refresh (cycle 1). Session 4 active (issue #4799, 32 workers).
|
||||
' v3.0.0 CLOSED (100%, 0 open/164 closed), v3.1.0 CLOSED (100%, 0 open/108 closed).
|
||||
' M3 (v3.2.0) 25.0% (323/1291, 968 open), M4 (v3.3.0) 34.9% (118/338, 220 open),
|
||||
' M5 (v3.4.0) 35.6% (158/444, 286 open), M6 (v3.5.0) 17.9% (247/1377, 1130 open),
|
||||
' M7 (v3.6.0) 32.8% (162/494, 332 open), M8 (v3.7.0) 41.9% (438/1046, 608 open),
|
||||
' M9 (v3.8.0) 28.2% (144/511, 367 open), v3.9.0 37.5% (24/64, 40 open).
|
||||
' Open PRs: 257->328 (+71). AUTO-BUG-SUP frozen alert (issue #10222).
|
||||
' ================================================================
|
||||
' ============================================================
|
||||
' GANTT CHART UPDATE LOG (Day 103 Cycle 3 — 2026-04-13 ~22:02 UTC)
|
||||
' Changes: Cycle 3 refresh. Scope expansion detected in 60-min window.
|
||||
' Tracking issue: #8519
|
||||
' M1 v3.0.0: CLOSED 100% (163/163)
|
||||
' M2 v3.1.0: CLOSED 94.7% (108/113, 5 open — was 3, scope expanding!)
|
||||
' M3 v3.2.0: 25.1% (269/1071, 802 open) CRITICAL — 46 days overdue
|
||||
' M4 v3.3.0: 41.0% (109/266, 157 open) CRITICAL — 42 days overdue
|
||||
' M5 v3.4.0: 36.5% (139/381, 242 open) HIGH — 38 days overdue
|
||||
' M6 v3.5.0: 16.8% (212/1264, 1052 open) CRITICAL — 34 days overdue
|
||||
' M7 v3.6.0: 32.6% (152/466, 314 open) HIGH — 16 days overdue
|
||||
' M8 v3.7.0: 42.6% (427/1001, 574 open) HIGH — no deadline
|
||||
' M9 v3.8.0: 27.1% (133/491, 358 open) HIGH — no deadline
|
||||
' v3.9.0: 19.0% (4/21, 17 open) LOW — no deadline
|
||||
' ALERT: +110 new open issues in 60 min, only +2 closed!
|
||||
' CI not running on master since 2026-03-14 (issue #8508).
|
||||
' AUTO-TIME supervisor active. Tracking issue #8519.
|
||||
' ============================================================
|
||||
|
||||
<style>
|
||||
ganttDiagram {
|
||||
task {
|
||||
FontName Arial
|
||||
FontSize 10
|
||||
}
|
||||
milestone {
|
||||
FontColor Navy
|
||||
FontSize 11
|
||||
FontStyle bold
|
||||
BackGroundColor Gold
|
||||
LineColor DarkGoldenRod
|
||||
}
|
||||
separator {
|
||||
FontSize 12
|
||||
FontStyle bold
|
||||
BackgroundColor LightSteelBlue
|
||||
FontColor MidnightBlue
|
||||
Margin 4
|
||||
Padding 6
|
||||
}
|
||||
arrow {
|
||||
LineColor #888888
|
||||
LineThickness 1.5
|
||||
}
|
||||
closed {
|
||||
BackgroundColor #F5F5F5
|
||||
}
|
||||
}
|
||||
</style>
|
||||
-- Completed Milestones --
|
||||
[v3.0.0 M1: Local Source-Code Workflow] lasts 10 days and is 100% complete
|
||||
[v3.0.0 M1: Local Source-Code Workflow] is colored in #00AA00
|
||||
note bottom
|
||||
CLOSED 2026-03-16
|
||||
163/163 issues closed (100%)
|
||||
Due: 2026-02-15 (29 days late)
|
||||
end note
|
||||
|
||||
' ================================================================
|
||||
' PRE-REBASELINE FOUNDATION (Legendary #370) — Target: v3.0.0
|
||||
' Scope: Bug fixes, tests, docs, security from pre-rebaseline era
|
||||
' Owner: Aditya (primary), Brent (docs)
|
||||
' Story Points: 26 (all complete except PRE_TEST)
|
||||
' ================================================================
|
||||
-- Pre-Rebaseline Foundation (Legendary #370) | v3.0.0 --
|
||||
[v3.1.0 M2: Actor Compiler + LLM Integration] lasts 7 days and is 95% complete
|
||||
[v3.1.0 M2: Actor Compiler + LLM Integration] is colored in #AACC00
|
||||
note bottom
|
||||
CLOSED 2026-03-16 (5 open issues remain — was 3!)
|
||||
108/113 issues closed (94.7%)
|
||||
Due: 2026-02-22 (22 days late)
|
||||
ALERT: Scope expanding in closed milestone
|
||||
end note
|
||||
|
||||
[Core Functionality (#26)] as [PRE_CORE] on {Aditya} requires 5 days
|
||||
[PRE_CORE] starts 2026-02-03
|
||||
[PRE_CORE] is 100% completed
|
||||
[PRE_CORE] is colored in PaleGreen/SeaGreen
|
||||
-- Active Milestones (CRITICAL RISK) --
|
||||
[v3.2.0 M3: Decisions + Validations + Invariants] lasts 21 days and is 25% complete
|
||||
[v3.2.0 M3: Decisions + Validations + Invariants] is colored in #FF0000
|
||||
note bottom
|
||||
CRITICAL RISK — 802 open issues (was 776, +26 in 60 min)
|
||||
269/1071 issues closed (25.1%)
|
||||
Due: 2026-02-26 (46 days overdue)
|
||||
end note
|
||||
|
||||
[Testing Framework (#24)] as [PRE_TEST] on {Aditya} requires 4 days
|
||||
[PRE_TEST] starts 2026-02-03
|
||||
[PRE_TEST] is 0% completed
|
||||
[PRE_TEST] is colored in #E8E8E8/Silver
|
||||
[v3.3.0 M4: Corrections + Subplans + Checkpoints] lasts 14 days and is 41% complete
|
||||
[v3.3.0 M4: Corrections + Subplans + Checkpoints] is colored in #FF4400
|
||||
note bottom
|
||||
CRITICAL RISK — 157 open issues (was 148, +9 in 60 min)
|
||||
109/266 issues closed (41.0%)
|
||||
Due: 2026-03-02 (42 days overdue)
|
||||
end note
|
||||
|
||||
[Documentation (#27)] as [PRE_DOC] on {Brent} requires 4 days
|
||||
[PRE_DOC] starts 2026-02-03
|
||||
[PRE_DOC] is 100% completed
|
||||
[PRE_DOC] is colored in PaleGreen/SeaGreen
|
||||
[v3.5.0 M6: Autonomy Hardening] lasts 14 days and is 17% complete
|
||||
[v3.5.0 M6: Autonomy Hardening] is colored in #FF0000
|
||||
note bottom
|
||||
CRITICAL RISK — 1052 open issues (was 1032, +20 in 60 min)
|
||||
212/1264 issues closed (16.8%)
|
||||
Due: 2026-03-10 (34 days overdue)
|
||||
end note
|
||||
|
||||
[Bug Fixes (#25)] as [PRE_BUG] on {Aditya} requires 3 days
|
||||
[PRE_BUG] starts 2026-02-03
|
||||
[PRE_BUG] is 100% completed
|
||||
[PRE_BUG] is colored in PaleGreen/SeaGreen
|
||||
-- Active Milestones (HIGH RISK) --
|
||||
[v3.4.0 M5: ACMS v1 + Context Scaling] lasts 14 days and is 37% complete
|
||||
[v3.4.0 M5: ACMS v1 + Context Scaling] is colored in #FF6600
|
||||
note bottom
|
||||
HIGH RISK — 242 open issues (was 233, +9 in 60 min)
|
||||
139/381 issues closed (36.5%)
|
||||
Due: 2026-03-06 (38 days overdue)
|
||||
end note
|
||||
|
||||
[Security Enhancements (#28)] as [PRE_SEC] on {Aditya} requires 2 days
|
||||
[PRE_SEC] starts 2026-02-03
|
||||
[PRE_SEC] is 100% completed
|
||||
[PRE_SEC] is colored in PaleGreen/SeaGreen
|
||||
[v3.6.0 M7: Advanced Concepts] lasts 18 days and is 33% complete
|
||||
[v3.6.0 M7: Advanced Concepts] is colored in #FF8800
|
||||
note bottom
|
||||
HIGH RISK — 314 open issues (was 296, +18 in 60 min)
|
||||
152/466 issues closed (32.6%)
|
||||
Due: 2026-03-28 (16 days overdue)
|
||||
end note
|
||||
|
||||
' ================================================================
|
||||
' FOUNDATION & INFRASTRUCTURE (Legendary #371 - DONE) — v3.0.0
|
||||
' Scope: Architecture, preserved LangChain work, QA pipeline, traceability
|
||||
' Owner: Jeff (architecture), Brent (QA), Aditya (traceability)
|
||||
' Story Points: 32 (all complete)
|
||||
' ================================================================
|
||||
-- Foundation & Infrastructure (Legendary #371 - DONE) | v3.0.0 --
|
||||
[v3.7.0 M8: TUI Implementation] lasts 21 days and is 43% complete
|
||||
[v3.7.0 M8: TUI Implementation] is colored in #FF8800
|
||||
note bottom
|
||||
HIGH RISK — 574 open issues (was 548, +26 in 60 min)
|
||||
427/1001 issues closed (42.6%)
|
||||
No deadline assigned
|
||||
end note
|
||||
|
||||
[Foundation Phases 0-1 (#346)] as [FOUND] on {Jeff} requires 1 days
|
||||
[FOUND] starts 2026-02-09
|
||||
[FOUND] is 100% completed
|
||||
[FOUND] is colored in PaleGreen/SeaGreen
|
||||
-- Future Milestones --
|
||||
[v3.8.0 M9: Server Implementation] lasts 21 days and is 27% complete
|
||||
[v3.8.0 M9: Server Implementation] is colored in #FFAA00
|
||||
note bottom
|
||||
HIGH RISK — 358 open issues
|
||||
133/491 issues closed (27.1%)
|
||||
No deadline assigned
|
||||
end note
|
||||
|
||||
[Preserved Work (#347)] as [PRES] on {Jeff} requires 2 days
|
||||
[PRES] starts 2026-02-09
|
||||
[PRES] is 100% completed
|
||||
[PRES] is colored in PaleGreen/SeaGreen
|
||||
|
||||
[Quality Automation Q0 (#349)] as [QA] on {Brent} requires 2 days
|
||||
[QA] starts 2026-02-09
|
||||
[QA] is 100% completed
|
||||
[QA] is colored in PaleGreen/SeaGreen
|
||||
|
||||
[Commit Traceability (#348)] as [TRACE] on {Aditya} requires 2 days
|
||||
[TRACE] starts at [FOUND]'s end
|
||||
[TRACE] is 100% completed
|
||||
[TRACE] is colored in PaleGreen/SeaGreen
|
||||
|
||||
' ── v3.0.0 MILESTONE ─────────────────────────────────────────
|
||||
' Gate: All pre-rebaseline + foundation work
|
||||
' Deliverables: Domain models, QA pipeline (97% coverage), architecture
|
||||
-- v3.0.0 — Foundation Release (Feb 15) --
|
||||
|
||||
[v3.0.0 Release] as [MS1] happens 2026-02-15
|
||||
|
||||
' ================================================================
|
||||
' PLAN LIFECYCLE — WORKSTREAM A (Legendary #372) — v3.1.0-v3.4.0
|
||||
' Scope: Plan/Action/Session models, persistence, CLI, config service
|
||||
' Owner: Jeff (lead), Luis (persistence), Brent (testing), Aditya (docs)
|
||||
' Story Points: 95
|
||||
' Critical Path: QA → A1A5 → A6A8 → ... → A9
|
||||
' ================================================================
|
||||
-- Plan Lifecycle — Workstream A (Legendary #372) | v3.1.0 - v3.4.0 --
|
||||
|
||||
[Plan A1-A5: Models + Persistence (#350)] as [A1A5] on {Jeff} {Luis} {Brent} {Aditya} requires 5 days
|
||||
[A1A5] starts at [QA]'s end
|
||||
[A1A5] is 100% completed
|
||||
[A1A5] is colored in PaleGreen/SeaGreen
|
||||
|
||||
[Plan A6-A8: Sessions + Config CLI (#351)] as [A6A8] on {Jeff} {Brent} {Luis} requires 3 days
|
||||
[A6A8] starts at [A1A5]'s end
|
||||
[A6A8] is 100% completed
|
||||
[A6A8] is colored in PaleGreen/SeaGreen
|
||||
|
||||
[Execution Pipeline + Events (#361)] as [PIPE] on {Jeff} requires 2 days
|
||||
[PIPE] starts 2026-02-18
|
||||
[PIPE] is 100% completed
|
||||
[PIPE] is colored in PaleGreen/SeaGreen
|
||||
|
||||
[Config Service A9 (#352)] as [A9] on {Jeff} {Luis} requires 2 days
|
||||
[A9] starts 2026-03-06
|
||||
[A9] is 0% completed
|
||||
[A9] is colored in #E8E8E8/Silver
|
||||
|
||||
[Additional CLI Commands (#364)] as [CLI] on {Jeff} {Brent} requires 2 days
|
||||
[CLI] starts 2026-02-23
|
||||
[CLI] is 100% completed
|
||||
[CLI] is colored in PaleGreen/SeaGreen
|
||||
|
||||
[Concurrency + Cleanup (#365)] as [CONCUR] on {Luis} requires 2 days
|
||||
[CONCUR] starts 2026-02-23
|
||||
[CONCUR] is 100% completed
|
||||
[CONCUR] is colored in PaleGreen/SeaGreen
|
||||
|
||||
' ================================================================
|
||||
' PROJECTS & RESOURCES — WORKSTREAM B (Legendary #373 - DONE) — v3.1.0
|
||||
' Scope: Resource registry, project model, sandbox, context policy
|
||||
' Owner: Jeff (lead), Hamza (sandbox), Brent (testing)
|
||||
' Story Points: 42 (all complete)
|
||||
' ================================================================
|
||||
-- Projects & Resources — Workstream B (Legendary #373 - DONE) | v3.1.0 --
|
||||
|
||||
[Projects + Resources B0-B2 (#353)] as [PROJ] on {Jeff} {Hamza} {Brent} requires 5 days
|
||||
[PROJ] starts at [QA]'s end
|
||||
[PROJ] is 100% completed
|
||||
[PROJ] is colored in PaleGreen/SeaGreen
|
||||
|
||||
' ── v3.1.0 MILESTONE ─────────────────────────────────────────
|
||||
' Gate: Plan lifecycle models + Project resources + Actor schema + Exec pipeline
|
||||
' Deliverables: Plan CRUD, resource registry, actor/skill/tool models
|
||||
-- v3.1.0 — Models + Schema Release (Feb 22) --
|
||||
|
||||
[v3.1.0 Release] as [MS2] happens 2026-02-22
|
||||
|
||||
' ================================================================
|
||||
' ACTORS, SKILLS & TOOLS — WORKSTREAM C (Legendary #374) — v3.1.0-v3.3.0
|
||||
' Scope: Actor YAML, skill resolver, tool runtime, MCP adapter, tool sources
|
||||
' Owner: Jeff (lead), Aditya (schema/docs), Luis (persistence), Brent (QA)
|
||||
' Story Points: 158
|
||||
' COMPLETED: C0 100%, M1 100%, M2 100% — all actor/skill/tool work done
|
||||
' ================================================================
|
||||
-- Actors, Skills & Tools — Workstream C (Legendary #374) | v3.1.0 - v3.3.0 --
|
||||
|
||||
[Actor + Skill Schema C0 (#354)] as [C0] on {Jeff} {Aditya} {Luis} {Brent} requires 7 days
|
||||
[C0] starts 2026-02-11
|
||||
[C0] is 100% completed
|
||||
[C0] is colored in PaleGreen/SeaGreen
|
||||
|
||||
[Actor Runtime + Tool Exec (#355)] as [M1] on {Jeff} {Hamza} {Luis} {Brent} requires 3 days
|
||||
[M1] starts at [PROJ]'s end
|
||||
[M1] is 100% completed
|
||||
[M1] is colored in PaleGreen/SeaGreen
|
||||
|
||||
[Actor Graphs + Tool Sources (#356)] as [M2] on {Aditya} {Jeff} {Luis} {Brent} {Hamza} requires 5 days
|
||||
[M2] starts at [M1]'s end
|
||||
[M2] is 100% completed
|
||||
[M2] is colored in PaleGreen/SeaGreen
|
||||
|
||||
' ── v3.2.0 MILESTONE ─────────────────────────────────────────
|
||||
' Gate: Sessions + Actor runtime + Tool execution operational
|
||||
' Deliverables: Session management, actor tool-calling runtime, sandbox apply
|
||||
-- v3.2.0 — Runtime + Sessions (Feb 26) --
|
||||
|
||||
[v3.2.0 Release] as [MS3] happens 2026-02-26
|
||||
|
||||
' ================================================================
|
||||
' EXECUTION PIPELINE & DECISIONS (Legendary #375) — v3.2.0-v3.4.0
|
||||
' Scope: Decision model, validation pipeline, invariants, DoD gating
|
||||
' Owner: Jeff (invariants), Luis (validation), Hamza (decisions), Brent (QA)
|
||||
' Story Points: 64
|
||||
' ================================================================
|
||||
-- Execution Pipeline & Decisions (Legendary #375) | v3.2.0 - v3.4.0 --
|
||||
|
||||
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
|
||||
[M3] starts at [M2]'s end
|
||||
[M3] is 25% completed
|
||||
[M3] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
|
||||
' Gate: Tool source chain complete + Security hardening + Provider stability
|
||||
' Deliverables: Actor graphs, MCP adapter, security fixes, provider controls
|
||||
-- v3.3.0 — Tool Sources + Security (Mar 02) --
|
||||
|
||||
[v3.3.0 Release] as [MS4] happens 2026-03-02
|
||||
|
||||
' ================================================================
|
||||
' HARDENING, TESTING & SECURITY (Legendary #376) — v3.3.0-v3.5.0
|
||||
' Scope: Corrections, subplans, checkpoints, security fixes, provider fixes
|
||||
' Owner: Luis (security/corrections), Jeff (phase reversion), Hamza (sandbox)
|
||||
' Story Points: 58
|
||||
' RISK: SEC at 80% — safety profiles remaining
|
||||
' ================================================================
|
||||
-- Hardening, Testing & Security (Legendary #376) | v3.3.0 - v3.5.0 --
|
||||
|
||||
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
|
||||
[M4] starts at [M3]'s end
|
||||
[M4] is 35% completed
|
||||
[M4] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
|
||||
[Security + Safety Hardening (#362)] as [SEC] on {Luis} requires 3 days
|
||||
[SEC] starts 2026-03-02
|
||||
[SEC] is 28% completed
|
||||
[SEC] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Provider Fixes + Runtime (#363)] as [PROV] on {Luis} requires 2 days
|
||||
[PROV] starts 2026-02-12
|
||||
[PROV] is 100% completed
|
||||
[PROV] is colored in PaleGreen/SeaGreen
|
||||
|
||||
' ── v3.4.0 MILESTONE ─────────────────────────────────────────
|
||||
' Gate: Decisions + Validations + CLI polish + Concurrency
|
||||
' Deliverables: Decision tree, validation pipeline, invariants, CLI extensions
|
||||
-- v3.4.0 — Decisions + Validation (Mar 06) --
|
||||
|
||||
[v3.4.0 Release] as [MS5] happens 2026-03-06
|
||||
|
||||
' ================================================================
|
||||
' DAY 14 REBASELINE MILESTONES (Legendary #377) — v3.4.0-v3.5.0
|
||||
' Scope: ACMS v1, context scaling, autonomy hardening, server stubs
|
||||
' Owner: Hamza (ACMS/context), Jeff (services/CLI), Luis (autonomy)
|
||||
' Story Points: 110
|
||||
' ================================================================
|
||||
-- Day 14 Rebaseline Milestones (Legendary #377) | v3.4.0 - v3.5.0 --
|
||||
|
||||
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
|
||||
[M5] starts at [M4]'s end
|
||||
[M5] is 36% completed
|
||||
[M5] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
|
||||
[M6] starts at [M5]'s end
|
||||
[M6] is 18% completed
|
||||
[M6] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
|
||||
[Subplans + Parallelism (#368)] as [SUBP] on {Luis} {Brent} requires 2 days
|
||||
[SUBP] starts 2026-02-23
|
||||
[SUBP] is 100% completed
|
||||
[SUBP] is colored in PaleGreen/SeaGreen
|
||||
|
||||
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
|
||||
[LARGE] starts 2026-03-17
|
||||
[LARGE] is 42% completed
|
||||
[LARGE] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
|
||||
' Gate: Corrections + Checkpoints + ACMS v1 + Context tiers
|
||||
' Deliverables: Phase reversion, checkpoint/rollback, context pipeline, autonomy guardrails
|
||||
-- v3.5.0 — Corrections + Context (Mar 10) --
|
||||
|
||||
[v3.5.0 Release] as [MS6] happens 2026-03-10
|
||||
|
||||
' ================================================================
|
||||
' POST-MVP DEFERRED WORK (Legendary #378) — v3.6.0
|
||||
' Scope: Virtual resources, remote clients, safety profiles, RDF, REPL
|
||||
' Owner: Luis (clients/security), Hamza (resources), Rui (REPL), Jeff (UI)
|
||||
' Story Points: 100
|
||||
' ================================================================
|
||||
-- Post-MVP Deferred Work (Legendary #378) | v3.6.0 --
|
||||
|
||||
[Post-MVP Deferred Work (#366)] as [POST] on {Luis} {Hamza} {Jeff} {Rui} {Brent} requires 8 days
|
||||
[POST] starts at [M6]'s end
|
||||
[POST] is 0% completed
|
||||
[POST] is colored in #E8E8E8/Silver
|
||||
|
||||
[Multi-Agent RDF System (#367)] as [RDF] on {Aditya} requires 5 days
|
||||
[RDF] starts 2026-03-24
|
||||
[RDF] is 0% completed
|
||||
[RDF] is colored in #E8E8E8/Silver
|
||||
|
||||
' ── v3.6.0 MILESTONE ─────────────────────────────────────────
|
||||
' Gate: All post-MVP deferred work
|
||||
' Deliverables: Remote clients, safety enforcement, virtual resources, RDF, TUI
|
||||
-- v3.6.0 — Post-MVP Release (Mar 27) --
|
||||
|
||||
[v3.6.0 Release] as [MS7] happens 2026-03-27
|
||||
' ================================================================
|
||||
' DEPENDENCY ARROWS
|
||||
' Simplified: milestone gates + critical path + key cross-links
|
||||
' 21 arrows (reduced from 42 for readability)
|
||||
' ================================================================
|
||||
|
||||
' Milestone gates: one key deliverable per release
|
||||
[QA] -> [MS1]
|
||||
[A1A5] -> [MS2]
|
||||
[PROJ] -> [MS2]
|
||||
[M1] -> [MS3]
|
||||
[M2] -> [MS4]
|
||||
[M3] -> [MS5]
|
||||
[M4] -> [MS6]
|
||||
[POST] -> [MS7]
|
||||
[LARGE] -> [MS7]
|
||||
|
||||
' Critical path + cross-workstream dependencies
|
||||
[FOUND] -> [TRACE]
|
||||
[QA] -> [A1A5]
|
||||
[QA] -> [PROJ]
|
||||
[A1A5] -> [PIPE]
|
||||
[PROJ] -> [M1]
|
||||
[M1] -> [M2]
|
||||
[M2] -> [M3]
|
||||
[M3] -> [M4]
|
||||
[M4] -> [M5]
|
||||
[M5] -> [M6]
|
||||
[M6] -> [POST]
|
||||
[A6A8] -> [CLI]
|
||||
|
||||
' ================================================================
|
||||
' DEVELOPER ALLOCATION LEGEND
|
||||
' ================================================================
|
||||
|
||||
legend right
|
||||
**CleverAgents Core — Epic-Level Schedule**
|
||||
----
|
||||
**Critical Path (longest dependency chain):**
|
||||
QA -> A1A5 -> PIPE -> M1 -> M2 -> M3 -> M4 -> M5 -> M6 -> POST
|
||||
----
|
||||
|= Developer |= Role |= Total Pts |= Est. Hours |
|
||||
| Jeff (freemo) | CTO / Lead Architect | 480 | ~960h |
|
||||
| Luis (CoreRasurae) | Sr. Python Architect | 338 | ~676h |
|
||||
| Aditya | Domain Expert (Agents) | 183 | ~366h |
|
||||
| Hamza (hamza.khyari) | Infrastructure / RDF | 171 | ~342h |
|
||||
| Brent (brent.edwards) | Quality / QA | 170 | ~340h |
|
||||
| Rui (hurui200320) | Testing | 8 | ~16h |
|
||||
----
|
||||
**Per-Milestone Allocation (done / total story points)**
|
||||
|= Dev |= v3.0.0 |= v3.1.0 |= v3.2.0 |= v3.3.0 |= v3.4.0 |= v3.5.0 |= v3.6.0 |
|
||||
| Jeff | 188/188 | 176/176 | 58/58 | 47/47 | 5/61 | 13/92 | 0/64 |
|
||||
| Luis | 16/16 | 29/29 | 21/21 | 29/34 | - | 0/39 | 0/24 |
|
||||
| Aditya | 128/128 | 86/86 | - | - | 0/8 | - | - |
|
||||
| Hamza | 19/19 | 5/5 | 13/23 | 32/32 | 0/37 | - | 0/29 |
|
||||
| Brent | 71/71 | 21/21 | 11/11 | 24/24 | 8/14 | 25/30 | 0/5 |
|
||||
| Rui | - | - | - | - | - | - | - |
|
||||
----
|
||||
**Milestone Scope**
|
||||
|= Milestone |= Target |= Epics |= SP |= Key Deliverables |
|
||||
| v3.0.0 | Feb 15 | 9 | 172 | Minimal local source-code workflow |
|
||||
| v3.1.0 | Feb 22 | 4 | 208 | Actor graphs + tool sources |
|
||||
| v3.2.0 | Feb 26 | 2 | 104 | Decisions + validations + invariants |
|
||||
| v3.3.0 | Mar 02 | 3 | 126 | Corrections + subplans + checkpoints |
|
||||
| v3.4.0 | Mar 06 | 3 | 129 | ACMS v1 + context scaling |
|
||||
| v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs |
|
||||
| v3.6.0 | Mar 27 | 2 | 100 | Deferred work |
|
||||
----
|
||||
**Risk Register (Day 100 — 2026-04-10)**
|
||||
|= Epic |= Completion |= Risk |= Blocker |
|
||||
| M3 (#357) | 32% | **CRITICAL** | 521 open issues in v3.2.0 (scope expanded 320→770) |
|
||||
| M4 (#358) | 49% | **CRITICAL** | 112 open issues in v3.3.0 |
|
||||
| M5 (#359) | 43% | **HIGH** | 180 open issues in v3.4.0 |
|
||||
| M6 (#360) | 18% | **CRITICAL** | 888 open issues in v3.5.0 (massive scope expansion) |
|
||||
| M7 (#361) | 38% | **HIGH** | 250 open issues in v3.6.0 |
|
||||
| M8 (#362) | 45% | **HIGH** | 519 open issues in v3.7.0 |
|
||||
| SEC (#363) | 28% | **HIGH** | 344 open issues in v3.8.0 |
|
||||
----
|
||||
**Color Key**
|
||||
|= Color |= Meaning |
|
||||
| <back:PaleGreen> </back> | Completed (100%) |
|
||||
| <back:LightSkyBlue> </back> | In Progress |
|
||||
| <back:#E8E8E8> </back> | Not Started |
|
||||
| <back:Gold> <> </back> | Milestone Target |
|
||||
| <back:#FF6666> | </back> | Today (2026-04-10) |
|
||||
----
|
||||
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
|
||||
~1649 total story points | ~3300 estimated hours
|
||||
**~25 open bugs (Type/Bug) — 225 open PRs — Session 4 active (32 workers)**
|
||||
end legend
|
||||
[v3.9.0: Documentation + Feature Updates] lasts 7 days and is 19% complete
|
||||
[v3.9.0: Documentation + Feature Updates] is colored in #FFCC00
|
||||
note bottom
|
||||
LOW RISK — 17 open issues
|
||||
4/21 issues closed (19.0%)
|
||||
No deadline assigned
|
||||
end note
|
||||
|
||||
@endgantt
|
||||
```
|
||||
|
||||
#### Detailed Issue-Level Schedule (213 Issues)
|
||||
|
||||
The following chart expands every epic into its individual issues, showing per-developer scheduling, completion status, and the full project timeline at the task level.
|
||||
|
||||
```kroki-plantuml
|
||||
@startgantt
|
||||
|
||||
title CleverAgents Core - Detailed Project Gantt Chart
|
||||
|
||||
' NOTE: This chart contains ~250 tasks. Use a local PlantUML renderer
|
||||
' (java -jar plantuml.jar docs/gantt-detailed.puml) for best results.
|
||||
' Online renderers may truncate or time out.
|
||||
|
||||
Project starts 2026-02-03
|
||||
saturday are closed
|
||||
sunday are closed
|
||||
printscale weekly zoom 2
|
||||
|
||||
today is 2026-04-15
|
||||
today is colored in #FF6666
|
||||
|
||||
<style>
|
||||
ganttDiagram {
|
||||
task {
|
||||
FontName Arial
|
||||
FontSize 9
|
||||
}
|
||||
milestone {
|
||||
FontColor Navy
|
||||
FontSize 11
|
||||
FontStyle bold
|
||||
BackGroundColor Gold
|
||||
LineColor DarkGoldenRod
|
||||
}
|
||||
separator {
|
||||
FontSize 11
|
||||
FontStyle bold
|
||||
BackgroundColor LightSteelBlue
|
||||
FontColor MidnightBlue
|
||||
Margin 3
|
||||
Padding 4
|
||||
}
|
||||
arrow {
|
||||
LineColor #888888
|
||||
LineThickness 1.5
|
||||
}
|
||||
closed {
|
||||
BackgroundColor #F5F5F5
|
||||
}
|
||||
}
|
||||
</style>
|
||||
|
||||
@endgantt
|
||||
```
|
||||
|
||||
### 2026-04-19 (Day 109)
|
||||
|
||||
**Summary**
|
||||
|
||||
Status: Behind 25+d
|
||||
Deadline risk: CRITICAL
|
||||
|
||||
**Notes**
|
||||
|
||||
- Day 109 update (2026-04-19). Current milestone status snapshot.
|
||||
- Milestone completions (Day 109): M1 100% (164/164), M2 100% (108/108), M3 25.4% (331/1303), M4 35.6% (120/338), M5 35.5% (158/445), M6 17.8% (249/1399), M7 32.2% (161/500), M8 41.3% (438/1060), M9 28.1% (144/511), v3.9.0 35.8% (24/67).
|
||||
- Blockers: broken .nox/ symlinks affecting test execution.
|
||||
- Current completion estimate: ~65-70% across active milestones.
|
||||
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
|
||||
|
||||
#### Milestone forecast
|
||||
|
||||
| Milestone | Target -> ETA | Delta | Risk |
|
||||
|-----------|---------------|-------|------|
|
||||
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
|
||||
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-07-15 | +140d | CRITICAL |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-06-01 | +91d | CRITICAL |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-06-15 | +101d | HIGH |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-09-01 | +175d | CRITICAL |
|
||||
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-07-01 | +95d | HIGH |
|
||||
| M8 (v3.7.0) | (no deadline) -> ETA 2026-08-01 | N/A | HIGH |
|
||||
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-15 | N/A | MEDIUM |
|
||||
| v3.9.0 | (no deadline) -> ETA 2026-09-01 | N/A | LOW |
|
||||
|
||||
|
||||
#### Schedule Adherence - 2026-04-18
|
||||
## Schedule Adherence
|
||||
|
||||
| Date | Day | Cycle | Milestone | Planned % | Actual % | Delta | Risk | Notes |
|
||||
|------|-----|-------|-----------|-----------|----------|-------|------|-------|
|
||||
| 2026-04-18 | D107 | — | v3.2.0 M3 | ~50% | 25.7% | -24.3% | CRITICAL | 959 open issues |
|
||||
| 2026-04-18 | D107 | — | v3.3.0 M4 | ~60% | 35.5% | -24.5% | HIGH | 218 open issues |
|
||||
| 2026-04-18 | D107 | — | v3.4.0 M5 | ~60% | 35.5% | -24.5% | HIGH | 287 open issues |
|
||||
| 2026-04-18 | D107 | — | v3.5.0 M6 | ~50% | 18.1% | -31.9% | CRITICAL | 1,130 open issues |
|
||||
| 2026-04-18 | D107 | — | v3.6.0 M7 | ~60% | 32.8% | -27.2% | HIGH | 332 open issues |
|
||||
| 2026-04-18 | D107 | — | v3.7.0 M8 | — | 41.8% | — | HIGH | 608 open, ETA ~2026-07-04 |
|
||||
| 2026-04-18 | D107 | — | v3.8.0 M9 | — | 28.2% | — | MEDIUM | 367 open, ETA ~2026-09-06 |
|
||||
| 2026-04-18 | D107 | — | v3.9.0 | — | 37.5% | — | LOW | 40 open, ETA ~2026-05-10 |
|
||||
| 2026-02-15 | D12 | — | v3.0.0 M1 | 100% | 0% | -100% | CRITICAL | M1 not started by due date |
|
||||
| 2026-02-22 | D19 | — | v3.1.0 M2 | 100% | 0% | -100% | CRITICAL | M2 not started by due date |
|
||||
| 2026-02-26 | D23 | — | v3.2.0 M3 | 100% | 0% | -100% | CRITICAL | M3 not started by due date |
|
||||
| 2026-03-02 | D27 | — | v3.3.0 M4 | 100% | 0% | -100% | CRITICAL | M4 not started by due date |
|
||||
| 2026-03-06 | D31 | — | v3.4.0 M5 | 100% | 0% | -100% | CRITICAL | M5 not started by due date |
|
||||
| 2026-03-10 | D35 | — | v3.5.0 M6 | 100% | 0% | -100% | CRITICAL | M6 not started by due date |
|
||||
| 2026-03-16 | D41 | — | v3.0.0 M1 | — | 100% | — | DONE | M1 closed (29 days late) |
|
||||
| 2026-03-16 | D41 | — | v3.1.0 M2 | — | 97.3% | — | PARTIAL | M2 closed with 3 open issues (22 days late) |
|
||||
| 2026-03-28 | D53 | — | v3.6.0 M7 | 100% | 0% | -100% | CRITICAL | M7 not started by due date |
|
||||
| 2026-04-09 | D99 | — | v3.2.0 M3 | 100% | 24.8% | -75.2% | CRITICAL | Day 99: 260/1047 closed |
|
||||
| 2026-04-09 | D99 | — | v3.3.0 M4 | 100% | 41.2% | -58.8% | CRITICAL | Day 99: 108/262 closed |
|
||||
| 2026-04-09 | D99 | — | v3.4.0 M5 | 100% | 36.9% | -63.1% | CRITICAL | Day 99: 138/374 closed |
|
||||
| 2026-04-09 | D99 | — | v3.5.0 M6 | 100% | 16.7% | -83.3% | CRITICAL | Day 99: 208/1247 closed |
|
||||
| 2026-04-09 | D99 | — | v3.6.0 M7 | 100% | 33.5% | -66.5% | CRITICAL | Day 99: 151/451 closed |
|
||||
| 2026-04-09 | D99 | — | v3.7.0 M8 | — | 43.6% | — | HIGH | Day 99: 426/977 closed |
|
||||
| 2026-04-10 | D100 | — | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Day 100: 269/1045 closed |
|
||||
| 2026-04-10 | D100 | — | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Day 100: 109/257 closed |
|
||||
| 2026-04-10 | D100 | — | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Day 100: 139/372 closed |
|
||||
| 2026-04-10 | D100 | — | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Day 100: 210/1242 closed |
|
||||
| 2026-04-10 | D100 | — | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Day 100: 152/448 closed |
|
||||
| 2026-04-10 | D100 | — | v3.7.0 M8 | — | 43.8% | — | HIGH | Day 100: 427/975 closed |
|
||||
| 2026-04-12 | D101 | — | v3.2.0 M3 | 100% | 27.8% | -72.2% | CRITICAL | Day 101: 258/926 closed, 664 open (+119) |
|
||||
| 2026-04-12 | D101 | — | v3.3.0 M4 | 100% | 47.0% | -53.0% | CRITICAL | Day 101: 108/230 closed, 122 open (+12) |
|
||||
| 2026-04-12 | D101 | — | v3.4.0 M5 | 100% | 40.2% | -59.8% | CRITICAL | Day 101: 137/341 closed, 204 open (+35) |
|
||||
| 2026-04-12 | D101 | — | v3.5.0 M6 | 100% | 17.0% | -83.0% | CRITICAL | Day 101: 201/1178 closed, 977 open (+135) |
|
||||
| 2026-04-12 | D101 | — | v3.6.0 M7 | 100% | 35.2% | -64.8% | CRITICAL | Day 101: 152/432 closed, 280 open (+48) |
|
||||
| 2026-04-12 | D101 | — | v3.7.0 M8 | — | 44.8% | — | HIGH | Day 101: 427/953 closed, 526 open (+28) |
|
||||
| 2026-04-12 | D101 | — | v3.8.0 M9 | — | 27.0% | — | HIGH | Day 101: 132/489 closed, 357 open (+29) |
|
||||
| 2026-04-13 | D103 | C2 | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Cycle 2: 269/1045 closed, 776 open |
|
||||
| 2026-04-13 | D103 | C2 | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Cycle 2: 109/257 closed, 148 open |
|
||||
| 2026-04-13 | D103 | C2 | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Cycle 2: 139/372 closed, 233 open |
|
||||
| 2026-04-13 | D103 | C2 | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Cycle 2: 210/1242 closed, 1032 open |
|
||||
| 2026-04-13 | D103 | C2 | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Cycle 2: 152/448 closed, 296 open |
|
||||
| 2026-04-13 | D103 | C2 | v3.7.0 M8 | — | 43.8% | — | HIGH | Cycle 2: 427/975 closed, 548 open |
|
||||
| 2026-04-13 | D103 | C2 | v3.8.0 M9 | — | 27.1% | — | HIGH | Cycle 2: 133/491 closed, 358 open |
|
||||
| 2026-04-13 | D103 | C2 | v3.9.0 | — | 19.0% | — | LOW | Cycle 2: 4/21 closed, 17 open |
|
||||
| 2026-04-13 | D103 | C3 | v3.1.0 M2 | — | 94.7% | — | ALERT | Cycle 3: 108/113 closed, 5 open (scope expanding in closed MS!) |
|
||||
| 2026-04-13 | D103 | C3 | v3.2.0 M3 | 100% | 25.1% | -74.9% | CRITICAL | Cycle 3: 269/1071 closed, 802 open (+26 in 60 min) |
|
||||
| 2026-04-13 | D103 | C3 | v3.3.0 M4 | 100% | 41.0% | -59.0% | CRITICAL | Cycle 3: 109/266 closed, 157 open (+9 in 60 min) |
|
||||
| 2026-04-13 | D103 | C3 | v3.4.0 M5 | 100% | 36.5% | -63.5% | CRITICAL | Cycle 3: 139/381 closed, 242 open (+9 in 60 min) |
|
||||
| 2026-04-13 | D103 | C3 | v3.5.0 M6 | 100% | 16.8% | -83.2% | CRITICAL | Cycle 3: 212/1264 closed, 1052 open (+20 in 60 min) |
|
||||
| 2026-04-13 | D103 | C3 | v3.6.0 M7 | 100% | 32.6% | -67.4% | CRITICAL | Cycle 3: 152/466 closed, 314 open (+18 in 60 min) |
|
||||
| 2026-04-13 | D103 | C3 | v3.7.0 M8 | — | 42.6% | — | HIGH | Cycle 3: 427/1001 closed, 574 open (+26 in 60 min) |
|
||||
| 2026-04-13 | D103 | C3 | v3.8.0 M9 | — | 27.1% | — | HIGH | Cycle 3: 133/491 closed, 358 open (unchanged) |
|
||||
|
||||
## Daily Snapshot - 2026-04-18
|
||||
## Scope Expansion Alert (Cycle 2 → Cycle 3, ~60 min window)
|
||||
|
||||
| Milestone | Completed % | Open Issues | Risk Assessment |
|
||||
|-----------|-------------|-------------|-----------------|
|
||||
| v3.2.0 (M3) | 25.7% | 959 | 🔴 High |
|
||||
| v3.3.0 (M4) | 35.5% | 218 | 🔴 High |
|
||||
| v3.4.0 (M5) | 35.5% | 287 | 🔴 High |
|
||||
| v3.5.0 (M6) | 18.1% | 1,130 | 🔴 High |
|
||||
| v3.6.0 (M7) | 32.8% | 332 | 🔴 High |
|
||||
| v3.7.0 (M8) | 41.8% | 608 | 🟡 Medium |
|
||||
| v3.8.0 (M9) | 28.2% | 367 | 🟡 Medium |
|
||||
| v3.9.0 | 37.5% | 40 | 🟢 Low |
|
||||
**CRITICAL**: In the 60-minute window between Cycle 2 and Cycle 3, all active milestones gained new open issues with minimal closures:
|
||||
|
||||
| Milestone | Open C2 | Open C3 | Delta | Closed C2 | Closed C3 | Delta |
|
||||
|-----------|---------|---------|-------|-----------|-----------|-------|
|
||||
| v3.1.0 M2 | 3 | 5 | **+2** | 108 | 108 | 0 |
|
||||
| v3.2.0 M3 | 776 | 802 | **+26** | 269 | 269 | 0 |
|
||||
| v3.3.0 M4 | 148 | 157 | **+9** | 109 | 109 | 0 |
|
||||
| v3.4.0 M5 | 233 | 242 | **+9** | 139 | 139 | 0 |
|
||||
| v3.5.0 M6 | 1032 | 1052 | **+20** | 210 | 212 | +2 |
|
||||
| v3.6.0 M7 | 296 | 314 | **+18** | 152 | 152 | 0 |
|
||||
| v3.7.0 M8 | 548 | 574 | **+26** | 427 | 427 | 0 |
|
||||
|
||||
**Total new open issues in 60 min: +110** | **Total new closed issues in 60 min: +2**
|
||||
|
||||
## Milestone Summaries
|
||||
|
||||
### v3.0.0 (M1) — CLOSED
|
||||
- **Status**: Complete
|
||||
- **Closed**: 2026-03-16 (29 days after due date 2026-02-15)
|
||||
- **Issues**: 163/163 closed (100%)
|
||||
- **Notes**: First milestone completed. Established local source-code workflow, git worktree sandbox, SQLite persistence, actor-based LLM path.
|
||||
|
||||
### v3.1.0 (M2) — CLOSED (scope expanding!)
|
||||
- **Status**: Closed but scope expanding — 5 open issues (was 3 at Cycle 2)
|
||||
- **Closed**: 2026-03-16 (22 days after due date 2026-02-22)
|
||||
- **Issues**: 108/113 closed (94.7%) — 5 open
|
||||
- **Notes**: Actor compiler and LLM integration complete. Open issue count growing despite milestone closure. LangGraph StateGraph compilation, MCP adapter, tool router operational.
|
||||
|
||||
### v3.2.0 (M3) — CRITICAL RISK
|
||||
- **Status**: Open — 46 days overdue (due 2026-02-26)
|
||||
- **Issues**: 269/1071 closed (25.1%) — 802 open (+26 in 60 min)
|
||||
- **Scope**: Massively expanded (was ~300 issues, now 1071 and growing)
|
||||
- **Blockers**: Decision recording system, invariant management, plan correction engine (revert/append modes)
|
||||
- **Key features**: `plan tree`, `plan explain`, `invariant add/list/remove`, `plan correct`
|
||||
- **Notes**: CI not running on master since 2026-03-14. E2E tests deleted (commit 8ea00f5). Scope growing faster than issues are being closed.
|
||||
|
||||
### v3.3.0 (M4) — CRITICAL RISK
|
||||
- **Status**: Open — 42 days overdue (due 2026-03-02)
|
||||
- **Issues**: 109/266 closed (41.0%) — 157 open (+9 in 60 min)
|
||||
- **Blockers**: Subplan spawning during execution, parallel subplan execution, three-way merge strategy, checkpoint creation and rollback
|
||||
- **Key features**: `plan rollback`, parallel execution with max_parallel, parent plan tracking
|
||||
- **Notes**: Depends on M3 completion for correction flow.
|
||||
|
||||
### v3.4.0 (M5) — HIGH RISK
|
||||
- **Status**: Open — 38 days overdue (due 2026-03-06)
|
||||
- **Issues**: 139/381 closed (36.5%) — 242 open (+9 in 60 min)
|
||||
- **Blockers**: ACMS v1 pipeline, context window management (hot/warm/cold tiers), 10k+ file indexing without timeout
|
||||
- **Key features**: `context list/add/show/clear`, budget enforcement, context assembly CLI
|
||||
- **Notes**: Context scaling is a major technical challenge. Budget constraints (max_file_size, max_total_size).
|
||||
|
||||
### v3.5.0 (M6) — CRITICAL RISK
|
||||
- **Status**: Open — 34 days overdue (due 2026-03-10)
|
||||
- **Issues**: 212/1264 closed (16.8%) — 1052 open (+20 in 60 min)
|
||||
- **Scope**: Massively expanded (was ~200 issues, now 1264 and growing)
|
||||
- **Blockers**: A2A facade session/plan lifecycle, event queue pub/sub, guard enforcement, autonomy hardening
|
||||
- **Key features**: Hierarchical decomposition (4+ levels), parallel execution (10+ concurrent), realistic porting task
|
||||
- **Notes**: Server stubs moved to M9 (ADR-047, ADR-048). TUI features moved to M8. Largest milestone by scope.
|
||||
|
||||
### v3.6.0 (M7) — HIGH RISK
|
||||
- **Status**: Open — 16 days overdue (due 2026-03-28)
|
||||
- **Issues**: 152/466 closed (32.6%) — 314 open (+18 in 60 min)
|
||||
- **Blockers**: Advanced context strategies, additional LLM backends, container tool execution, pluggable scope chain
|
||||
- **Key features**: ACP→A2A rename, cost/session budgets, safety profiles, E2E workflow spec tests
|
||||
- **Notes**: Advanced concepts milestone. Abstraction layers for TUI/Server included.
|
||||
|
||||
### v3.7.0 (M8) — HIGH RISK
|
||||
- **Status**: Open — No deadline assigned
|
||||
- **Issues**: 427/1001 closed (42.6%) — 574 open (+26 in 60 min)
|
||||
- **Blockers**: Textual TUI MainScreen, persona system (YAML-based), reference/command input (@, /, ! modes)
|
||||
- **Key features**: TuiMaterializer A2A integration, session persistence (SQLite), Dracula theme, multi-session tabs
|
||||
- **Notes**: TUI features moved here from M6. Highest absolute completion count (427 closed). ADR-044, ADR-045, ADR-046.
|
||||
|
||||
### v3.8.0 (M9) — HIGH RISK
|
||||
- **Status**: Open — No deadline assigned
|
||||
- **Issues**: 133/491 closed (27.1%) — 358 open (unchanged)
|
||||
- **Blockers**: A2A JSON-RPC 2.0 wire format, stdio/HTTP transports, LangGraph Platform RemoteGraph, FastAPI + A2A SDK
|
||||
- **Key features**: Authentication/authorization (API tokens, RBAC), entity sync, PostgreSQL backend, Docker/K8s/Helm
|
||||
- **Notes**: Server implementation. ADR-047 (A2A adoption), ADR-048 (server architecture). No deadline.
|
||||
|
||||
### v3.9.0 — LOW RISK
|
||||
- **Status**: Open — No deadline assigned
|
||||
- **Issues**: 4/21 closed (19.0%) — 17 open (unchanged)
|
||||
- **Notes**: Documentation and feature updates. Lowest priority milestone.
|
||||
|
||||
## Risk Register
|
||||
|
||||
| Risk | Severity | Milestones Affected | Status | Mitigation |
|
||||
|------|----------|---------------------|--------|------------|
|
||||
| All active milestones overdue | CRITICAL | M3-M7 | Active | Increase automation, parallel workers |
|
||||
| Scope expanding faster than closing (+110 open in 60 min) | CRITICAL | All | ESCALATING | Scope freeze, prioritization |
|
||||
| CI not running on master (since 2026-03-14) | CRITICAL | All | Open (#8508) | Fix CI trigger configuration |
|
||||
| Massive scope expansion (M3: 1071, M6: 1264 issues) | CRITICAL | M3, M6 | Active | Scope management, prioritization |
|
||||
| 802 open issues in M3 alone | CRITICAL | M3 | Active | Focus automation on M3 |
|
||||
| 1052 open issues in M6 | CRITICAL | M6 | Active | Parallel worker pools |
|
||||
| E2E tests deleted (commit 8ea00f5, issue #8459) | HIGH | All | Open | Restore E2E test suite |
|
||||
| Open PR #8380 unmerged (Day 103 Timeline Update) | MEDIUM | Timeline | Open | Superseded by PR #8582 |
|
||||
| v3.1.0 closed with 5 open issues (growing) | MEDIUM | M2 | ESCALATING | Resolve remaining issues, prevent scope creep |
|
||||
|
||||
## Timeline Update — 2026-04-16 (Cycle 2 Verification)
|
||||
|
||||
### Schedule Adherence Updates
|
||||
|
||||
| Date | Day | Cycle | Milestone | Planned % | Actual % | Delta | Risk | Notes |
|
||||
|------|-----|-------|-----------|-----------|----------|-------|------|-------|
|
||||
| 2026-04-14 | D104 | C2 | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Day 104: 269/1045 closed, 776 open |
|
||||
| 2026-04-14 | D104 | C2 | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Day 104: 109/257 closed, 148 open |
|
||||
| 2026-04-14 | D104 | C2 | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Day 104: 139/372 closed, 233 open |
|
||||
| 2026-04-14 | D104 | C2 | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Day 104: 210/1242 closed, 1032 open |
|
||||
| 2026-04-14 | D104 | C2 | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Day 104: 152/448 closed, 296 open |
|
||||
| 2026-04-14 | D104 | C2 | v3.7.0 M8 | — | 43.8% | — | HIGH | Day 104: 427/975 closed, 548 open |
|
||||
| 2026-04-14 | D104 | C2 | v3.8.0 M9 | — | 27.1% | — | HIGH | Day 104: 133/491 closed, 358 open |
|
||||
| 2026-04-15 | D105 | C2 | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Day 105: no changes detected |
|
||||
| 2026-04-15 | D105 | C2 | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Day 105: no changes detected |
|
||||
| 2026-04-15 | D105 | C2 | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Day 105: no changes detected |
|
||||
| 2026-04-15 | D105 | C2 | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Day 105: no changes detected |
|
||||
| 2026-04-15 | D105 | C2 | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Day 105: no changes detected |
|
||||
| 2026-04-15 | D105 | C2 | v3.7.0 M8 | — | 43.8% | — | HIGH | Day 105: no changes detected |
|
||||
| 2026-04-15 | D105 | C2 | v3.8.0 M9 | — | 27.1% | — | HIGH | Day 105: no changes detected |
|
||||
| 2026-04-16 | D106 | C2 | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Cycle 2 verification: no milestone changes since Day 104 |
|
||||
| 2026-04-16 | D106 | C2 | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Cycle 2 verification: no milestone changes since Day 104 |
|
||||
| 2026-04-16 | D106 | C2 | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Cycle 2 verification: no milestone changes since Day 104 |
|
||||
| 2026-04-16 | D106 | C2 | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Cycle 2 verification: no milestone changes since Day 104 |
|
||||
| 2026-04-16 | D106 | C2 | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Cycle 2 verification: no milestone changes since Day 104 |
|
||||
| 2026-04-16 | D106 | C2 | v3.7.0 M8 | — | 43.8% | — | HIGH | Cycle 2 verification: no milestone changes since Day 104 |
|
||||
| 2026-04-16 | D106 | C2 | v3.8.0 M9 | — | 27.1% | — | HIGH | Cycle 2 verification: no milestone changes since Day 104 |
|
||||
|
||||
### Verification Summary (Cycle 2)
|
||||
|
||||
- **Snapshot**: Milestone data verified -- no changes since Cycle 1
|
||||
- **Milestones at risk**: v3.2.0 (OVERDUE 49d), v3.3.0 (OVERDUE 45d), v3.4.0 (OVERDUE 41d), v3.5.0 (OVERDUE 37d), v3.6.0 (OVERDUE 19d)
|
||||
- **Notes**: All M3-M7 milestones remain overdue. No milestone closures detected. PR #10062 (Day 106 update) pending merge.
|
||||
|
||||
|
||||
## Automation Activity Log
|
||||
|
||||
| Date | Day | Cycle | Agent | Action |
|
||||
|------|-----|-------|-------|--------|
|
||||
| 2026-04-13 | D103 | C1 | AUTO-TIME | Supervisor started, tracking issue #8519 created |
|
||||
| 2026-04-13 | D103 | C2 | AUTO-TIME-1 | Timeline updated on branch auto-time-1-day103-cycle2, PR #8582 created |
|
||||
| 2026-04-13 | D103 | C3 | AUTO-TIME-2 | Timeline updated on branch auto-time-2-day103-cycle3, scope expansion alert added |
|
||||
| 2026-04-16 | D106 | C2 | AUTO-TIME-3 | Timeline verified on branch auto-time-3-day106-cycle2, PR #10062 created |
|
||||
|
||||
---
|
||||
**Automated by CleverAgents Bot**
|
||||
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor
|
||||
|
||||
Reference in New Issue
Block a user