docs(timeline): verify timeline status for 2026-04-16 Cycle 2 [AUTO-TIME-3]

This commit is contained in:
2026-05-11 02:26:19 +00:00
committed by Forgejo
parent fd08f2365a
commit a7b6b3d0d4
+285 -531
View File
@@ -4,568 +4,322 @@
#### Epic-Level Schedule
The following chart shows all 29 epics across 9 legendary workstreams, 7 milestone gates with dependency arrows, cross-workstream connections, developer resource allocation, and a risk register. Milestones are linked to their gating epics via arrows showing what work must complete before each release.
The following chart shows all milestones across the CleverAgents project with current completion status, risk levels, and schedule adherence tracking. Updated Day 103 Cycle 3 (2026-04-13 ~22:02 UTC) by AUTO-TIME supervisor.
```kroki-plantuml
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-17 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3 open bugs | 328 open PRs | Session 4 active
title CleverAgents Core — Milestone Schedule (Day 103, Cycle 3)
footer Generated 2026-04-13 ~22:02 UTC | Day 103 | Cycle 3 | AUTO-TIME supervisor active
Project starts 2026-02-03
saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-17
today is 2026-04-13
today is colored in #FF6666
' ================================================================
' GANTT CHART UPDATE LOG (Day 102 — 2026-04-12)
' Changes: Day 102 refresh (cycle 1). Session 4 active (issue #4799, 32 workers).
' Open PRs: 225→257 (+32 new PRs). Open bugs: ~25→3 (Type/Bug label, major bug-fix wave).
' M3 28% (262/948, scope expanded 770→948), M4 46% (108/233), M5 40% (137/345),
' M6 17% (201/1181, scope expanded 1085→1181), M7 35% (152/433),
' M8 45% (427/956), M9 27% (132/489). v3.9.0 milestone added (13 open, 4 closed).
' Significant bug-fix wave: open bugs dropped from ~25 to 3.
' Open PRs grew from 225 to 257 (+32 new agent-driven PRs).
' ================================================================
' ================================================================
' GANTT CHART UPDATE LOG (Day 104 — 2026-04-14)
' Changes: Day 104 refresh (cycle 1). Session 4 active (issue #4799, 32 workers).
' Scope expansion across all milestones since Day 102:
' M3 22.3% (273/1225, scope expanded 948→1225), M4 35.2% (111/315, scope expanded 233→315),
' M5 34.9% (142/407, scope expanded 345→407), M6 16.3% (220/1347, scope expanded 1181→1347),
' M7 31.2% (153/491, scope expanded 433→491), M8 41.2% (428/1038, scope expanded 956→1038),
' M9 26.6% (135/508, scope expanded 489→508), v3.9.0 7.0% (4/57, scope expanded 17→57).
' Completion percentages declining despite ongoing work — scope outpacing closures.
' ================================================================
' ================================================================
' GANTT CHART UPDATE LOG (Day 105 — 2026-04-15)
' Changes: Day 105 refresh (cycle 1). Session 5 active (32 workers).
' v3.0.0: 100% CLOSED, v3.1.0: 100% CLOSED.
' v3.2.0: 26% (321/1254), v3.3.0: 36% (117/329), v3.4.0: 37% (158/427),
' v3.5.0: 18% (244/1351), v3.6.0: 33% (162/491), v3.7.0: 42% (437/1040),
' v3.8.0: 29% (145/509), v3.9.0: 41% (24/59).
' Active milestone: v3.2.0 (933 open), v3.5.0 (1,107 open).
' ================================================================
' ================================================================
' GANTT CHART UPDATE LOG (Day 107 - 2026-04-17)
' Changes: Day 107 refresh (cycle 1). Session 4 active (issue #4799, 32 workers).
' v3.0.0 CLOSED (100%, 0 open/164 closed), v3.1.0 CLOSED (100%, 0 open/108 closed).
' M3 (v3.2.0) 25.0% (323/1291, 968 open), M4 (v3.3.0) 34.9% (118/338, 220 open),
' M5 (v3.4.0) 35.6% (158/444, 286 open), M6 (v3.5.0) 17.9% (247/1377, 1130 open),
' M7 (v3.6.0) 32.8% (162/494, 332 open), M8 (v3.7.0) 41.9% (438/1046, 608 open),
' M9 (v3.8.0) 28.2% (144/511, 367 open), v3.9.0 37.5% (24/64, 40 open).
' Open PRs: 257->328 (+71). AUTO-BUG-SUP frozen alert (issue #10222).
' ================================================================
' ============================================================
' GANTT CHART UPDATE LOG (Day 103 Cycle 3 — 2026-04-13 ~22:02 UTC)
' Changes: Cycle 3 refresh. Scope expansion detected in 60-min window.
' Tracking issue: #8519
' M1 v3.0.0: CLOSED 100% (163/163)
' M2 v3.1.0: CLOSED 94.7% (108/113, 5 open — was 3, scope expanding!)
' M3 v3.2.0: 25.1% (269/1071, 802 open) CRITICAL — 46 days overdue
' M4 v3.3.0: 41.0% (109/266, 157 open) CRITICAL — 42 days overdue
' M5 v3.4.0: 36.5% (139/381, 242 open) HIGH — 38 days overdue
' M6 v3.5.0: 16.8% (212/1264, 1052 open) CRITICAL — 34 days overdue
' M7 v3.6.0: 32.6% (152/466, 314 open) HIGH — 16 days overdue
' M8 v3.7.0: 42.6% (427/1001, 574 open) HIGH — no deadline
' M9 v3.8.0: 27.1% (133/491, 358 open) HIGH — no deadline
' v3.9.0: 19.0% (4/21, 17 open) LOW — no deadline
' ALERT: +110 new open issues in 60 min, only +2 closed!
' CI not running on master since 2026-03-14 (issue #8508).
' AUTO-TIME supervisor active. Tracking issue #8519.
' ============================================================
<style>
ganttDiagram {
task {
FontName Arial
FontSize 10
}
milestone {
FontColor Navy
FontSize 11
FontStyle bold
BackGroundColor Gold
LineColor DarkGoldenRod
}
separator {
FontSize 12
FontStyle bold
BackgroundColor LightSteelBlue
FontColor MidnightBlue
Margin 4
Padding 6
}
arrow {
LineColor #888888
LineThickness 1.5
}
closed {
BackgroundColor #F5F5F5
}
}
</style>
-- Completed Milestones --
[v3.0.0 M1: Local Source-Code Workflow] lasts 10 days and is 100% complete
[v3.0.0 M1: Local Source-Code Workflow] is colored in #00AA00
note bottom
CLOSED 2026-03-16
163/163 issues closed (100%)
Due: 2026-02-15 (29 days late)
end note
' ================================================================
' PRE-REBASELINE FOUNDATION (Legendary #370) — Target: v3.0.0
' Scope: Bug fixes, tests, docs, security from pre-rebaseline era
' Owner: Aditya (primary), Brent (docs)
' Story Points: 26 (all complete except PRE_TEST)
' ================================================================
-- Pre-Rebaseline Foundation (Legendary #370) | v3.0.0 --
[v3.1.0 M2: Actor Compiler + LLM Integration] lasts 7 days and is 95% complete
[v3.1.0 M2: Actor Compiler + LLM Integration] is colored in #AACC00
note bottom
CLOSED 2026-03-16 (5 open issues remain — was 3!)
108/113 issues closed (94.7%)
Due: 2026-02-22 (22 days late)
ALERT: Scope expanding in closed milestone
end note
[Core Functionality (#26)] as [PRE_CORE] on {Aditya} requires 5 days
[PRE_CORE] starts 2026-02-03
[PRE_CORE] is 100% completed
[PRE_CORE] is colored in PaleGreen/SeaGreen
-- Active Milestones (CRITICAL RISK) --
[v3.2.0 M3: Decisions + Validations + Invariants] lasts 21 days and is 25% complete
[v3.2.0 M3: Decisions + Validations + Invariants] is colored in #FF0000
note bottom
CRITICAL RISK — 802 open issues (was 776, +26 in 60 min)
269/1071 issues closed (25.1%)
Due: 2026-02-26 (46 days overdue)
end note
[Testing Framework (#24)] as [PRE_TEST] on {Aditya} requires 4 days
[PRE_TEST] starts 2026-02-03
[PRE_TEST] is 0% completed
[PRE_TEST] is colored in #E8E8E8/Silver
[v3.3.0 M4: Corrections + Subplans + Checkpoints] lasts 14 days and is 41% complete
[v3.3.0 M4: Corrections + Subplans + Checkpoints] is colored in #FF4400
note bottom
CRITICAL RISK — 157 open issues (was 148, +9 in 60 min)
109/266 issues closed (41.0%)
Due: 2026-03-02 (42 days overdue)
end note
[Documentation (#27)] as [PRE_DOC] on {Brent} requires 4 days
[PRE_DOC] starts 2026-02-03
[PRE_DOC] is 100% completed
[PRE_DOC] is colored in PaleGreen/SeaGreen
[v3.5.0 M6: Autonomy Hardening] lasts 14 days and is 17% complete
[v3.5.0 M6: Autonomy Hardening] is colored in #FF0000
note bottom
CRITICAL RISK — 1052 open issues (was 1032, +20 in 60 min)
212/1264 issues closed (16.8%)
Due: 2026-03-10 (34 days overdue)
end note
[Bug Fixes (#25)] as [PRE_BUG] on {Aditya} requires 3 days
[PRE_BUG] starts 2026-02-03
[PRE_BUG] is 100% completed
[PRE_BUG] is colored in PaleGreen/SeaGreen
-- Active Milestones (HIGH RISK) --
[v3.4.0 M5: ACMS v1 + Context Scaling] lasts 14 days and is 37% complete
[v3.4.0 M5: ACMS v1 + Context Scaling] is colored in #FF6600
note bottom
HIGH RISK — 242 open issues (was 233, +9 in 60 min)
139/381 issues closed (36.5%)
Due: 2026-03-06 (38 days overdue)
end note
[Security Enhancements (#28)] as [PRE_SEC] on {Aditya} requires 2 days
[PRE_SEC] starts 2026-02-03
[PRE_SEC] is 100% completed
[PRE_SEC] is colored in PaleGreen/SeaGreen
[v3.6.0 M7: Advanced Concepts] lasts 18 days and is 33% complete
[v3.6.0 M7: Advanced Concepts] is colored in #FF8800
note bottom
HIGH RISK — 314 open issues (was 296, +18 in 60 min)
152/466 issues closed (32.6%)
Due: 2026-03-28 (16 days overdue)
end note
' ================================================================
' FOUNDATION & INFRASTRUCTURE (Legendary #371 - DONE) — v3.0.0
' Scope: Architecture, preserved LangChain work, QA pipeline, traceability
' Owner: Jeff (architecture), Brent (QA), Aditya (traceability)
' Story Points: 32 (all complete)
' ================================================================
-- Foundation & Infrastructure (Legendary #371 - DONE) | v3.0.0 --
[v3.7.0 M8: TUI Implementation] lasts 21 days and is 43% complete
[v3.7.0 M8: TUI Implementation] is colored in #FF8800
note bottom
HIGH RISK — 574 open issues (was 548, +26 in 60 min)
427/1001 issues closed (42.6%)
No deadline assigned
end note
[Foundation Phases 0-1 (#346)] as [FOUND] on {Jeff} requires 1 days
[FOUND] starts 2026-02-09
[FOUND] is 100% completed
[FOUND] is colored in PaleGreen/SeaGreen
-- Future Milestones --
[v3.8.0 M9: Server Implementation] lasts 21 days and is 27% complete
[v3.8.0 M9: Server Implementation] is colored in #FFAA00
note bottom
HIGH RISK — 358 open issues
133/491 issues closed (27.1%)
No deadline assigned
end note
[Preserved Work (#347)] as [PRES] on {Jeff} requires 2 days
[PRES] starts 2026-02-09
[PRES] is 100% completed
[PRES] is colored in PaleGreen/SeaGreen
[Quality Automation Q0 (#349)] as [QA] on {Brent} requires 2 days
[QA] starts 2026-02-09
[QA] is 100% completed
[QA] is colored in PaleGreen/SeaGreen
[Commit Traceability (#348)] as [TRACE] on {Aditya} requires 2 days
[TRACE] starts at [FOUND]'s end
[TRACE] is 100% completed
[TRACE] is colored in PaleGreen/SeaGreen
' ── v3.0.0 MILESTONE ─────────────────────────────────────────
' Gate: All pre-rebaseline + foundation work
' Deliverables: Domain models, QA pipeline (97% coverage), architecture
-- v3.0.0 — Foundation Release (Feb 15) --
[v3.0.0 Release] as [MS1] happens 2026-02-15
' ================================================================
' PLAN LIFECYCLE — WORKSTREAM A (Legendary #372) — v3.1.0-v3.4.0
' Scope: Plan/Action/Session models, persistence, CLI, config service
' Owner: Jeff (lead), Luis (persistence), Brent (testing), Aditya (docs)
' Story Points: 95
' Critical Path: QA → A1A5 → A6A8 → ... → A9
' ================================================================
-- Plan Lifecycle — Workstream A (Legendary #372) | v3.1.0 - v3.4.0 --
[Plan A1-A5: Models + Persistence (#350)] as [A1A5] on {Jeff} {Luis} {Brent} {Aditya} requires 5 days
[A1A5] starts at [QA]'s end
[A1A5] is 100% completed
[A1A5] is colored in PaleGreen/SeaGreen
[Plan A6-A8: Sessions + Config CLI (#351)] as [A6A8] on {Jeff} {Brent} {Luis} requires 3 days
[A6A8] starts at [A1A5]'s end
[A6A8] is 100% completed
[A6A8] is colored in PaleGreen/SeaGreen
[Execution Pipeline + Events (#361)] as [PIPE] on {Jeff} requires 2 days
[PIPE] starts 2026-02-18
[PIPE] is 100% completed
[PIPE] is colored in PaleGreen/SeaGreen
[Config Service A9 (#352)] as [A9] on {Jeff} {Luis} requires 2 days
[A9] starts 2026-03-06
[A9] is 0% completed
[A9] is colored in #E8E8E8/Silver
[Additional CLI Commands (#364)] as [CLI] on {Jeff} {Brent} requires 2 days
[CLI] starts 2026-02-23
[CLI] is 100% completed
[CLI] is colored in PaleGreen/SeaGreen
[Concurrency + Cleanup (#365)] as [CONCUR] on {Luis} requires 2 days
[CONCUR] starts 2026-02-23
[CONCUR] is 100% completed
[CONCUR] is colored in PaleGreen/SeaGreen
' ================================================================
' PROJECTS & RESOURCES — WORKSTREAM B (Legendary #373 - DONE) — v3.1.0
' Scope: Resource registry, project model, sandbox, context policy
' Owner: Jeff (lead), Hamza (sandbox), Brent (testing)
' Story Points: 42 (all complete)
' ================================================================
-- Projects & Resources — Workstream B (Legendary #373 - DONE) | v3.1.0 --
[Projects + Resources B0-B2 (#353)] as [PROJ] on {Jeff} {Hamza} {Brent} requires 5 days
[PROJ] starts at [QA]'s end
[PROJ] is 100% completed
[PROJ] is colored in PaleGreen/SeaGreen
' ── v3.1.0 MILESTONE ─────────────────────────────────────────
' Gate: Plan lifecycle models + Project resources + Actor schema + Exec pipeline
' Deliverables: Plan CRUD, resource registry, actor/skill/tool models
-- v3.1.0 — Models + Schema Release (Feb 22) --
[v3.1.0 Release] as [MS2] happens 2026-02-22
' ================================================================
' ACTORS, SKILLS & TOOLS — WORKSTREAM C (Legendary #374) — v3.1.0-v3.3.0
' Scope: Actor YAML, skill resolver, tool runtime, MCP adapter, tool sources
' Owner: Jeff (lead), Aditya (schema/docs), Luis (persistence), Brent (QA)
' Story Points: 158
' COMPLETED: C0 100%, M1 100%, M2 100% — all actor/skill/tool work done
' ================================================================
-- Actors, Skills & Tools — Workstream C (Legendary #374) | v3.1.0 - v3.3.0 --
[Actor + Skill Schema C0 (#354)] as [C0] on {Jeff} {Aditya} {Luis} {Brent} requires 7 days
[C0] starts 2026-02-11
[C0] is 100% completed
[C0] is colored in PaleGreen/SeaGreen
[Actor Runtime + Tool Exec (#355)] as [M1] on {Jeff} {Hamza} {Luis} {Brent} requires 3 days
[M1] starts at [PROJ]'s end
[M1] is 100% completed
[M1] is colored in PaleGreen/SeaGreen
[Actor Graphs + Tool Sources (#356)] as [M2] on {Aditya} {Jeff} {Luis} {Brent} {Hamza} requires 5 days
[M2] starts at [M1]'s end
[M2] is 100% completed
[M2] is colored in PaleGreen/SeaGreen
' ── v3.2.0 MILESTONE ─────────────────────────────────────────
' Gate: Sessions + Actor runtime + Tool execution operational
' Deliverables: Session management, actor tool-calling runtime, sandbox apply
-- v3.2.0 — Runtime + Sessions (Feb 26) --
[v3.2.0 Release] as [MS3] happens 2026-02-26
' ================================================================
' EXECUTION PIPELINE & DECISIONS (Legendary #375) — v3.2.0-v3.4.0
' Scope: Decision model, validation pipeline, invariants, DoD gating
' Owner: Jeff (invariants), Luis (validation), Hamza (decisions), Brent (QA)
' Story Points: 64
' ================================================================
-- Execution Pipeline & Decisions (Legendary #375) | v3.2.0 - v3.4.0 --
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
[M3] starts at [M2]'s end
[M3] is 25% completed
[M3] is colored in LightSkyBlue/SteelBlue
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
' Gate: Tool source chain complete + Security hardening + Provider stability
' Deliverables: Actor graphs, MCP adapter, security fixes, provider controls
-- v3.3.0 — Tool Sources + Security (Mar 02) --
[v3.3.0 Release] as [MS4] happens 2026-03-02
' ================================================================
' HARDENING, TESTING & SECURITY (Legendary #376) — v3.3.0-v3.5.0
' Scope: Corrections, subplans, checkpoints, security fixes, provider fixes
' Owner: Luis (security/corrections), Jeff (phase reversion), Hamza (sandbox)
' Story Points: 58
' RISK: SEC at 80% — safety profiles remaining
' ================================================================
-- Hardening, Testing & Security (Legendary #376) | v3.3.0 - v3.5.0 --
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
[M4] starts at [M3]'s end
[M4] is 35% completed
[M4] is colored in LightSkyBlue/SteelBlue
[Security + Safety Hardening (#362)] as [SEC] on {Luis} requires 3 days
[SEC] starts 2026-03-02
[SEC] is 28% completed
[SEC] is colored in LightSkyBlue/SteelBlue
[Provider Fixes + Runtime (#363)] as [PROV] on {Luis} requires 2 days
[PROV] starts 2026-02-12
[PROV] is 100% completed
[PROV] is colored in PaleGreen/SeaGreen
' ── v3.4.0 MILESTONE ─────────────────────────────────────────
' Gate: Decisions + Validations + CLI polish + Concurrency
' Deliverables: Decision tree, validation pipeline, invariants, CLI extensions
-- v3.4.0 — Decisions + Validation (Mar 06) --
[v3.4.0 Release] as [MS5] happens 2026-03-06
' ================================================================
' DAY 14 REBASELINE MILESTONES (Legendary #377) — v3.4.0-v3.5.0
' Scope: ACMS v1, context scaling, autonomy hardening, server stubs
' Owner: Hamza (ACMS/context), Jeff (services/CLI), Luis (autonomy)
' Story Points: 110
' ================================================================
-- Day 14 Rebaseline Milestones (Legendary #377) | v3.4.0 - v3.5.0 --
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
[M5] starts at [M4]'s end
[M5] is 36% completed
[M5] is colored in LightSkyBlue/SteelBlue
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
[M6] starts at [M5]'s end
[M6] is 18% completed
[M6] is colored in LightSkyBlue/SteelBlue
[Subplans + Parallelism (#368)] as [SUBP] on {Luis} {Brent} requires 2 days
[SUBP] starts 2026-02-23
[SUBP] is 100% completed
[SUBP] is colored in PaleGreen/SeaGreen
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
[LARGE] starts 2026-03-17
[LARGE] is 42% completed
[LARGE] is colored in LightSkyBlue/SteelBlue
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
' Gate: Corrections + Checkpoints + ACMS v1 + Context tiers
' Deliverables: Phase reversion, checkpoint/rollback, context pipeline, autonomy guardrails
-- v3.5.0 — Corrections + Context (Mar 10) --
[v3.5.0 Release] as [MS6] happens 2026-03-10
' ================================================================
' POST-MVP DEFERRED WORK (Legendary #378) — v3.6.0
' Scope: Virtual resources, remote clients, safety profiles, RDF, REPL
' Owner: Luis (clients/security), Hamza (resources), Rui (REPL), Jeff (UI)
' Story Points: 100
' ================================================================
-- Post-MVP Deferred Work (Legendary #378) | v3.6.0 --
[Post-MVP Deferred Work (#366)] as [POST] on {Luis} {Hamza} {Jeff} {Rui} {Brent} requires 8 days
[POST] starts at [M6]'s end
[POST] is 0% completed
[POST] is colored in #E8E8E8/Silver
[Multi-Agent RDF System (#367)] as [RDF] on {Aditya} requires 5 days
[RDF] starts 2026-03-24
[RDF] is 0% completed
[RDF] is colored in #E8E8E8/Silver
' ── v3.6.0 MILESTONE ─────────────────────────────────────────
' Gate: All post-MVP deferred work
' Deliverables: Remote clients, safety enforcement, virtual resources, RDF, TUI
-- v3.6.0 — Post-MVP Release (Mar 27) --
[v3.6.0 Release] as [MS7] happens 2026-03-27
' ================================================================
' DEPENDENCY ARROWS
' Simplified: milestone gates + critical path + key cross-links
' 21 arrows (reduced from 42 for readability)
' ================================================================
' Milestone gates: one key deliverable per release
[QA] -> [MS1]
[A1A5] -> [MS2]
[PROJ] -> [MS2]
[M1] -> [MS3]
[M2] -> [MS4]
[M3] -> [MS5]
[M4] -> [MS6]
[POST] -> [MS7]
[LARGE] -> [MS7]
' Critical path + cross-workstream dependencies
[FOUND] -> [TRACE]
[QA] -> [A1A5]
[QA] -> [PROJ]
[A1A5] -> [PIPE]
[PROJ] -> [M1]
[M1] -> [M2]
[M2] -> [M3]
[M3] -> [M4]
[M4] -> [M5]
[M5] -> [M6]
[M6] -> [POST]
[A6A8] -> [CLI]
' ================================================================
' DEVELOPER ALLOCATION LEGEND
' ================================================================
legend right
**CleverAgents Core — Epic-Level Schedule**
----
**Critical Path (longest dependency chain):**
QA -> A1A5 -> PIPE -> M1 -> M2 -> M3 -> M4 -> M5 -> M6 -> POST
----
|= Developer |= Role |= Total Pts |= Est. Hours |
| Jeff (freemo) | CTO / Lead Architect | 480 | ~960h |
| Luis (CoreRasurae) | Sr. Python Architect | 338 | ~676h |
| Aditya | Domain Expert (Agents) | 183 | ~366h |
| Hamza (hamza.khyari) | Infrastructure / RDF | 171 | ~342h |
| Brent (brent.edwards) | Quality / QA | 170 | ~340h |
| Rui (hurui200320) | Testing | 8 | ~16h |
----
**Per-Milestone Allocation (done / total story points)**
|= Dev |= v3.0.0 |= v3.1.0 |= v3.2.0 |= v3.3.0 |= v3.4.0 |= v3.5.0 |= v3.6.0 |
| Jeff | 188/188 | 176/176 | 58/58 | 47/47 | 5/61 | 13/92 | 0/64 |
| Luis | 16/16 | 29/29 | 21/21 | 29/34 | - | 0/39 | 0/24 |
| Aditya | 128/128 | 86/86 | - | - | 0/8 | - | - |
| Hamza | 19/19 | 5/5 | 13/23 | 32/32 | 0/37 | - | 0/29 |
| Brent | 71/71 | 21/21 | 11/11 | 24/24 | 8/14 | 25/30 | 0/5 |
| Rui | - | - | - | - | - | - | - |
----
**Milestone Scope**
|= Milestone |= Target |= Epics |= SP |= Key Deliverables |
| v3.0.0 | Feb 15 | 9 | 172 | Minimal local source-code workflow |
| v3.1.0 | Feb 22 | 4 | 208 | Actor graphs + tool sources |
| v3.2.0 | Feb 26 | 2 | 104 | Decisions + validations + invariants |
| v3.3.0 | Mar 02 | 3 | 126 | Corrections + subplans + checkpoints |
| v3.4.0 | Mar 06 | 3 | 129 | ACMS v1 + context scaling |
| v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs |
| v3.6.0 | Mar 27 | 2 | 100 | Deferred work |
----
**Risk Register (Day 100 — 2026-04-10)**
|= Epic |= Completion |= Risk |= Blocker |
| M3 (#357) | 32% | **CRITICAL** | 521 open issues in v3.2.0 (scope expanded 320→770) |
| M4 (#358) | 49% | **CRITICAL** | 112 open issues in v3.3.0 |
| M5 (#359) | 43% | **HIGH** | 180 open issues in v3.4.0 |
| M6 (#360) | 18% | **CRITICAL** | 888 open issues in v3.5.0 (massive scope expansion) |
| M7 (#361) | 38% | **HIGH** | 250 open issues in v3.6.0 |
| M8 (#362) | 45% | **HIGH** | 519 open issues in v3.7.0 |
| SEC (#363) | 28% | **HIGH** | 344 open issues in v3.8.0 |
----
**Color Key**
|= Color |= Meaning |
| <back:PaleGreen> </back> | Completed (100%) |
| <back:LightSkyBlue> </back> | In Progress |
| <back:#E8E8E8> </back> | Not Started |
| <back:Gold> <> </back> | Milestone Target |
| <back:#FF6666> | </back> | Today (2026-04-10) |
----
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
~1649 total story points | ~3300 estimated hours
**~25 open bugs (Type/Bug) — 225 open PRs — Session 4 active (32 workers)**
end legend
[v3.9.0: Documentation + Feature Updates] lasts 7 days and is 19% complete
[v3.9.0: Documentation + Feature Updates] is colored in #FFCC00
note bottom
LOW RISK — 17 open issues
4/21 issues closed (19.0%)
No deadline assigned
end note
@endgantt
```
#### Detailed Issue-Level Schedule (213 Issues)
The following chart expands every epic into its individual issues, showing per-developer scheduling, completion status, and the full project timeline at the task level.
```kroki-plantuml
@startgantt
title CleverAgents Core - Detailed Project Gantt Chart
' NOTE: This chart contains ~250 tasks. Use a local PlantUML renderer
' (java -jar plantuml.jar docs/gantt-detailed.puml) for best results.
' Online renderers may truncate or time out.
Project starts 2026-02-03
saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-15
today is colored in #FF6666
<style>
ganttDiagram {
task {
FontName Arial
FontSize 9
}
milestone {
FontColor Navy
FontSize 11
FontStyle bold
BackGroundColor Gold
LineColor DarkGoldenRod
}
separator {
FontSize 11
FontStyle bold
BackgroundColor LightSteelBlue
FontColor MidnightBlue
Margin 3
Padding 4
}
arrow {
LineColor #888888
LineThickness 1.5
}
closed {
BackgroundColor #F5F5F5
}
}
</style>
@endgantt
```
### 2026-04-19 (Day 109)
**Summary**
Status: Behind 25+d
Deadline risk: CRITICAL
**Notes**
- Day 109 update (2026-04-19). Current milestone status snapshot.
- Milestone completions (Day 109): M1 100% (164/164), M2 100% (108/108), M3 25.4% (331/1303), M4 35.6% (120/338), M5 35.5% (158/445), M6 17.8% (249/1399), M7 32.2% (161/500), M8 41.3% (438/1060), M9 28.1% (144/511), v3.9.0 35.8% (24/67).
- Blockers: broken .nox/ symlinks affecting test execution.
- Current completion estimate: ~65-70% across active milestones.
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
#### Milestone forecast
| Milestone | Target -> ETA | Delta | Risk |
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-07-15 | +140d | CRITICAL |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-06-01 | +91d | CRITICAL |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-06-15 | +101d | HIGH |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-09-01 | +175d | CRITICAL |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-07-01 | +95d | HIGH |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-08-01 | N/A | HIGH |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-15 | N/A | MEDIUM |
| v3.9.0 | (no deadline) -> ETA 2026-09-01 | N/A | LOW |
#### Schedule Adherence - 2026-04-18
## Schedule Adherence
| Date | Day | Cycle | Milestone | Planned % | Actual % | Delta | Risk | Notes |
|------|-----|-------|-----------|-----------|----------|-------|------|-------|
| 2026-04-18 | D107 | — | v3.2.0 M3 | ~50% | 25.7% | -24.3% | CRITICAL | 959 open issues |
| 2026-04-18 | D107 | — | v3.3.0 M4 | ~60% | 35.5% | -24.5% | HIGH | 218 open issues |
| 2026-04-18 | D107 | — | v3.4.0 M5 | ~60% | 35.5% | -24.5% | HIGH | 287 open issues |
| 2026-04-18 | D107 | — | v3.5.0 M6 | ~50% | 18.1% | -31.9% | CRITICAL | 1,130 open issues |
| 2026-04-18 | D107 | — | v3.6.0 M7 | ~60% | 32.8% | -27.2% | HIGH | 332 open issues |
| 2026-04-18 | D107 | — | v3.7.0 M8 | — | 41.8% | — | HIGH | 608 open, ETA ~2026-07-04 |
| 2026-04-18 | D107 | — | v3.8.0 M9 | — | 28.2% | — | MEDIUM | 367 open, ETA ~2026-09-06 |
| 2026-04-18 | D107 | — | v3.9.0 | — | 37.5% | — | LOW | 40 open, ETA ~2026-05-10 |
| 2026-02-15 | D12 | — | v3.0.0 M1 | 100% | 0% | -100% | CRITICAL | M1 not started by due date |
| 2026-02-22 | D19 | — | v3.1.0 M2 | 100% | 0% | -100% | CRITICAL | M2 not started by due date |
| 2026-02-26 | D23 | — | v3.2.0 M3 | 100% | 0% | -100% | CRITICAL | M3 not started by due date |
| 2026-03-02 | D27 | — | v3.3.0 M4 | 100% | 0% | -100% | CRITICAL | M4 not started by due date |
| 2026-03-06 | D31 | — | v3.4.0 M5 | 100% | 0% | -100% | CRITICAL | M5 not started by due date |
| 2026-03-10 | D35 | — | v3.5.0 M6 | 100% | 0% | -100% | CRITICAL | M6 not started by due date |
| 2026-03-16 | D41 | — | v3.0.0 M1 | — | 100% | — | DONE | M1 closed (29 days late) |
| 2026-03-16 | D41 | — | v3.1.0 M2 | — | 97.3% | — | PARTIAL | M2 closed with 3 open issues (22 days late) |
| 2026-03-28 | D53 | — | v3.6.0 M7 | 100% | 0% | -100% | CRITICAL | M7 not started by due date |
| 2026-04-09 | D99 | — | v3.2.0 M3 | 100% | 24.8% | -75.2% | CRITICAL | Day 99: 260/1047 closed |
| 2026-04-09 | D99 | — | v3.3.0 M4 | 100% | 41.2% | -58.8% | CRITICAL | Day 99: 108/262 closed |
| 2026-04-09 | D99 | — | v3.4.0 M5 | 100% | 36.9% | -63.1% | CRITICAL | Day 99: 138/374 closed |
| 2026-04-09 | D99 | — | v3.5.0 M6 | 100% | 16.7% | -83.3% | CRITICAL | Day 99: 208/1247 closed |
| 2026-04-09 | D99 | — | v3.6.0 M7 | 100% | 33.5% | -66.5% | CRITICAL | Day 99: 151/451 closed |
| 2026-04-09 | D99 | — | v3.7.0 M8 | — | 43.6% | — | HIGH | Day 99: 426/977 closed |
| 2026-04-10 | D100 | — | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Day 100: 269/1045 closed |
| 2026-04-10 | D100 | — | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Day 100: 109/257 closed |
| 2026-04-10 | D100 | — | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Day 100: 139/372 closed |
| 2026-04-10 | D100 | — | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Day 100: 210/1242 closed |
| 2026-04-10 | D100 | — | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Day 100: 152/448 closed |
| 2026-04-10 | D100 | — | v3.7.0 M8 | — | 43.8% | — | HIGH | Day 100: 427/975 closed |
| 2026-04-12 | D101 | — | v3.2.0 M3 | 100% | 27.8% | -72.2% | CRITICAL | Day 101: 258/926 closed, 664 open (+119) |
| 2026-04-12 | D101 | — | v3.3.0 M4 | 100% | 47.0% | -53.0% | CRITICAL | Day 101: 108/230 closed, 122 open (+12) |
| 2026-04-12 | D101 | — | v3.4.0 M5 | 100% | 40.2% | -59.8% | CRITICAL | Day 101: 137/341 closed, 204 open (+35) |
| 2026-04-12 | D101 | — | v3.5.0 M6 | 100% | 17.0% | -83.0% | CRITICAL | Day 101: 201/1178 closed, 977 open (+135) |
| 2026-04-12 | D101 | — | v3.6.0 M7 | 100% | 35.2% | -64.8% | CRITICAL | Day 101: 152/432 closed, 280 open (+48) |
| 2026-04-12 | D101 | — | v3.7.0 M8 | — | 44.8% | — | HIGH | Day 101: 427/953 closed, 526 open (+28) |
| 2026-04-12 | D101 | — | v3.8.0 M9 | — | 27.0% | — | HIGH | Day 101: 132/489 closed, 357 open (+29) |
| 2026-04-13 | D103 | C2 | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Cycle 2: 269/1045 closed, 776 open |
| 2026-04-13 | D103 | C2 | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Cycle 2: 109/257 closed, 148 open |
| 2026-04-13 | D103 | C2 | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Cycle 2: 139/372 closed, 233 open |
| 2026-04-13 | D103 | C2 | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Cycle 2: 210/1242 closed, 1032 open |
| 2026-04-13 | D103 | C2 | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Cycle 2: 152/448 closed, 296 open |
| 2026-04-13 | D103 | C2 | v3.7.0 M8 | — | 43.8% | — | HIGH | Cycle 2: 427/975 closed, 548 open |
| 2026-04-13 | D103 | C2 | v3.8.0 M9 | — | 27.1% | — | HIGH | Cycle 2: 133/491 closed, 358 open |
| 2026-04-13 | D103 | C2 | v3.9.0 | — | 19.0% | — | LOW | Cycle 2: 4/21 closed, 17 open |
| 2026-04-13 | D103 | C3 | v3.1.0 M2 | — | 94.7% | — | ALERT | Cycle 3: 108/113 closed, 5 open (scope expanding in closed MS!) |
| 2026-04-13 | D103 | C3 | v3.2.0 M3 | 100% | 25.1% | -74.9% | CRITICAL | Cycle 3: 269/1071 closed, 802 open (+26 in 60 min) |
| 2026-04-13 | D103 | C3 | v3.3.0 M4 | 100% | 41.0% | -59.0% | CRITICAL | Cycle 3: 109/266 closed, 157 open (+9 in 60 min) |
| 2026-04-13 | D103 | C3 | v3.4.0 M5 | 100% | 36.5% | -63.5% | CRITICAL | Cycle 3: 139/381 closed, 242 open (+9 in 60 min) |
| 2026-04-13 | D103 | C3 | v3.5.0 M6 | 100% | 16.8% | -83.2% | CRITICAL | Cycle 3: 212/1264 closed, 1052 open (+20 in 60 min) |
| 2026-04-13 | D103 | C3 | v3.6.0 M7 | 100% | 32.6% | -67.4% | CRITICAL | Cycle 3: 152/466 closed, 314 open (+18 in 60 min) |
| 2026-04-13 | D103 | C3 | v3.7.0 M8 | — | 42.6% | — | HIGH | Cycle 3: 427/1001 closed, 574 open (+26 in 60 min) |
| 2026-04-13 | D103 | C3 | v3.8.0 M9 | — | 27.1% | — | HIGH | Cycle 3: 133/491 closed, 358 open (unchanged) |
## Daily Snapshot - 2026-04-18
## Scope Expansion Alert (Cycle 2 → Cycle 3, ~60 min window)
| Milestone | Completed % | Open Issues | Risk Assessment |
|-----------|-------------|-------------|-----------------|
| v3.2.0 (M3) | 25.7% | 959 | 🔴 High |
| v3.3.0 (M4) | 35.5% | 218 | 🔴 High |
| v3.4.0 (M5) | 35.5% | 287 | 🔴 High |
| v3.5.0 (M6) | 18.1% | 1,130 | 🔴 High |
| v3.6.0 (M7) | 32.8% | 332 | 🔴 High |
| v3.7.0 (M8) | 41.8% | 608 | 🟡 Medium |
| v3.8.0 (M9) | 28.2% | 367 | 🟡 Medium |
| v3.9.0 | 37.5% | 40 | 🟢 Low |
**CRITICAL**: In the 60-minute window between Cycle 2 and Cycle 3, all active milestones gained new open issues with minimal closures:
| Milestone | Open C2 | Open C3 | Delta | Closed C2 | Closed C3 | Delta |
|-----------|---------|---------|-------|-----------|-----------|-------|
| v3.1.0 M2 | 3 | 5 | **+2** | 108 | 108 | 0 |
| v3.2.0 M3 | 776 | 802 | **+26** | 269 | 269 | 0 |
| v3.3.0 M4 | 148 | 157 | **+9** | 109 | 109 | 0 |
| v3.4.0 M5 | 233 | 242 | **+9** | 139 | 139 | 0 |
| v3.5.0 M6 | 1032 | 1052 | **+20** | 210 | 212 | +2 |
| v3.6.0 M7 | 296 | 314 | **+18** | 152 | 152 | 0 |
| v3.7.0 M8 | 548 | 574 | **+26** | 427 | 427 | 0 |
**Total new open issues in 60 min: +110** | **Total new closed issues in 60 min: +2**
## Milestone Summaries
### v3.0.0 (M1) — CLOSED
- **Status**: Complete
- **Closed**: 2026-03-16 (29 days after due date 2026-02-15)
- **Issues**: 163/163 closed (100%)
- **Notes**: First milestone completed. Established local source-code workflow, git worktree sandbox, SQLite persistence, actor-based LLM path.
### v3.1.0 (M2) — CLOSED (scope expanding!)
- **Status**: Closed but scope expanding — 5 open issues (was 3 at Cycle 2)
- **Closed**: 2026-03-16 (22 days after due date 2026-02-22)
- **Issues**: 108/113 closed (94.7%) — 5 open
- **Notes**: Actor compiler and LLM integration complete. Open issue count growing despite milestone closure. LangGraph StateGraph compilation, MCP adapter, tool router operational.
### v3.2.0 (M3) — CRITICAL RISK
- **Status**: Open — 46 days overdue (due 2026-02-26)
- **Issues**: 269/1071 closed (25.1%) — 802 open (+26 in 60 min)
- **Scope**: Massively expanded (was ~300 issues, now 1071 and growing)
- **Blockers**: Decision recording system, invariant management, plan correction engine (revert/append modes)
- **Key features**: `plan tree`, `plan explain`, `invariant add/list/remove`, `plan correct`
- **Notes**: CI not running on master since 2026-03-14. E2E tests deleted (commit 8ea00f5). Scope growing faster than issues are being closed.
### v3.3.0 (M4) — CRITICAL RISK
- **Status**: Open — 42 days overdue (due 2026-03-02)
- **Issues**: 109/266 closed (41.0%) — 157 open (+9 in 60 min)
- **Blockers**: Subplan spawning during execution, parallel subplan execution, three-way merge strategy, checkpoint creation and rollback
- **Key features**: `plan rollback`, parallel execution with max_parallel, parent plan tracking
- **Notes**: Depends on M3 completion for correction flow.
### v3.4.0 (M5) — HIGH RISK
- **Status**: Open — 38 days overdue (due 2026-03-06)
- **Issues**: 139/381 closed (36.5%) — 242 open (+9 in 60 min)
- **Blockers**: ACMS v1 pipeline, context window management (hot/warm/cold tiers), 10k+ file indexing without timeout
- **Key features**: `context list/add/show/clear`, budget enforcement, context assembly CLI
- **Notes**: Context scaling is a major technical challenge. Budget constraints (max_file_size, max_total_size).
### v3.5.0 (M6) — CRITICAL RISK
- **Status**: Open — 34 days overdue (due 2026-03-10)
- **Issues**: 212/1264 closed (16.8%) — 1052 open (+20 in 60 min)
- **Scope**: Massively expanded (was ~200 issues, now 1264 and growing)
- **Blockers**: A2A facade session/plan lifecycle, event queue pub/sub, guard enforcement, autonomy hardening
- **Key features**: Hierarchical decomposition (4+ levels), parallel execution (10+ concurrent), realistic porting task
- **Notes**: Server stubs moved to M9 (ADR-047, ADR-048). TUI features moved to M8. Largest milestone by scope.
### v3.6.0 (M7) — HIGH RISK
- **Status**: Open — 16 days overdue (due 2026-03-28)
- **Issues**: 152/466 closed (32.6%) — 314 open (+18 in 60 min)
- **Blockers**: Advanced context strategies, additional LLM backends, container tool execution, pluggable scope chain
- **Key features**: ACP→A2A rename, cost/session budgets, safety profiles, E2E workflow spec tests
- **Notes**: Advanced concepts milestone. Abstraction layers for TUI/Server included.
### v3.7.0 (M8) — HIGH RISK
- **Status**: Open — No deadline assigned
- **Issues**: 427/1001 closed (42.6%) — 574 open (+26 in 60 min)
- **Blockers**: Textual TUI MainScreen, persona system (YAML-based), reference/command input (@, /, ! modes)
- **Key features**: TuiMaterializer A2A integration, session persistence (SQLite), Dracula theme, multi-session tabs
- **Notes**: TUI features moved here from M6. Highest absolute completion count (427 closed). ADR-044, ADR-045, ADR-046.
### v3.8.0 (M9) — HIGH RISK
- **Status**: Open — No deadline assigned
- **Issues**: 133/491 closed (27.1%) — 358 open (unchanged)
- **Blockers**: A2A JSON-RPC 2.0 wire format, stdio/HTTP transports, LangGraph Platform RemoteGraph, FastAPI + A2A SDK
- **Key features**: Authentication/authorization (API tokens, RBAC), entity sync, PostgreSQL backend, Docker/K8s/Helm
- **Notes**: Server implementation. ADR-047 (A2A adoption), ADR-048 (server architecture). No deadline.
### v3.9.0 — LOW RISK
- **Status**: Open — No deadline assigned
- **Issues**: 4/21 closed (19.0%) — 17 open (unchanged)
- **Notes**: Documentation and feature updates. Lowest priority milestone.
## Risk Register
| Risk | Severity | Milestones Affected | Status | Mitigation |
|------|----------|---------------------|--------|------------|
| All active milestones overdue | CRITICAL | M3-M7 | Active | Increase automation, parallel workers |
| Scope expanding faster than closing (+110 open in 60 min) | CRITICAL | All | ESCALATING | Scope freeze, prioritization |
| CI not running on master (since 2026-03-14) | CRITICAL | All | Open (#8508) | Fix CI trigger configuration |
| Massive scope expansion (M3: 1071, M6: 1264 issues) | CRITICAL | M3, M6 | Active | Scope management, prioritization |
| 802 open issues in M3 alone | CRITICAL | M3 | Active | Focus automation on M3 |
| 1052 open issues in M6 | CRITICAL | M6 | Active | Parallel worker pools |
| E2E tests deleted (commit 8ea00f5, issue #8459) | HIGH | All | Open | Restore E2E test suite |
| Open PR #8380 unmerged (Day 103 Timeline Update) | MEDIUM | Timeline | Open | Superseded by PR #8582 |
| v3.1.0 closed with 5 open issues (growing) | MEDIUM | M2 | ESCALATING | Resolve remaining issues, prevent scope creep |
## Timeline Update — 2026-04-16 (Cycle 2 Verification)
### Schedule Adherence Updates
| Date | Day | Cycle | Milestone | Planned % | Actual % | Delta | Risk | Notes |
|------|-----|-------|-----------|-----------|----------|-------|------|-------|
| 2026-04-14 | D104 | C2 | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Day 104: 269/1045 closed, 776 open |
| 2026-04-14 | D104 | C2 | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Day 104: 109/257 closed, 148 open |
| 2026-04-14 | D104 | C2 | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Day 104: 139/372 closed, 233 open |
| 2026-04-14 | D104 | C2 | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Day 104: 210/1242 closed, 1032 open |
| 2026-04-14 | D104 | C2 | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Day 104: 152/448 closed, 296 open |
| 2026-04-14 | D104 | C2 | v3.7.0 M8 | — | 43.8% | — | HIGH | Day 104: 427/975 closed, 548 open |
| 2026-04-14 | D104 | C2 | v3.8.0 M9 | — | 27.1% | — | HIGH | Day 104: 133/491 closed, 358 open |
| 2026-04-15 | D105 | C2 | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Day 105: no changes detected |
| 2026-04-15 | D105 | C2 | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Day 105: no changes detected |
| 2026-04-15 | D105 | C2 | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Day 105: no changes detected |
| 2026-04-15 | D105 | C2 | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Day 105: no changes detected |
| 2026-04-15 | D105 | C2 | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Day 105: no changes detected |
| 2026-04-15 | D105 | C2 | v3.7.0 M8 | — | 43.8% | — | HIGH | Day 105: no changes detected |
| 2026-04-15 | D105 | C2 | v3.8.0 M9 | — | 27.1% | — | HIGH | Day 105: no changes detected |
| 2026-04-16 | D106 | C2 | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Cycle 2 verification: no milestone changes since Day 104 |
| 2026-04-16 | D106 | C2 | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Cycle 2 verification: no milestone changes since Day 104 |
| 2026-04-16 | D106 | C2 | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Cycle 2 verification: no milestone changes since Day 104 |
| 2026-04-16 | D106 | C2 | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Cycle 2 verification: no milestone changes since Day 104 |
| 2026-04-16 | D106 | C2 | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Cycle 2 verification: no milestone changes since Day 104 |
| 2026-04-16 | D106 | C2 | v3.7.0 M8 | — | 43.8% | — | HIGH | Cycle 2 verification: no milestone changes since Day 104 |
| 2026-04-16 | D106 | C2 | v3.8.0 M9 | — | 27.1% | — | HIGH | Cycle 2 verification: no milestone changes since Day 104 |
### Verification Summary (Cycle 2)
- **Snapshot**: Milestone data verified -- no changes since Cycle 1
- **Milestones at risk**: v3.2.0 (OVERDUE 49d), v3.3.0 (OVERDUE 45d), v3.4.0 (OVERDUE 41d), v3.5.0 (OVERDUE 37d), v3.6.0 (OVERDUE 19d)
- **Notes**: All M3-M7 milestones remain overdue. No milestone closures detected. PR #10062 (Day 106 update) pending merge.
## Automation Activity Log
| Date | Day | Cycle | Agent | Action |
|------|-----|-------|-------|--------|
| 2026-04-13 | D103 | C1 | AUTO-TIME | Supervisor started, tracking issue #8519 created |
| 2026-04-13 | D103 | C2 | AUTO-TIME-1 | Timeline updated on branch auto-time-1-day103-cycle2, PR #8582 created |
| 2026-04-13 | D103 | C3 | AUTO-TIME-2 | Timeline updated on branch auto-time-2-day103-cycle3, scope expansion alert added |
| 2026-04-16 | D106 | C2 | AUTO-TIME-3 | Timeline verified on branch auto-time-3-day106-cycle2, PR #10062 created |
---
**Automated by CleverAgents Bot**
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor