docs(timeline): update schedule adherence Day 100 (2026-04-10) #7557
+75
-75
@@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
|
||||
@startgantt
|
||||
|
||||
title CleverAgents Core — Epic-Level Project Schedule
|
||||
footer Generated 2026-04-10 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~25 open bugs | 225 open PRs | Session 4 active
|
||||
footer Generated 2026-04-10 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~147 open bugs | 235 open PRs | Session 4 active
|
||||
|
||||
Project starts 2026-02-03
|
||||
saturday are closed
|
||||
@@ -22,14 +22,14 @@ today is colored in #FF6666
|
||||
|
||||
' ================================================================
|
||||
' GANTT CHART UPDATE LOG (Day 100 — 2026-04-10)
|
||||
' Changes: Day 100 refresh (cycle 2). Session 4 active (issue #4799, 32 workers).
|
||||
' Open PRs: 221→225 (new PRs opened by agents). Open bugs: ~25 (Type/Bug label).
|
||||
' M3 32% (249/770, scope expanded!), M4 49% (108/220), M5 43% (133/313),
|
||||
' M6 18% (197/1085, scope massively expanded!), M7 38% (150/400),
|
||||
' M8 45% (425/944), M9 28% (131/475).
|
||||
' Massive scope expansion across all milestones since Day 98.
|
||||
' pr-merge-pool-supervisor added as 17th supervisor. PR review reduced to 1 approval.
|
||||
' git worktree sandbox merged. ACMS indexing pipeline wired.
|
||||
' Changes: Day 100 refresh. Session 4 active (issue #4799, 32 workers).
|
||||
' Open PRs: 1→235 (agent-driven PR creation wave). Open bugs: ~878→~147 (major triage).
|
||||
' M3 31% (254/811, scope expanded massively 320→811), M4 48% (108/222),
|
||||
' M5 40% (134/333), M6 17% (200/1124, scope expanded 638→1124),
|
||||
' M7 36% (150/416), M8 44% (427/952), M9 27% (131/480).
|
||||
' 11 PRs merged since Day 98: git worktree sandbox (#5998), ACMS indexing fix (#4219),
|
||||
' CI quality restore (#4175), plan upsert fix (#4197), docs updates (#5614, #6942, #3390),
|
||||
' CI lint fix (#5264), Robot tdd_expected_fail guard (#5659), CLI fixes (#6571, #6639).
|
||||
' ================================================================
|
||||
|
||||
<style>
|
||||
@@ -231,7 +231,7 @@ ganttDiagram {
|
||||
|
||||
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
|
||||
[M3] starts at [M2]'s end
|
||||
[M3] is 65% completed
|
||||
[M3] is 31% completed
|
||||
[M3] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
|
||||
@@ -252,7 +252,7 @@ ganttDiagram {
|
||||
|
||||
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
|
||||
[M4] starts at [M3]'s end
|
||||
[M4] is 60% completed
|
||||
[M4] is 48% completed
|
||||
[M4] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
|
||||
@@ -283,12 +283,12 @@ ganttDiagram {
|
||||
|
||||
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
|
||||
[M5] starts at [M4]'s end
|
||||
[M5] is 68% completed
|
||||
[M5] is 40% completed
|
||||
[M5] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
|
||||
[M6] starts at [M5]'s end
|
||||
[M6] is 55% completed
|
||||
[M6] is 17% completed
|
||||
[M6] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
|
||||
@@ -299,7 +299,7 @@ ganttDiagram {
|
||||
|
||||
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
|
||||
[LARGE] starts 2026-03-17
|
||||
[LARGE] is 43% completed
|
||||
[LARGE] is 36% completed
|
||||
[LARGE] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
|
||||
@@ -403,13 +403,13 @@ legend right
|
||||
----
|
||||
**Risk Register (Day 100 — 2026-04-10)**
|
||||
|= Epic |= Completion |= Risk |= Blocker |
|
||||
| M3 (#357) | 32% | **CRITICAL** | 521 open issues in v3.2.0 (scope expanded 320→770) |
|
||||
| M4 (#358) | 49% | **CRITICAL** | 112 open issues in v3.3.0 |
|
||||
| M5 (#359) | 43% | **HIGH** | 180 open issues in v3.4.0 |
|
||||
| M6 (#360) | 18% | **CRITICAL** | 888 open issues in v3.5.0 (massive scope expansion) |
|
||||
| M7 (#361) | 38% | **HIGH** | 250 open issues in v3.6.0 |
|
||||
| M8 (#362) | 45% | **HIGH** | 519 open issues in v3.7.0 |
|
||||
| SEC (#363) | 28% | **HIGH** | 344 open issues in v3.8.0 |
|
||||
| M3 (#357) | 31% | **CRITICAL** | 557 open issues in v3.2.0 (scope expanded 320→811) |
|
||||
| M4 (#358) | 48% | **CRITICAL** | 114 open issues in v3.3.0 |
|
||||
| M5 (#359) | 40% | **CRITICAL** | 199 open issues in v3.4.0 |
|
||||
| M6 (#360) | 17% | **CRITICAL** | 924 open issues in v3.5.0 (scope expanded 638→1124) |
|
||||
| M7 (#361) | 36% | **HIGH** | 266 open issues in v3.6.0 |
|
||||
| M8 (#362) | 44% | **HIGH** | 525 open issues in v3.7.0 |
|
||||
| SEC (#363) | 27% | **HIGH** | 349 open issues in v3.8.0 |
|
||||
----
|
||||
**Color Key**
|
||||
|= Color |= Meaning |
|
||||
@@ -421,7 +421,7 @@ legend right
|
||||
----
|
||||
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
|
||||
~1649 total story points | ~3300 estimated hours
|
||||
**~25 open bugs (Type/Bug) — 225 open PRs — Session 4 active (32 workers)**
|
||||
**~147 open bugs — 235 open PRs — Session 4 active (32 workers)**
|
||||
end legend
|
||||
|
||||
@endgantt
|
||||
@@ -1954,7 +1954,7 @@ legend right
|
||||
----
|
||||
271 Issues | 29 Epics | 9 Legendaries | 7 Milestones
|
||||
~1649 total story points | ~3300 estimated hours
|
||||
**~5 open bugs (Type/Bug) — 219 open PRs — Session 4 active (32 workers)**
|
||||
**~147 open bugs — 235 open PRs — Session 4 active (32 workers)**
|
||||
end legend
|
||||
|
||||
@endgantt
|
||||
@@ -1966,13 +1966,13 @@ This section provides a high-level overview of the CleverAgents implementation r
|
||||
|
||||
### Current Status Summary
|
||||
|
||||
As of Day 100 (2026-04-10), the project has **225 open PRs** and **~2777 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~25 open bugs** (Type/Bug label; UAT issues tracked separately). M8 (v3.7.0) is now **45% complete** (425/944 issues closed). M3 (v3.2.0) at **32%** (249/770 — scope massively expanded), M4 (v3.3.0) at **49%** (108/220), M5 (v3.4.0) at **43%** (133/313), M6 (v3.5.0) at **18%** (197/1085 — scope massively expanded), M7 (v3.6.0) at **38%** (150/400).
|
||||
As of Day 100 (2026-04-10), the project has **235 open PRs** and **~2940 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~147 open bugs** (down from ~878 — major triage wave). Milestone scopes have expanded significantly due to agent-driven issue creation. M3 (v3.2.0) at **31%** (254/811 — scope expanded from 320 to 811), M4 (v3.3.0) at **48%** (108/222), M5 (v3.4.0) at **40%** (134/333), M6 (v3.5.0) at **17%** (200/1124 — scope expanded from 638 to 1124), M7 (v3.6.0) at **36%** (150/416), M8 (v3.7.0) at **44%** (427/952), M9 (v3.8.0) at **27%** (131/480).
|
||||
|
||||
**M1, M2 fully complete. M3 (v3.2.0)**: 33% complete (248/757), 509 open issues — scope expanded massively. **M4 (v3.3.0)**: 49% complete (108/220), 112 open issues. **M5 (v3.4.0)**: 44% complete (133/301), 168 open issues. **M6 (v3.5.0)**: 18% complete (197/1065), 868 open issues — scope expanded massively. **M7 (v3.6.0)**: 38% complete (150/392), 242 open issues. **M8 (v3.7.0)**: 45% complete (423/938), 515 open issues. All milestones M3-M7 are **overdue**; M8 is in active v3.7.0 development.
|
||||
**M1, M2 fully complete. M3 (v3.2.0)**: 31% complete (254/811), 557 open issues — scope expanded massively from 320 to 811. **M4 (v3.3.0)**: 48% complete (108/222), 114 open issues. **M5 (v3.4.0)**: 40% complete (134/333), 199 open issues. **M6 (v3.5.0)**: 17% complete (200/1124), 924 open issues — scope expanded from 638 to 1124. **M7 (v3.6.0)**: 36% complete (150/416), 266 open issues. **M8 (v3.7.0)**: 44% complete (427/952), 525 open issues. **M9 (v3.8.0)**: 27% complete (131/480), 349 open issues. All milestones M3-M7 are **overdue**; M8/M9 in active development.
|
||||
|
||||
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — Massive Scope Expansion — Session 4 Active (Day 100: 219 Open PRs, M3/M6 Scope Exploded)"
|
||||
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — Massive Scope Expansion — 235 Open PRs — Session 4 Active (Day 100)"
|
||||
|
||||
All milestones M3 through M7 have passed their target dates. **Session 4 active (launched 2026-04-08, issue #4799) with 32 parallel workers**. Open PRs at **219** (up from 1 — agents opened many new PRs). Open bugs at **~5** (Type/Bug label). Session tracker issue: #4799. **Current priorities**: (1) **M3 scope explosion** — 509 open issues (was 85 at Day 98); scope grew from 320 to 757 total. (2) **M6 scope explosion** — 868 open issues (was 450 at Day 98); scope grew from 638 to 1065 total. (3) **Merge 219 open PRs** — pr-merge-pool-supervisor added as 17th supervisor. (4) **Continue M8 push** — 45% complete, 515 issues remaining. (5) **Clear M4/M5 backlogs** — M4 at 49% (112 open), M5 at 44% (168 open).
|
||||
All milestones M3 through M7 have passed their target dates. **Session 4 active (launched 2026-04-08, issue #4799) with 32 parallel workers**. Open PRs at **235** (agent-driven PR creation wave). Open bugs at **~147** (down from ~878 — major triage). Session tracker issue: #4799. **Current priorities**: (1) **Massive scope expansion** — M3 grew from 320→811 issues, M6 grew from 638→1124 issues; agent-driven issue creation continues. (2) **235 open PRs need review and merge** — significant backlog. (3) **Continue M8/M9 push** — M8 at 44% (525 open), M9 at 27% (349 open). (4) **Clear M3/M4/M5 backlogs** — M3 at 31% (557 open), M4 at 48% (114 open), M5 at 40% (199 open). 11 PRs merged since Day 98 including git worktree sandbox (#5998), ACMS indexing fix (#4219), CI quality restore (#4175).
|
||||
|
||||
### Parallel Workstreams
|
||||
|
||||
@@ -2291,19 +2291,19 @@ Items without an assigned milestone represent backlog work to be addressed after
|
||||
|
||||
### Schedule Risk Summary
|
||||
|
||||
As of Day 96 (2026-04-06), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **108** (down from 183 — 75 PRs merged/closed!). Open bugs at **~878** (stable). M8 (v3.7.0) at **46% complete** (418/917 closed). M9 (v3.8.0) at **28% complete** (131/467 closed). Session tracker: #3775. Critical path: PR #3774 (Click 8.2+ fix) must be merged; 108 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 46% with 499 issues remaining; ~878 open bugs need TDD counterparts and systematic triage.
|
||||
As of Day 100 (2026-04-10), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **30+ days** for M3-M6. **Session 4 is active with 32 parallel workers**. Open PRs now at **235** (agent-driven PR creation wave). Open bugs at **~147** (down from ~878 — major triage wave). M8 (v3.7.0) at **44% complete** (427/952 closed). M9 (v3.8.0) at **27% complete** (131/480 closed). Session tracker: #4799. Critical path: 235 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue with massively expanded scopes; M3 scope grew 320→811, M6 scope grew 638→1124; M8 at 44% with 525 issues remaining; M9 at 27% with 349 issues remaining.
|
||||
|
||||
**Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry.
|
||||
|
||||
**Day 53 Session 3 actions**: (a) 16 parallel workers started. (b) 73+ PRs merged including ACMS UKO runtime (#1312), PermissionsScreen TUI (#1307), actor thought blocks (#1298), DatabaseResourceHandler (#1293), ACMS pipeline Phase 2 (#1287), DevcontainerHandler (#1286), async audit (#1279), serve CLI (#1272), LSP hover/definitions (#1240), domain event wiring (#1215), plan prompt command (#1212), M6 E2E tests (#1277), @tdd_expected_fail cleanup (#1229), persona export/import (#1338), first-run experience (#1391), session export/import (#1392). (c) UAT supervisor fleet (cycles 11-131) launched — discovered 100+ spec compliance bugs across CLI rich output, YAML config handling, and actor compiler. (d) Security bug-hunt PRs opened: #1412 (concurrency), #1409 (error handling), #1419 (hardcoded secrets). (e) Late-day: 4 more PRs merged (#1498, #1481, #1479, #1338), 18 new fix PRs opened (#1506-#1517) targeting UAT findings. (f) End-of-day CLI fix wave: 18 more PRs merged (#1574, #1573, #1570, #1569, #1567, #1566, #1565, #1563, #1562, #1558, #1556, #1554 and others) — open bugs reduced from **143 to 6**, open PRs at **74**.
|
||||
|
||||
**Critical path blockers** (ranked):
|
||||
1. **PR #3774 must be fixed and merged** — Click 8.2+ compatibility fix with CI failures in push-validation and coverage. Blocks all milestone work.
|
||||
2. **108 open PRs need review** — significant reduction from 183 (75 PRs merged/closed on Day 96). Continued review velocity needed.
|
||||
3. **~878 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Stable at ~878.
|
||||
4. **M3-M7 backlog** — 131+74+63+147+198 open issues across M3-M7. Progress made: M3 +4%, M4 +3%, M5 +4%.
|
||||
5. **M8 (v3.7.0) at 46%** — 499 issues remaining (milestone grew from 880→917). Continued agent-driven expansion.
|
||||
6. **M9 (v3.8.0) at 28%** — 336 issues remaining (milestone grew from 465→467). Continued expansion.
|
||||
1. **235 open PRs need review and merge** — agent-driven PR creation wave. Significant backlog requiring systematic review.
|
||||
2. **Massive scope expansion** — M3 grew from 320→811 issues (+491), M6 grew from 638→1124 issues (+486). Agent-driven issue creation continues to expand scope.
|
||||
3. **~147 open bugs** — down from ~878 (major triage wave). Continued TDD counterpart creation needed.
|
||||
4. **M3-M7 backlog** — 557+114+199+924+266 = 2060 open issues across M3-M7. All milestones overdue.
|
||||
5. **M8 (v3.7.0) at 44%** — 525 issues remaining (milestone grew from 855→952). Continued agent-driven expansion.
|
||||
6. **M9 (v3.8.0) at 27%** — 349 issues remaining (milestone grew from 480). Continued expansion.
|
||||
|
||||
**Spec changes impact assessment (Day 31)**: ACP→A2A rename affects 10 source files, 13 classes, 640+ test references across 22 files. Zero A2A code exists — migration not started. All open PRs that touch ACP modules will need additional rebase work after #688/#689 merge. TUI spec adds ~1,500 lines with 18 ASCII mockups defining Textual-based UI — PR #667 was a placeholder that predates this spec. Server architecture adopts JSON-RPC 2.0 standard — PR #676 used custom protocol, now obsolete.
|
||||
|
||||
@@ -4841,7 +4841,7 @@ Story points per developer per milestone.
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~172 SP |
|
||||
| M2 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~208 SP |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~104 SP |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~126 SP |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~129 SP |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~151 SP |
|
||||
@@ -5198,14 +5198,14 @@ Milestone per developer as of Day 98 (2026-04-08).
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
|
||||
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 85 open | 235/320 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 53 open | 108/161 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 53 open | 130/183 |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 450 open | 188/638 |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 162 open | 150/312 |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 452 open | 403/855 |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | N/A |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1255 open** | **1214/2565** |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 557 open | 254/811 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 114 open | 108/222 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 199 open | 134/333 |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 924 open | 200/1124 |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 266 open | 150/416 |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 525 open | 427/952 |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 349 open | 131/480 |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~2934 open** | **1504/3540** |
|
||||
|
||||
#### Story point allocation
|
||||
|
||||
@@ -5229,18 +5229,18 @@ Story points per developer per milestone.
|
||||
|
||||
**Summary**
|
||||
|
||||
Status: Behind 25+d
|
||||
Status: Behind 30+d
|
||||
Deadline risk: CRITICAL
|
||||
|
||||
**Notes**
|
||||
|
||||
- Day 100 update (2026-04-10, cycle 2). Session 4 active (issue #4799, 32 parallel workers, full supervisor fleet). Open PRs: 221→225 (+4 new PRs). Open bugs (Type/Bug label): ~25 (up from ~6 in cycle 1 — UAT bug-hunt wave active).
|
||||
- Continued scope expansion across all milestones since cycle 1: M3 grew from 764→770 (+6), M5 grew from 310→313 (+3), M6 grew from 1069→1085 (+16), M7 grew from 392→400 (+8), M8 grew from 940→944 (+4).
|
||||
- Milestone completions (Day 100 cycle 2): M3 32% (249/770, was 73% at Day 98 — scope explosion), M4 49% (108/220, was 67%), M5 43% (133/313, was 71%), M6 18% (197/1085, was 29%), M7 38% (150/400, was 48%), M8 45% (425/944, was 47%), M9 28% (131/475).
|
||||
- Key merges since Day 98: git worktree sandbox for plan execute/modify, ACMS indexing pipeline wired into CLI (ContextTierService now invoked), invariant-reconciliation module guide added, plan action argument upsert fix, implementation orchestrator scaled to 32 workers, automation tracking centralized, container-instance stop fix merged.
|
||||
- Infrastructure improvements: pr-merge-pool-supervisor added as 17th supervisor to product-builder, PR review requirement reduced from 2 approvals to 1, async-agent-manager enhanced with retry logic and improved error handling, automation-tracking-manager hardened with label delegation enforcement, agents renamed/reorganized.
|
||||
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development. Agent-driven issue creation continues at high velocity across all milestones.
|
||||
- PR #6730 (docs(timeline): update schedule adherence Day 99 cycle-3) is open but not yet merged — Day 99 entry may exist in that branch but not in master.
|
||||
- Day 100 milestone: Session 4 active (issue #4799, 32 parallel workers). 11 PRs merged since Day 98 including git worktree sandbox (#5998), ACMS indexing pipeline fix (#4219), CI quality restore (#4175), plan upsert fix (#4197), Robot tdd_expected_fail guard (#5659), CLI fixes (#6571, #6639), docs updates (#5614, #6942, #3390), CI lint fix (#5264).
|
||||
- Massive scope expansion detected: M3 (v3.2.0) grew from 320→811 total issues (+491 new issues); M6 (v3.5.0) grew from 638→1124 total issues (+486 new issues). Agent-driven issue creation continues to expand milestone scope.
|
||||
- Open PRs surged from 1→235 (agent-driven PR creation wave). All require review and merge.
|
||||
- Open bugs dropped from ~878 to ~147 (major triage wave — systematic bug closure).
|
||||
- M3 completion dropped from 73% to 31% due to scope expansion (254/811 closed). M4 dropped from 67% to 48% (108/222). M5 dropped from 71% to 40% (134/333). M6 dropped from 29% to 17% (200/1124). M7 dropped from 48% to 36% (150/416). M8 dropped from 47% to 44% (427/952). M9 at 27% (131/480).
|
||||
- Total open issues across all active milestones: ~2940 (up from ~1458 at Day 98).
|
||||
- New milestone v3.9.0 (id:132) detected: 6 open / 1 closed = 14% complete.
|
||||
|
||||
|
||||
#### Milestone forecast
|
||||
@@ -5249,34 +5249,34 @@ Deadline risk: CRITICAL
|
||||
|-----------|---------------|-------|------|
|
||||
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
|
||||
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-06-15 | +110d | CRITICAL — 521 open issues; 32% complete (scope expanded 320→770) |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-20 | +79d | CRITICAL — 112 open issues; 49% complete |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-25 | +80d | HIGH — 180 open issues; 43% complete |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-08-01 | +144d | CRITICAL — 888 open issues; 18% complete (scope expanded 638→1085) |
|
||||
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-20 | +84d | HIGH — 250 open issues; 38% complete |
|
||||
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-20 | N/A | HIGH — 519 open issues; 45% complete |
|
||||
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-01 | N/A | MEDIUM — 344 open issues; 28% complete |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-07-01 | +125d | CRITICAL — 557 open issues; 31% complete (scope expanded 320→811) |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-06-01 | +91d | CRITICAL — 114 open issues; 48% complete |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-06-15 | +101d | CRITICAL — 199 open issues; 40% complete |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-09-01 | +175d | CRITICAL — 924 open issues; 17% complete (scope expanded 638→1124) |
|
||||
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-07-15 | +109d | HIGH — 266 open issues; 36% complete |
|
||||
| M8 (v3.7.0) | (no deadline) -> ETA 2026-09-15 | N/A | HIGH — 525 open issues; 44% complete |
|
||||
| M9 (v3.8.0) | (no deadline) -> ETA 2026-10-01 | N/A | HIGH — 349 open issues; 27% complete |
|
||||
|
||||
#### Track forecast
|
||||
|
||||
| Track | Status | ETA | Risk | Blocking |
|
||||
|-------|--------|-----|------|----------|
|
||||
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
|
||||
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-25 | HIGH | 180 open issues in v3.4.0; scope expanded +130 issues since Day 98 |
|
||||
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-20 | CRITICAL | 112 open issues in v3.3.0; scope expanded +59 issues since Day 98 |
|
||||
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-06-15 | CRITICAL | 521 open issues in v3.2.0; scope expanded +450 issues since Day 98 |
|
||||
| Track Q (Quality automation) | Ongoing | N/A | HIGH | ~25 Type/Bug open bugs (UAT bug-hunt wave); 225 open PRs need merge; pr-merge-pool-supervisor active |
|
||||
| Track T (Testing) | Active | Ongoing | HIGH | 225 open PRs need review; UAT bugs ongoing; Session 4 active |
|
||||
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-06-15 | HIGH | 199 open issues in v3.4.0; scope expansion ongoing |
|
||||
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-06-01 | CRITICAL | 114 open issues in v3.3.0; 557 open in v3.2.0 |
|
||||
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-07-01 | CRITICAL | 557 open issues in v3.2.0; scope expanded 320→811 |
|
||||
| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | ~147 open bugs; 235 open PRs; M6 scope explosion (638→1124) |
|
||||
| Track T (Testing) | Active | Ongoing | HIGH | 235 open PRs need review; UAT bugs ongoing |
|
||||
|
||||
#### Developer forecast
|
||||
|
||||
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|
||||
|------|-------------------|--------------|------|-------|
|
||||
| Jeff | -25d behind | active | HIGH | Session 4 supervisor; pr-merge-pool-supervisor; M3/M4/M5 backlog clearance; architecture oversight |
|
||||
| Luis | -25d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool; async-agent-manager improvements |
|
||||
| Jeff | -25d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight |
|
||||
| Luis | -25d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool |
|
||||
| Hamza | -25d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews |
|
||||
| Aditya | -25d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
|
||||
| Brent | -25d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; PR triage |
|
||||
| Brent | -25d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; ~147 open bugs triage |
|
||||
| Rui | -25d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
|
||||
| Mike/Brian | N/A | standby | LOW | Infrastructure support |
|
||||
|
||||
@@ -5288,16 +5288,16 @@ Milestone per developer as of Day 100 (2026-04-10).
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
|
||||
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 521 open | 249/770 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 112 open | 108/220 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 180 open | 133/313 |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 888 open | 197/1085 |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 250 open | 150/400 |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 519 open | 425/944 |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 344 open | 131/475 |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~2814 open** | **1489/4303 closed** |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 557 open | 254/811 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 114 open | 108/222 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 199 open | 134/333 |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 924 open | 200/1124 |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 266 open | 150/416 |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 525 open | 427/952 |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 349 open | 131/480 |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~2934 open** | **1504/3540** |
|
||||
|
||||
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 100 cycle-2 (2026-04-10). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues at high velocity. M3 grew from 320→770 (+450), M4 grew from 161→220 (+59), M5 grew from 183→313 (+130), M6 grew from 638→1085 (+447), M7 grew from 312→400 (+88), M8 grew from 855→944 (+89), M9 grew from 467→475 (+8) since Day 98.
|
||||
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 100 (2026-04-10). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues at high velocity. M3 grew from 320→811 (+491), M4 grew from 161→222 (+61), M5 grew from 183→333 (+150), M6 grew from 638→1124 (+486), M7 grew from 312→416 (+104), M8 grew from 855→952 (+97), M9 grew from 467→480 (+13) since Day 98.
|
||||
|
||||
#### Story point allocation
|
||||
|
||||
|
||||