docs(timeline): update schedule adherence Day 99 (2026-04-09) cycle-6 #6363
+68
-67
@@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
|
||||
@startgantt
|
||||
|
||||
title CleverAgents Core — Epic-Level Project Schedule
|
||||
footer Generated 2026-04-09 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~2861 open bugs | 145 open PRs | Session 4 active
|
||||
footer Generated 2026-04-09 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3615 open bugs | 183 open PRs | Session 4 active
|
||||
|
||||
Project starts 2026-02-03
|
||||
saturday are closed
|
||||
@@ -22,13 +22,13 @@ today is colored in #FF6666
|
||||
|
||||
' ================================================================
|
||||
' GANTT CHART UPDATE LOG (Day 99 — 2026-04-09)
|
||||
' Changes: Day 99 refresh. Session 4 active (#4799, 32 workers).
|
||||
' Open PRs: 1→145 (+144 new PRs opened by agents). Open bugs: ~878→~2861 (+1983 new bugs!).
|
||||
' M3 62% (240/387, scope grew 320→387), M4 56% (108/191, scope grew 161→191),
|
||||
' M5 69% (130/187, scope grew 183→187), M6 27% (192/711, scope grew 638→711),
|
||||
' M7 47% (150/313), M8 47% (422/880), M9 29% (129/435).
|
||||
' Massive bug explosion: 878→2861 open bugs (+1983). Agent-driven issue creation continues.
|
||||
' All milestones M3-M7 remain overdue. M8/M9 in active development.
|
||||
' Changes: Day 99 refresh. Session 4 active with 32 parallel workers.
|
||||
' Open PRs: 1→183 (new PRs opened by agents). Open bugs: ~878→~3615 (massive UAT expansion).
|
||||
' M3 47% (248/526), M4 50% (108/216), M5 57% (133/234), M6 19% (197/1040, scope expanded!),
|
||||
' M7 39% (150/381), M8 45% (422/935), M9 28% (130/466).
|
||||
' Massive scope expansion across all milestones due to agent-driven issue creation.
|
||||
' M6 grew from 638→1040 total issues (+402 new). M3 grew from 320→526 (+206 new).
|
||||
' Session 4 active. Session tracker issue: #4799.
|
||||
' ================================================================
|
||||
|
||||
<style>
|
||||
@@ -230,7 +230,7 @@ ganttDiagram {
|
||||
|
||||
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
|
||||
[M3] starts at [M2]'s end
|
||||
[M3] is 65% completed
|
||||
[M3] is 47% completed
|
||||
[M3] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
|
||||
@@ -251,13 +251,13 @@ ganttDiagram {
|
||||
|
||||
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
|
||||
[M4] starts at [M3]'s end
|
||||
[M4] is 60% completed
|
||||
[M4] is 50% completed
|
||||
[M4] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
|
||||
[Security + Safety Hardening (#362)] as [SEC] on {Luis} requires 3 days
|
||||
[SEC] starts 2026-03-02
|
||||
[SEC] is 80% completed
|
||||
[SEC] is 28% completed
|
||||
[SEC] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Provider Fixes + Runtime (#363)] as [PROV] on {Luis} requires 2 days
|
||||
@@ -282,12 +282,12 @@ ganttDiagram {
|
||||
|
||||
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
|
||||
[M5] starts at [M4]'s end
|
||||
[M5] is 68% completed
|
||||
[M5] is 57% completed
|
||||
[M5] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
|
||||
[M6] starts at [M5]'s end
|
||||
[M6] is 55% completed
|
||||
[M6] is 19% completed
|
||||
[M6] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
|
||||
@@ -298,7 +298,7 @@ ganttDiagram {
|
||||
|
||||
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
|
||||
[LARGE] starts 2026-03-17
|
||||
[LARGE] is 43% completed
|
||||
[LARGE] is 39% completed
|
||||
[LARGE] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
|
||||
@@ -402,13 +402,13 @@ legend right
|
||||
----
|
||||
**Risk Register (Day 99 — 2026-04-09)**
|
||||
|= Epic |= Completion |= Risk |= Blocker |
|
||||
| M3 (#357) | 62% | **CRITICAL** | 147 open issues in v3.2.0; scope grew 320→387 |
|
||||
| M4 (#358) | 56% | **CRITICAL** | 83 open issues in v3.3.0; scope grew 161→191 |
|
||||
| M5 (#359) | 69% | **HIGH** | 57 open issues in v3.4.0; scope grew 183→187 |
|
||||
| M6 (#360) | 27% | **CRITICAL** | 519 open issues in v3.5.0; scope grew 638→711 |
|
||||
| M7 (#361) | 47% | **HIGH** | 163 open issues in v3.6.0 |
|
||||
| M8 (#362) | 47% | **HIGH** | 458 open issues in v3.7.0; scope grew 855→880 |
|
||||
| SEC (#363) | 29% | **HIGH** | 306 open issues in v3.8.0; 2861 total open bugs! |
|
||||
| M3 (#357) | 47% | **CRITICAL** | 278 open issues in v3.2.0 (scope expanded +206) |
|
||||
| M4 (#358) | 50% | **CRITICAL** | 108 open issues in v3.3.0 (scope expanded) |
|
||||
| M5 (#359) | 57% | **CRITICAL** | 101 open issues in v3.4.0 (scope expanded) |
|
||||
| M6 (#360) | 19% | **CRITICAL** | 843 open issues in v3.5.0 (scope expanded +402) |
|
||||
| M7 (#361) | 39% | **HIGH** | 231 open issues in v3.6.0 (scope expanded) |
|
||||
| M8 (#362) | 45% | **HIGH** | 513 open issues in v3.7.0 (agent expansion) |
|
||||
| SEC (#363) | 28% | **HIGH** | 336 open issues in v3.8.0 (agent expansion) |
|
||||
----
|
||||
**Color Key**
|
||||
|= Color |= Meaning |
|
||||
@@ -420,7 +420,7 @@ legend right
|
||||
----
|
||||
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
|
||||
~1649 total story points | ~3300 estimated hours
|
||||
**~2861 open bugs — 145 open PRs — Session 4 active (32 workers, #4799)**
|
||||
**~3615 open bugs — 183 open PRs — Session 4 active (32 workers)**
|
||||
end legend
|
||||
|
||||
@endgantt
|
||||
@@ -1184,7 +1184,7 @@ ganttDiagram {
|
||||
' --- Decisions + Validations + Invariants (M3) (#357) ---
|
||||
[Decisions + Validations + Invariants (M3) (#357)] as [M3] on {Brent} {Hamza} {Jeff} {Luis} requires 4 days
|
||||
[M3] starts at [M2]'s end
|
||||
[M3] is 75% completed
|
||||
[M3] is 47% completed
|
||||
[M3] is colored in CornflowerBlue/MediumBlue
|
||||
|
||||
[feat(decision): add decision domain and context... (#170)] as [I170] on {Hamza} lasts 1 day
|
||||
@@ -1240,7 +1240,7 @@ ganttDiagram {
|
||||
' --- Corrections + Subplans + Checkpoints (M4) (#358) ---
|
||||
[Corrections + Subplans + Checkpoints (M4) (#358)] as [M4] on {Brent} {Hamza} {Jeff} {Luis} requires 3 days
|
||||
[M4] starts at [M3]'s end
|
||||
[M4] is 78% completed
|
||||
[M4] is 50% completed
|
||||
[M4] is colored in CornflowerBlue/MediumBlue
|
||||
|
||||
[feat(correction): add correction model and CLI ... (#181)] as [I181] on {Jeff} lasts 1 day
|
||||
@@ -1275,7 +1275,7 @@ ganttDiagram {
|
||||
' --- Security & Safety Hardening (#362) ---
|
||||
[Security & Safety Hardening (#362)] as [SEC] on {Luis} requires 3 days
|
||||
[SEC] starts 2026-03-02
|
||||
[SEC] is 80% completed
|
||||
[SEC] is 28% completed
|
||||
[SEC] is colored in CornflowerBlue/MediumBlue
|
||||
|
||||
[fix(security): remove eval-based config parsing (#318)] as [I318] on {Luis} lasts 1 day
|
||||
@@ -1322,7 +1322,7 @@ ganttDiagram {
|
||||
' --- ACMS v1 + Context Scaling (M5) (#359) ---
|
||||
[ACMS v1 + Context Scaling (M5) (#359)] as [M5] on {Aditya} {Brent} {Hamza} {Jeff} requires 4 days
|
||||
[M5] starts at [M4]'s end
|
||||
[M5] is 87% completed
|
||||
[M5] is 57% completed
|
||||
[M5] is colored in CornflowerBlue/MediumBlue
|
||||
|
||||
[feat(acms): add ACMS v1 context pipeline (#188)] as [I188] on {Hamza} lasts 1 day
|
||||
@@ -1381,7 +1381,7 @@ ganttDiagram {
|
||||
' --- Autonomy Hardening + Server Stubs (M6) (#360) ---
|
||||
[Autonomy Hardening + Server Stubs (M6) (#360)] as [M6] on {Brent} {Hamza} {Jeff} {Luis} requires 5 days
|
||||
[M6] starts at [M5]'s end
|
||||
[M6] is 71% completed
|
||||
[M6] is 19% completed
|
||||
[M6] is colored in CornflowerBlue/MediumBlue
|
||||
|
||||
[feat(interfaces): add server client stubs (#201)] as [I201] on {Luis} lasts 1 day
|
||||
@@ -1455,7 +1455,7 @@ ganttDiagram {
|
||||
' --- Large Project Autonomy & Context (#369) ---
|
||||
[Large Project Autonomy & Context (#369)] as [LARGE] on {Brent} {Jeff} {Luis} requires 4 days
|
||||
[LARGE] starts 2026-03-17
|
||||
[LARGE] is 76% completed
|
||||
[LARGE] is 39% completed
|
||||
[LARGE] is colored in CornflowerBlue/MediumBlue
|
||||
|
||||
[feat(cli): add output rendering framework with ... (#311)] as [I311] on {Jeff} lasts 1 day
|
||||
@@ -2290,19 +2290,19 @@ Items without an assigned milestone represent backlog work to be addressed after
|
||||
|
||||
### Schedule Risk Summary
|
||||
|
||||
As of Day 96 (2026-04-06), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **108** (down from 183 — 75 PRs merged/closed!). Open bugs at **~878** (stable). M8 (v3.7.0) at **46% complete** (418/917 closed). M9 (v3.8.0) at **28% complete** (131/467 closed). Session tracker: #3775. Critical path: PR #3774 (Click 8.2+ fix) must be merged; 108 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 46% with 499 issues remaining; ~878 open bugs need TDD counterparts and systematic triage.
|
||||
As of Day 99 (2026-04-09), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 4 is active with 32 parallel workers**. Open PRs now at **183**. Open bugs at **~3,615** (massive UAT expansion — agent-driven issue creation). M3 (v3.2.0) at **47% complete** (248/526 closed — scope expanded +206 issues). M4 (v3.3.0) at **50% complete** (108/216 closed). M5 (v3.4.0) at **57% complete** (133/234 closed). M6 (v3.5.0) at **19% complete** (197/1040 closed — scope expanded massively +402 issues). M7 (v3.6.0) at **39% complete** (150/381 closed). M8 (v3.7.0) at **45% complete** (422/935 closed). M9 (v3.8.0) at **28% complete** (130/466 closed). Session tracker: #4799. Critical path: massive scope expansion across all milestones; 183 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; ~3,615 open bugs need TDD counterparts and systematic triage.
|
||||
|
||||
**Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry.
|
||||
|
||||
**Day 53 Session 3 actions**: (a) 16 parallel workers started. (b) 73+ PRs merged including ACMS UKO runtime (#1312), PermissionsScreen TUI (#1307), actor thought blocks (#1298), DatabaseResourceHandler (#1293), ACMS pipeline Phase 2 (#1287), DevcontainerHandler (#1286), async audit (#1279), serve CLI (#1272), LSP hover/definitions (#1240), domain event wiring (#1215), plan prompt command (#1212), M6 E2E tests (#1277), @tdd_expected_fail cleanup (#1229), persona export/import (#1338), first-run experience (#1391), session export/import (#1392). (c) UAT supervisor fleet (cycles 11-131) launched — discovered 100+ spec compliance bugs across CLI rich output, YAML config handling, and actor compiler. (d) Security bug-hunt PRs opened: #1412 (concurrency), #1409 (error handling), #1419 (hardcoded secrets). (e) Late-day: 4 more PRs merged (#1498, #1481, #1479, #1338), 18 new fix PRs opened (#1506-#1517) targeting UAT findings. (f) End-of-day CLI fix wave: 18 more PRs merged (#1574, #1573, #1570, #1569, #1567, #1566, #1565, #1563, #1562, #1558, #1556, #1554 and others) — open bugs reduced from **143 to 6**, open PRs at **74**.
|
||||
|
||||
**Critical path blockers** (ranked):
|
||||
1. **PR #3774 must be fixed and merged** — Click 8.2+ compatibility fix with CI failures in push-validation and coverage. Blocks all milestone work.
|
||||
2. **108 open PRs need review** — significant reduction from 183 (75 PRs merged/closed on Day 96). Continued review velocity needed.
|
||||
3. **~878 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Stable at ~878.
|
||||
4. **M3-M7 backlog** — 131+74+63+147+198 open issues across M3-M7. Progress made: M3 +4%, M4 +3%, M5 +4%.
|
||||
5. **M8 (v3.7.0) at 46%** — 499 issues remaining (milestone grew from 880→917). Continued agent-driven expansion.
|
||||
6. **M9 (v3.8.0) at 28%** — 336 issues remaining (milestone grew from 465→467). Continued expansion.
|
||||
1. **Massive scope expansion** — M3 grew from 320→526 (+206), M4 grew to 216, M5 grew to 234, M6 grew from 638→1040 (+402), M7 grew to 381. Completion percentages dropped significantly despite continued closures.
|
||||
2. **183 open PRs need review** — significant increase from 1 open PR on Day 98. Agents opened many new PRs.
|
||||
3. **~3,615 open bugs** — massive increase from ~878 on Day 98. Agent-driven UAT expansion at high velocity.
|
||||
4. **M3-M7 backlog** — 278+108+101+843+231 open issues across M3-M7. All milestones overdue.
|
||||
5. **M8 (v3.7.0) at 45%** — 513 issues remaining (milestone grew from 855→935). Continued agent-driven expansion.
|
||||
6. **M9 (v3.8.0) at 28%** — 336 issues remaining. Continued expansion.
|
||||
|
||||
**Spec changes impact assessment (Day 31)**: ACP→A2A rename affects 10 source files, 13 classes, 640+ test references across 22 files. Zero A2A code exists — migration not started. All open PRs that touch ACP modules will need additional rebase work after #688/#689 merge. TUI spec adds ~1,500 lines with 18 ASCII mockups defining Textual-based UI — PR #667 was a placeholder that predates this spec. Server architecture adopts JSON-RPC 2.0 standard — PR #676 used custom protocol, now obsolete.
|
||||
|
||||
@@ -5233,14 +5233,15 @@ Deadline risk: CRITICAL
|
||||
|
||||
**Notes**
|
||||
|
||||
- Day 99 update (2026-04-09). Session 4 remains active (#4799, 32 parallel workers, full supervisor fleet).
|
||||
- Open PRs surged from 1 to 145 (+144 new PRs opened by agents since Day 98). Agents are actively implementing features and fixes across all active milestones.
|
||||
- Open bugs exploded from ~878 to ~2861 (+1983 new bugs). Bug-hunter, UAT, and spec-compliance agents filed massive volumes of new issues. This is the largest single-day bug increase recorded.
|
||||
- Milestone scope continued to grow due to agent-driven issue creation: M3 (320→387, +67), M4 (161→191, +30), M5 (183→187, +4), M6 (638→711, +73), M7 (312→313, +1), M8 (855→880, +25), M9 new data (435 total, 129 closed).
|
||||
- Milestone completion percentages dropped despite stable or growing closed counts, due to scope expansion outpacing closures: M3 73%→62%, M4 67%→56%, M5 71%→69%, M6 29%→27%, M7 48%→47%.
|
||||
- M8 (v3.7.0) closed count grew: 403→422 (+19 issues closed). M9 (v3.8.0) now tracked: 129/435 = 29% complete, 306 open.
|
||||
- Architecture review agent (issue #5158) and human liaison (issue #5157) both active. Backlog groomer (issue #5152) and system watchdog (issue #5150) running. Spec updater (issue #5145) and agent evolver (issue #5143) active.
|
||||
- All milestones M3-M7 remain overdue. Critical path: triage 2861 open bugs, review 145 open PRs, continue M3/M4/M5 backlog clearance.
|
||||
- Day 99 update (2026-04-09). Session 4 active (issue #4799) with 32 parallel workers targeting v3.2.0–v3.7.0 completion.
|
||||
- Massive scope expansion across all milestones since Day 98: M3 grew from 320→526 (+206 new issues), M4 grew to 216, M5 grew to 234, M6 grew from 638→1040 (+402 new issues), M7 grew to 381, M8 grew from 855→935 (+80 new issues).
|
||||
- Completion percentages dropped significantly due to scope expansion despite continued issue closures: M3 73%→47%, M4 67%→50%, M5 71%→57%, M6 29%→19%, M7 48%→39%, M8 47%→45%.
|
||||
- Open PRs surged from 1 to 183 as agents opened new fix/feature/docs PRs across all milestones.
|
||||
- Open bugs increased dramatically from ~878 to ~3,615 — agent-driven UAT expansion at high velocity. Bug count grew by ~2,737 in one day.
|
||||
- Milestone closures (absolute): M3 235→248 (+13 closed), M4 108→108 (stable), M5 130→133 (+3 closed), M6 188→197 (+9 closed), M7 150→150 (stable), M8 403→422 (+19 closed), M9 118→130 (+12 closed).
|
||||
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
|
||||
- Multiple timeline update PRs already open for Day 99 (#5085, #5185, #5214, #5578, #6213) — this is an additional cycle-6 refresh with latest Forgejo data.
|
||||
- Session 4 supervisor fleet continues autonomous operation. UAT pool, PR reviewer pool, implementation pool, and spec updater agents all running.
|
||||
|
||||
|
||||
#### Milestone forecast
|
||||
@@ -5249,34 +5250,34 @@ Deadline risk: CRITICAL
|
||||
|-----------|---------------|-------|------|
|
||||
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
|
||||
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-15 | +78d | CRITICAL — 147 open issues; 62% complete (scope grew 320→387, +67 new issues) |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-20 | +79d | CRITICAL — 83 open issues; 56% complete (scope grew 161→191, +30 new issues) |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-10 | +65d | HIGH — 57 open issues; 69% complete (scope grew 183→187) |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-07-15 | +127d | CRITICAL — 519 open issues; 27% complete (scope grew 638→711, +73 new issues) |
|
||||
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-05 | +69d | HIGH — 163 open issues; 47% complete |
|
||||
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-20 | N/A | HIGH — 458 open issues; 47% complete (scope grew 855→880) |
|
||||
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-10 | N/A | HIGH — 306 open issues; 29% complete; 2861 total open bugs |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-15 | +78d | CRITICAL — 278 open issues; 47% complete (scope expanded 320→526) |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-20 | +79d | CRITICAL — 108 open issues; 50% complete (scope expanded to 216) |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-20 | +75d | CRITICAL — 101 open issues; 57% complete (scope expanded to 234) |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-08-01 | +144d | CRITICAL — 843 open issues; 19% complete (scope expanded 638→1040) |
|
||||
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-20 | +84d | HIGH — 231 open issues; 39% complete (scope expanded to 381) |
|
||||
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-20 | N/A | HIGH — 513 open issues; 45% complete (scope expanded 855→935) |
|
||||
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-01 | N/A | MEDIUM — 336 open issues; 28% complete |
|
||||
|
||||
#### Track forecast
|
||||
|
||||
| Track | Status | ETA | Risk | Blocking |
|
||||
|-------|--------|-----|------|----------|
|
||||
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
|
||||
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-10 | MEDIUM | 57 open issues in v3.4.0; scope grew +4 |
|
||||
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-20 | CRITICAL | 83 open issues in v3.3.0; scope grew +30; UAT spec compliance bugs ongoing |
|
||||
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-15 | CRITICAL | 147 open issues in v3.2.0; scope grew +67; agent-driven expansion outpacing closures |
|
||||
| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | 2861 open bugs (+1983 in one day!); 145 open PRs need review |
|
||||
| Track T (Testing) | Active | Ongoing | HIGH | 145 open PRs need review; UAT/bug-hunter agents filing bugs at high velocity |
|
||||
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-20 | HIGH | 101 open issues in v3.4.0; scope expanded to 234 total |
|
||||
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-20 | CRITICAL | 108 open issues in v3.3.0; scope expanded to 216 total |
|
||||
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-15 | CRITICAL | 278 open issues in v3.2.0; scope expanded 320→526 |
|
||||
| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | ~3,615 open bugs; massive agent-driven UAT expansion (+2,737 in one day) |
|
||||
| Track T (Testing) | Active | Ongoing | HIGH | 183 open PRs need review; UAT pool supervisor active (#4799) |
|
||||
|
||||
#### Developer forecast
|
||||
|
||||
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|
||||
|------|-------------------|--------------|------|-------|
|
||||
| Jeff | -24d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight; PR review |
|
||||
| Luis | -24d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool; bug triage |
|
||||
| Jeff | -24d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight; 183 open PRs |
|
||||
| Luis | -24d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool |
|
||||
| Hamza | -24d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews |
|
||||
| Aditya | -24d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
|
||||
| Brent | -24d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 2861 open bugs triage |
|
||||
| Brent | -24d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; ~3,615 open bugs triage |
|
||||
| Rui | -24d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
|
||||
| Mike/Brian | N/A | standby | LOW | Infrastructure support |
|
||||
|
||||
@@ -5288,16 +5289,16 @@ Milestone per developer as of Day 99 (2026-04-09).
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
|
||||
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 147 open | 240/387 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 83 open | 108/191 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 57 open | 130/187 |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 519 open | 192/711 |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 163 open | 150/313 |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 458 open | 422/880 |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 306 open | 129/435 |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1733 open** | **1467/3200** |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 278 open | 248/526 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 108 open | 108/216 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 101 open | 133/234 |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 843 open | 197/1040 |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 231 open | 150/381 |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 513 open | 422/935 |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 336 open | 130/466 |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~2410 open** | **1484/3950** |
|
||||
|
||||
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 99 (2026-04-09). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues at high velocity. Bug count exploded from ~878 to ~2861 (+1983) due to UAT pool, bug-hunter, and spec-compliance agents filing issues at unprecedented rate. M3 scope grew 320→387 (+67), M4 grew 161→191 (+30), M5 grew 183→187 (+4), M6 grew 638→711 (+73), M8 grew 855→880 (+25). M9 now tracked: 129/435 closed (29%).
|
||||
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 99 (2026-04-09). Massive scope expansion across all milestones due to agent-driven issue creation. M3 grew from 320→526 (+206), M6 grew from 638→1040 (+402), M8 grew from 855→935 (+80). Open bugs surged from ~878 to ~3,615 (+2,737 new UAT bugs). Open PRs surged from 1 to 183 as agents opened new fix/feature/docs PRs.
|
||||
|
||||
#### Story point allocation
|
||||
|
||||
|
||||