docs(timeline): update schedule adherence Day 99 (2026-04-09) #5214
+128
-29
@@ -10,25 +10,25 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
|
||||
@startgantt
|
||||
|
||||
title CleverAgents Core — Epic-Level Project Schedule
|
||||
footer Generated 2026-04-08 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~878 open bugs | 1 open PR | Session 4 active
|
||||
footer Generated 2026-04-09 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3181 open bugs | 167 open PRs | Session 4 active
|
||||
|
||||
Project starts 2026-02-03
|
||||
saturday are closed
|
||||
sunday are closed
|
||||
printscale weekly zoom 2
|
||||
|
||||
today is 2026-04-08
|
||||
today is 2026-04-09
|
||||
today is colored in #FF6666
|
||||
|
||||
' ================================================================
|
||||
' GANTT CHART UPDATE LOG (Day 98 — 2026-04-08)
|
||||
' Changes: Day 98 refresh. New build session #4799 launched 2026-04-08.
|
||||
' Open PRs: 108→1 (massive merge wave). Open bugs: ~878 (stable).
|
||||
' M3 73% (235/320), M4 67% (108/161), M5 71% (130/183), M6 29% (188/638, scope expanded!),
|
||||
' M7 48% (150/312), M8 47% (403/855).
|
||||
' Progress since Day 96: M3 +8%, M4 +7%, M5 +3%, M7 +5%, M8 +1%.
|
||||
' M6 scope expanded massively: 327→638 total issues (+311 new issues added).
|
||||
' Session 4 active. Session tracker issue: #4799.
|
||||
' GANTT CHART UPDATE LOG (Day 99 — 2026-04-09)
|
||||
' Changes: Day 99 refresh. Session 4 active (issue #4799, 32 workers).
|
||||
' Open PRs: 1→167 (agent-driven PR creation wave). Open bugs: ~878→~3181 (massive bug surge).
|
||||
' M3 52% (245/474), M4 54% (108/200), M5 60% (130/217), M6 19% (193/1000, scope explosion!),
|
||||
' M7 43% (150/352), M8 46% (422/927), M9 29% (129/442).
|
||||
' All milestones declined in % due to massive agent-driven issue creation.
|
||||
' M6 scope exploded: 638→1000 total issues (+362 new issues added).
|
||||
' Open bugs surged from ~878 to ~3181 (+2303 new bugs filed by agents).
|
||||
' ================================================================
|
||||
|
||||
<style>
|
||||
@@ -400,15 +400,15 @@ legend right
|
||||
| v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs |
|
||||
| v3.6.0 | Mar 27 | 2 | 100 | Deferred work |
|
||||
----
|
||||
**Risk Register (Day 96 — 2026-04-06)**
|
||||
**Risk Register (Day 99 — 2026-04-09)**
|
||||
|= Epic |= Completion |= Risk |= Blocker |
|
||||
| M3 (#357) | 65% | **CRITICAL** | 131 open issues in v3.2.0 |
|
||||
| M4 (#358) | 60% | **CRITICAL** | 74 open issues in v3.3.0 |
|
||||
| M5 (#359) | 68% | **HIGH** | 63 open issues in v3.4.0 |
|
||||
| M6 (#360) | 55% | **HIGH** | 147 open issues in v3.5.0 |
|
||||
| M7 (#361) | 43% | **HIGH** | 198 open issues in v3.6.0 |
|
||||
| M8 (#362) | 46% | **HIGH** | 499 open issues in v3.7.0 (agent expansion) |
|
||||
| SEC (#363) | 28% | **HIGH** | 336 open issues in v3.8.0 (agent expansion) |
|
||||
| M3 (#357) | 52% | **CRITICAL** | 229 open issues in v3.2.0 (milestone grew 320→474) |
|
||||
| M4 (#358) | 54% | **CRITICAL** | 92 open issues in v3.3.0 (milestone grew 161→200) |
|
||||
| M5 (#359) | 60% | **CRITICAL** | 87 open issues in v3.4.0 (milestone grew 183→217) |
|
||||
| M6 (#360) | 19% | **CRITICAL** | 807 open issues in v3.5.0 (scope explosion: 638→1000) |
|
||||
| M7 (#361) | 43% | **HIGH** | 202 open issues in v3.6.0 (milestone grew 312→352) |
|
||||
| M8 (#362) | 46% | **HIGH** | 505 open issues in v3.7.0 (milestone grew 855→927) |
|
||||
| SEC (#363) | 29% | **HIGH** | 313 open issues in v3.8.0 (milestone grew 442→467) |
|
||||
----
|
||||
**Color Key**
|
||||
|= Color |= Meaning |
|
||||
@@ -416,11 +416,11 @@ legend right
|
||||
| <back:LightSkyBlue> </back> | In Progress |
|
||||
| <back:#E8E8E8> </back> | Not Started |
|
||||
| <back:Gold> <> </back> | Milestone Target |
|
||||
| <back:#FF6666> | </back> | Today (2026-04-06) |
|
||||
| <back:#FF6666> | </back> | Today (2026-04-09) |
|
||||
----
|
||||
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
|
||||
~1649 total story points | ~3300 estimated hours
|
||||
**~878 open bugs — 108 open PRs — Session 3 active (16 workers, ~71 agents)**
|
||||
**~3181 open bugs — 167 open PRs — Session 4 active (32 workers)**
|
||||
end legend
|
||||
|
||||
@endgantt
|
||||
@@ -444,7 +444,7 @@ saturday are closed
|
||||
sunday are closed
|
||||
printscale weekly zoom 2
|
||||
|
||||
today is 2026-04-08
|
||||
today is 2026-04-09
|
||||
today is colored in #FF6666
|
||||
|
||||
<style>
|
||||
@@ -1949,11 +1949,11 @@ legend right
|
||||
| <back:LightSkyBlue> </back> | Issue: In Progress |
|
||||
| <back:#E8E8E8> </back> | Issue: Not Started |
|
||||
| <back:Gold> <> </back> | Milestone Target |
|
||||
| <back:#FF6666> | </back> | Today (2026-04-05) |
|
||||
| <back:#FF6666> | </back> | Today (2026-04-09) |
|
||||
----
|
||||
271 Issues | 29 Epics | 9 Legendaries | 7 Milestones
|
||||
~1649 total story points | ~3300 estimated hours
|
||||
**878 open bugs — 183 open PRs — Session 3 active (16 workers, ~71 agents)**
|
||||
**~3181 open bugs — 167 open PRs — Session 4 active (32 workers)**
|
||||
end legend
|
||||
|
||||
@endgantt
|
||||
@@ -1965,13 +1965,13 @@ This section provides a high-level overview of the CleverAgents implementation r
|
||||
|
||||
### Current Status Summary
|
||||
|
||||
As of Day 98 (2026-04-08), the project has **1 open PR** (down from 108 — massive merge wave!) and **~1458 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~878 open bugs** (stable). M8 (v3.7.0) is now **47% complete** (403/855 issues closed). M3 (v3.2.0) at **73%** (235/320), M4 (v3.3.0) at **67%** (108/161), M5 (v3.4.0) at **71%** (130/183), M6 (v3.5.0) at **29%** (188/638 — scope massively expanded from 327 to 638 issues), M7 (v3.6.0) at **48%** (150/312).
|
||||
As of Day 99 (2026-04-09), the project has **167 open PRs** and **~2235 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count has surged to **~3,181 open bugs** (up from ~878 — massive agent-driven bug filing wave). M8 (v3.7.0) is now **46% complete** (422/927 issues closed). M3 (v3.2.0) at **52%** (245/474), M4 (v3.3.0) at **54%** (108/200), M5 (v3.4.0) at **60%** (130/217), M6 (v3.5.0) at **19%** (193/1000 — scope exploded from 638 to 1000 issues), M7 (v3.6.0) at **43%** (150/352).
|
||||
|
||||
**M1, M2 fully complete. M3 (v3.2.0)**: 73% complete (235/320), 85 open issues. **M4 (v3.3.0)**: 67% complete (108/161), 53 open issues. **M5 (v3.4.0)**: 71% complete (130/183), 53 open issues. **M6 (v3.5.0)**: 29% complete (188/638), 450 open issues — scope expanded massively (+311 new issues). **M7 (v3.6.0)**: 48% complete (150/312), 162 open issues. **M8 (v3.7.0)**: 47% complete (403/855), 452 open issues. All milestones M3-M7 are **overdue**; M8 is in active v3.7.0 development.
|
||||
**M1, M2 fully complete. M3 (v3.2.0)**: 52% complete (245/474), 229 open issues. **M4 (v3.3.0)**: 54% complete (108/200), 92 open issues. **M5 (v3.4.0)**: 60% complete (130/217), 87 open issues. **M6 (v3.5.0)**: 19% complete (193/1000), 807 open issues — scope exploded from 638 to 1000 total (+362 new issues). **M7 (v3.6.0)**: 43% complete (150/352), 202 open issues. **M8 (v3.7.0)**: 46% complete (422/927), 505 open issues. **M9 (v3.8.0)**: 29% complete (129/442), 313 open issues. All milestones M3-M7 are **overdue**; M8/M9 are in active development.
|
||||
|
||||
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — ~878 Open Bugs — Session 4 Active (Day 98: New Session #4799, M6 Scope Expanded +311 Issues)"
|
||||
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — ~3181 Open Bugs — Session 4 Active (Day 99: M6 Scope Exploded to 1000 Issues, Bug Count Surged to ~3181)"
|
||||
|
||||
All milestones M3 through M7 have passed their target dates. **Session 4 launched 2026-04-08 with 32 parallel workers**. Open PRs at **1** (down from 108 — massive merge wave). Open bugs at **~878** (stable). Session tracker issue: #4799. **Current priorities**: (1) **M6 scope explosion** — 450 open issues (was 147 at Day 96); agent-driven issue creation expanded scope from 327 to 638 total. (2) **Triage ~878 open bugs** — systematic review required. (3) **Continue M8 push** — 47% complete, 452 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 73% (85 open), M4 at 67% (53 open), M5 at 71% (53 open).
|
||||
All milestones M3 through M7 have passed their target dates. **Session 4 active (launched 2026-04-08, issue #4799) with 32 parallel workers**. Open PRs at **167** (up from 1 — agent-driven PR creation wave). Open bugs at **~3,181** (up from ~878 — massive +2303 bug surge from agent-driven bug filing). Session tracker issue: #4799. **Current priorities**: (1) **M6 scope explosion** — 807 open issues (was 450 at Day 98); scope grew from 638 to 1000 total. (2) **Triage ~3,181 open bugs** — systematic review urgently required. (3) **Continue M8 push** — 46% complete, 505 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 52% (229 open), M4 at 54% (92 open), M5 at 60% (87 open).
|
||||
|
||||
### Parallel Workstreams
|
||||
|
||||
@@ -1985,8 +1985,8 @@ Development is organized into six concurrent workstreams plus continuous quality
|
||||
| **D** — Decisions & Apply | Decision tree model, change tracking, diff review, apply pipeline, correction engine | **Complete.** Decision recording (#172, PR #433) and plan explain CLI (#174, PR #464) merged Days 23-24 (Hamza). Influence DAG traversal (#542) merged Day 24 (Jeff). Cross-plan correction cascading (#547) merged Day 24 (Jeff). |
|
||||
| **E** — Subplans | Subplan domain model, orchestration, parallel execution, three-way merge | **Complete.** Subplan execute+merge (#184) merged Mar 1. Subplan service (#197) merged in integration batch Mar 2. |
|
||||
| **F** — ACMS & Context | UKO ontology, CRP protocol, context strategies, assembly pipeline, hot/warm/cold tiers | **Complete.** All ACMS v1 components merged. Repo indexing (#195, PR #610) **merged Day 30** (Hamza). Strategy coordinator (#192) **merged Day 30** (Jeff). UKO Layer 1 merged. Remaining: UKO Layer 2 (#575, PR #657 in review) and Layer 3 (#576, PR #660 in review) — both are Could Have / Low priority. |
|
||||
| **Q** — Quality & CI | Pre-commit hooks, Forgejo CI/CD, coverage enforcement (97%), security scanning | **Complete.** Coverage at 97-98%. |
|
||||
| **T** — Testing | Behave unit tests, Robot integration tests, ASV benchmarks, end-to-end smoke suites | **Active.** M3 E2E (#494 **merged**), M4 E2E (#495 **merged**), M5 E2E (#496 — PR #725 merged), M6 E2E (#497 — PR #1277 **merged**). TDD infra merged. 6 open bugs (down from 143 — massive CLI fix wave). UAT workers actively testing; security bug-hunt PRs (#1412, #1409, #1419) open for v3.7.0. |
|
||||
| **Q** — Quality & CI | Pre-commit hooks, Forgejo CI/CD, coverage enforcement (97%), security scanning | **Active.** Coverage at 97-98%. **~3,181 open bugs** (surged from ~878 — massive agent-driven bug filing wave). Systematic triage urgently required. |
|
||||
| **T** — Testing | Behave unit tests, Robot integration tests, ASV benchmarks, end-to-end smoke suites | **Active.** M3 E2E (#494 **merged**), M4 E2E (#495 **merged**), M5 E2E (#496 — PR #725 merged), M6 E2E (#497 — PR #1277 **merged**). TDD infra merged. 167 open PRs need review. UAT workers actively testing; Session 4 active with 32 workers. |
|
||||
|
||||
### What Has Been Completed
|
||||
|
||||
@@ -5223,3 +5223,102 @@ Story points per developer per milestone.
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
|
||||
|
||||
### 2026-04-09 (Day 99)
|
||||
|
||||
**Summary**
|
||||
|
||||
Status: Behind 20+d
|
||||
Deadline risk: CRITICAL
|
||||
|
||||
**Notes**
|
||||
|
||||
- Day 99 update (2026-04-09). Session 4 active (issue #4799, 32 parallel workers, full supervisor fleet).
|
||||
- Open PRs surged from 1 to **167** (+166 new agent-driven PRs opened since Day 98). Massive agent-driven PR creation wave.
|
||||
- Open bugs surged from ~878 to **~3,181** (+2,303 new bugs filed by agents). This is a critical escalation requiring systematic triage.
|
||||
- Milestone totals grew significantly due to continued agent-driven issue creation: M3 (320→474, +154), M4 (161→200, +39), M5 (183→217, +34), M6 (638→1000, +362 — scope explosion continues!), M7 (312→352, +40), M8 (855→927, +72), M9 (467→442, net -25 — some issues closed/moved).
|
||||
- Milestone completions (Day 99): M3 52% (245/474), M4 54% (108/200), M5 60% (130/217), M6 19% (193/1000), M7 43% (150/352), M8 46% (422/927), M9 29% (129/442).
|
||||
- All milestone percentages declined from Day 98 due to massive scope expansion outpacing closures. M6 dropped from 29% to 19% as scope grew from 638 to 1000 total issues.
|
||||
- M1 (v3.0.0) and M2 (v3.1.0) remain fully closed (163 and 108 issues respectively).
|
||||
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
|
||||
- Session 4 continues with 32 parallel workers targeting v3.2.0–v3.7.0 completion. Agent-driven issue creation and bug filing at very high velocity.
|
||||
- **Cycle-2 update (2026-04-09 ~09:10 UTC)**: M3 open grew 229→246 (+17), M6 open grew 807→815 (+8), M7 open grew 202→211 (+9), M9 open grew 313→315 (+2). Open PRs: 167→173. No new closures — scope expansion only.
|
||||
- **Cycle-3 update (2026-04-09 ~09:40 UTC)**: M3 closed grew 245→247 (+2 new closures!), M3 open grew 246→252 (+6 net), M4 open grew 92→95 (+3), M5 open grew 87→88 (+1), M6 open grew 815→819 (+4), M7 open grew 211→221 (+10), M9 open grew 315→321 (+6). Open PRs: 173→171 (-2 merged). M3 now 247/499 = 49%.
|
||||
- **Cycle-4 update (2026-04-09 ~10:10 UTC)**: M2 gained 1 new open issue (1/109 total — anomaly). M3 open grew 252→258 (+6). M5 open grew 88→92 (+4). M6 open grew 819→820 (+1). M8 open grew 506→507 (+1). M9 closed grew 129→130 (+1 closure), open grew 321→325 (+4). Open PRs: 171→173 (+2 new). Continued scope expansion across all milestones.
|
||||
- **Cycle-5 update (2026-04-09 ~10:40 UTC)**: M2 open grew 1→2 (+1 more anomaly). M3 open grew 258→261 (+3). M5 open grew 92→93 (+1). M6 open grew 820→824 (+4). M8 open grew 507→513 (+6). M9 open grew 325→336 (+11). Open PRs: 173→175 (+2). No new closures — continued scope expansion only.
|
||||
- **Cycle-6 update (2026-04-09 ~11:10 UTC)**: M3 closed grew 247→248 (+1 closure!), open grew 261→269 (+8 net). M4 closed grew 130→132 (+2 closures!), open grew 93→96 (+3 net). M5 open grew 93→96 (+3). M6 open grew 824→833 (+9). M7 open grew 221→222 (+1). M9 open reduced 336→334 (-2 moved/closed). Open PRs: 175→180 (+5). M3 now 248/517 = 48%, M4 now 132/228 = 58%.
|
||||
|
||||
|
||||
#### Milestone forecast
|
||||
|
||||
| Milestone | Target -> ETA | Delta | Risk |
|
||||
|-----------|---------------|-------|------|
|
||||
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
|
||||
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-06-01 | +96d | CRITICAL — 246 open issues; 50% complete (scope grew 320→491) |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-06-05 | +95d | CRITICAL — 92 open issues; 54% complete (scope grew 161→200) |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-06-05 | +91d | CRITICAL — 87 open issues; 60% complete (scope grew 183→217) |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-09-01 | +175d | CRITICAL — 807 open issues; 19% complete (scope exploded 638→1000) |
|
||||
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-15 | +79d | HIGH — 202 open issues; 43% complete (scope grew 312→352) |
|
||||
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-20 | N/A | HIGH — 505 open issues; 46% complete (scope grew 855→927) |
|
||||
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-01 | N/A | MEDIUM — 313 open issues; 29% complete |
|
||||
|
||||
#### Track forecast
|
||||
|
||||
| Track | Status | ETA | Risk | Blocking |
|
||||
|-------|--------|-----|------|----------|
|
||||
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
|
||||
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-06-05 | HIGH | 87 open issues in v3.4.0; scope grew 183→217 |
|
||||
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-06-05 | CRITICAL | 92 open issues in v3.3.0; scope grew 161→200 |
|
||||
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-06-01 | CRITICAL | 229 open issues in v3.2.0; scope grew 320→474 |
|
||||
| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | ~3,181 open bugs (surged from ~878); systematic triage urgently required |
|
||||
| Track T (Testing) | Active | Ongoing | HIGH | 167 open PRs need review; Session 4 active with 32 workers |
|
||||
|
||||
#### Developer forecast
|
||||
|
||||
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|
||||
|------|-------------------|--------------|------|-------|
|
||||
| Jeff | -24d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight; 167 open PRs |
|
||||
| Luis | -24d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool; bug triage |
|
||||
| Hamza | -24d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews |
|
||||
| Aditya | -24d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
|
||||
| Brent | -24d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; ~3,181 open bugs triage |
|
||||
| Rui | -24d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
|
||||
| Mike/Brian | N/A | standby | LOW | Infrastructure support |
|
||||
|
||||
#### Task inventory
|
||||
|
||||
Milestone per developer as of Day 99 (2026-04-09).
|
||||
|
||||
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
|
||||
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 229 open | 245/474 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 92 open | 108/200 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 87 open | 130/217 |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 807 open | 193/1000 |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 202 open | 150/352 |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 505 open | 422/927 |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 313 open | 129/442 |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~2235 open** | **1479/3708** |
|
||||
|
||||
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 99 (2026-04-09). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues at very high velocity across all milestones. M3 grew from 320→474 (+154), M4 grew from 161→200 (+39), M5 grew from 183→217 (+34), M6 grew from 638→1000 (+362 — scope explosion), M7 grew from 312→352 (+40), M8 grew from 855→927 (+72). Open bugs surged from ~878 to ~3,181 (+2,303 new bugs filed by agents).
|
||||
|
||||
#### Story point allocation
|
||||
|
||||
Story points per developer per milestone.
|
||||
|
||||
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~172 SP |
|
||||
| M2 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~208 SP |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~104 SP |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~126 SP |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~129 SP |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~100 SP |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
|
||||
|
||||