docs(timeline): update schedule adherence Day 95 final (2026-04-05) #3351

Closed
freemo wants to merge 1 commits from docs/timeline-day95-final-2026-04-05 into master
+54 -54
View File
@@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 536 open bugs | 92 open PRs | Session 3 active
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 701 open bugs | 97 open PRs | Session 3 active
Project starts 2026-02-03
saturday are closed
@@ -22,10 +22,10 @@ today is colored in #FF6666
' ================================================================
' GANTT CHART UPDATE LOG (Day 95 — 2026-04-05)
' Changes: Day 95 update (refreshed). Open PRs: 76→92 (+16). Open bugs: 536 (stable).
' Changes: Day 95 final refresh. Open PRs: 92→97 (+5). Open bugs: 536→701 (+165 agent-driven).
' Open issues: continued agent-driven expansion across all milestones.
' M3 67% (223/334), M4 63% (103/163), M5 70% (126/179), M6 67% (175/263),
' M7 55% (127/232), M8 52% (332/634), M9 27% (105/393).
' M3 66% (224/340), M4 63% (103/164), M5 70% (126/179), M6 59% (176/298),
' M7 47% (127/272), M8 45% (338/745), M9 26% (108/412).
' Session 3 active. UAT pool supervisor and spec updater agents running.
' Session tracker issue: #3075 (autonomous build progress report).
' ================================================================
@@ -229,7 +229,7 @@ ganttDiagram {
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
[M3] starts at [M2]'s end
[M3] is 70% completed
[M3] is 66% completed
[M3] is colored in LightSkyBlue/SteelBlue
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
@@ -250,13 +250,13 @@ ganttDiagram {
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
[M4] starts at [M3]'s end
[M4] is 72% completed
[M4] is 63% completed
[M4] is colored in LightSkyBlue/SteelBlue
[Security + Safety Hardening (#362)] as [SEC] on {Luis} requires 3 days
[SEC] starts 2026-03-02
[SEC] is 78% completed
[SEC] is 26% completed
[SEC] is colored in LightSkyBlue/SteelBlue
[Provider Fixes + Runtime (#363)] as [PROV] on {Luis} requires 2 days
@@ -281,12 +281,12 @@ ganttDiagram {
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
[M5] starts at [M4]'s end
[M5] is 75% completed
[M5] is 70% completed
[M5] is colored in LightSkyBlue/SteelBlue
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
[M6] starts at [M5]'s end
[M6] is 67% completed
[M6] is 59% completed
[M6] is colored in LightSkyBlue/SteelBlue
[Subplans + Parallelism (#368)] as [SUBP] on {Luis} {Brent} requires 2 days
@@ -296,7 +296,7 @@ ganttDiagram {
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
[LARGE] starts 2026-03-17
[LARGE] is 55% completed
[LARGE] is 47% completed
[LARGE] is colored in LightSkyBlue/SteelBlue
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
@@ -400,13 +400,13 @@ legend right
----
**Risk Register (Day 95 — 2026-04-05 refreshed)**
|= Epic |= Completion |= Risk |= Blocker |
| M3 (#357) | 67% | **CRITICAL** | 111 open issues in v3.2.0 |
| M4 (#358) | 63% | **CRITICAL** | 60 open issues in v3.3.0 |
| M3 (#357) | 66% | **CRITICAL** | 116 open issues in v3.2.0 |
| M4 (#358) | 63% | **CRITICAL** | 61 open issues in v3.3.0 |
| M5 (#359) | 70% | **HIGH** | 53 open issues in v3.4.0 |
| M6 (#360) | 67% | **HIGH** | 88 open issues in v3.5.0 |
| M7 (#361) | 55% | **HIGH** | 105 open issues in v3.6.0 |
| M8 (#362) | 52% | **HIGH** | 302 open issues in v3.7.0 (agent expansion) |
| SEC (#363) | 27% | **HIGH** | 288 open issues in v3.8.0 (agent expansion) |
| M6 (#360) | 59% | **HIGH** | 122 open issues in v3.5.0 |
| M7 (#361) | 47% | **HIGH** | 145 open issues in v3.6.0 |
| M8 (#362) | 45% | **HIGH** | 407 open issues in v3.7.0 (agent expansion) |
| SEC (#363) | 26% | **HIGH** | 304 open issues in v3.8.0 (agent expansion) |
----
**Color Key**
|= Color |= Meaning |
@@ -418,7 +418,7 @@ legend right
----
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
~1649 total story points | ~3300 estimated hours
**536 open bugs — 92 open PRs — Session 3 active (16 workers, ~71 agents)**
**701 open bugs — 97 open PRs — Session 3 active (16 workers, ~71 agents)**
end legend
@endgantt
@@ -1951,7 +1951,7 @@ legend right
----
271 Issues | 29 Epics | 9 Legendaries | 7 Milestones
~1649 total story points | ~3300 estimated hours
**536 open bugs — 76 open PRs — Session 3 active (16 workers, ~71 agents)**
**701 open bugs — 97 open PRs — Session 3 active (16 workers, ~71 agents)**
end legend
@endgantt
@@ -1963,13 +1963,13 @@ This section provides a high-level overview of the CleverAgents implementation r
### Current Status Summary
As of Day 95 (2026-04-05), the project has **76 open PRs** and **~2800+ open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **536 open bugs** (continued agent-driven expansion from 389). M8 (v3.7.0) is now **52% complete** (332/634 issues closed — milestone grew from 438→634). M9 (v3.8.0) is **27% complete** (105/393 issues closed).
As of Day 95 (2026-04-05), the project has **97 open PRs** and **~3000+ open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **701 open bugs** (continued agent-driven expansion from 536). M8 (v3.7.0) is now **45% complete** (338/745 issues closed — milestone grew from 634→745). M9 (v3.8.0) is **26% complete** (108/412 issues closed).
**M1, M2 fully complete. M3 (v3.2.0)**: 70% complete (222/317), 95 open issues. **M4 (v3.3.0)**: 72% complete (101/141), 40 open issues. **M5 (v3.4.0)**: 75% complete (126/169), 43 open issues. **M6 (v3.5.0)**: 67% complete (175/263), 88 open issues. **M7 (v3.6.0)**: 55% complete (127/232), 105 open issues. **M8 (v3.7.0)**: 52% complete (332/634), 302 open issues. **M9 (v3.8.0)**: 27% complete (105/393), 288 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
**M1, M2 fully complete. M3 (v3.2.0)**: 66% complete (224/340), 116 open issues. **M4 (v3.3.0)**: 63% complete (103/164), 61 open issues. **M5 (v3.4.0)**: 70% complete (126/179), 53 open issues. **M6 (v3.5.0)**: 59% complete (176/298), 122 open issues. **M7 (v3.6.0)**: 47% complete (127/272), 145 open issues. **M8 (v3.7.0)**: 45% complete (338/745), 407 open issues. **M9 (v3.8.0)**: 26% complete (108/412), 304 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 536 Open Bugs — Session 3 Active (Day 95: Continued Agent Expansion)"
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 701 Open Bugs — Session 3 Active (Day 95: Continued Agent Expansion)"
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **76** (up from 64). Open bugs at **536** (continued agent-driven expansion from 389). M8 (v3.7.0) at 52% (332/634 closed — milestone grew from 438→634). M9 (v3.8.0) at 27% (105/393 closed). New session tracker issues: #2874 (progress report), #2875 (UAT pool supervisor), #2876 (spec updater). **Current priorities**: (1) **Triage 536 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 76 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push** — 52% complete, 302 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 70% (95 open), M4 at 72% (40 open), M5 at 75% (43 open).
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **97** (up from 76). Open bugs at **701** (continued agent-driven expansion from 389). M8 (v3.7.0) at 45% (338/745 closed — milestone grew from 634→745). M9 (v3.8.0) at 26% (108/412 closed). New session tracker issues: #2874 (progress report), #2875 (UAT pool supervisor), #2876 (spec updater). **Current priorities**: (1) **Triage 701 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 97 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push**45% complete, 407 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 66% (116 open), M4 at 63% (61 open), M5 at 70% (53 open).
### Parallel Workstreams
@@ -2285,18 +2285,18 @@ Items without an assigned milestone represent backlog work to be addressed after
### Schedule Risk Summary
As of Day 95 (2026-04-05), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **76** (up from 64). Open bugs at **536** (continued agent-driven expansion from 389). M8 (v3.7.0) at **52% complete** (332/634 closed — milestone grew from 438→634). M9 (v3.8.0) at **27% complete** (105/393 closed). Critical path: 76 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 52% with 302 issues remaining; 536 open bugs need TDD counterparts and systematic triage.
As of Day 95 (2026-04-05), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **97** (up from 76). Open bugs at **701** (continued agent-driven expansion from 536). M8 (v3.7.0) at **45% complete** (338/745 closed — milestone grew from 634→745). M9 (v3.8.0) at **26% complete** (108/412 closed). Critical path: 97 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 45% with 407 issues remaining; 701 open bugs need TDD counterparts and systematic triage.
**Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry.
**Day 53 Session 3 actions**: (a) 16 parallel workers started. (b) 73+ PRs merged including ACMS UKO runtime (#1312), PermissionsScreen TUI (#1307), actor thought blocks (#1298), DatabaseResourceHandler (#1293), ACMS pipeline Phase 2 (#1287), DevcontainerHandler (#1286), async audit (#1279), serve CLI (#1272), LSP hover/definitions (#1240), domain event wiring (#1215), plan prompt command (#1212), M6 E2E tests (#1277), @tdd_expected_fail cleanup (#1229), persona export/import (#1338), first-run experience (#1391), session export/import (#1392). (c) UAT supervisor fleet (cycles 11-131) launched — discovered 100+ spec compliance bugs across CLI rich output, YAML config handling, and actor compiler. (d) Security bug-hunt PRs opened: #1412 (concurrency), #1409 (error handling), #1419 (hardcoded secrets). (e) Late-day: 4 more PRs merged (#1498, #1481, #1479, #1338), 18 new fix PRs opened (#1506-#1517) targeting UAT findings. (f) End-of-day CLI fix wave: 18 more PRs merged (#1574, #1573, #1570, #1569, #1567, #1566, #1565, #1563, #1562, #1558, #1556, #1554 and others) — open bugs reduced from **143 to 6**, open PRs at **74**.
**Critical path blockers** (ranked):
1. **76 open PRs need review** — continued agent-driven PR creation. All require review before merge.
2. **536 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued agent-driven expansion.
3. **M3-M7 backlog**95+40+43+88+105 open issues across M3-M7. All milestones regressed as agents added new issues.
4. **M8 (v3.7.0) at 52%**302 issues remaining (milestone grew from 438→634). Continued agent-driven expansion.
5. **M9 (v3.8.0) at 27%**288 issues remaining (milestone grew from 359→393). Significant expansion.
1. **97 open PRs need review** — continued agent-driven PR creation. All require review before merge.
2. **701 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued agent-driven expansion.
3. **M3-M7 backlog**116+61+53+122+145 open issues across M3-M7. All milestones regressed as agents added new issues.
4. **M8 (v3.7.0) at 45%**407 issues remaining (milestone grew from 634→745). Continued agent-driven expansion.
5. **M9 (v3.8.0) at 26%**304 issues remaining (milestone grew from 393→412). Significant expansion.
**Spec changes impact assessment (Day 31)**: ACP→A2A rename affects 10 source files, 13 classes, 640+ test references across 22 files. Zero A2A code exists — migration not started. All open PRs that touch ACP modules will need additional rebase work after #688/#689 merge. TUI spec adds ~1,500 lines with 18 ASCII mockups defining Textual-based UI — PR #667 was a placeholder that predates this spec. Server architecture adopts JSON-RPC 2.0 standard — PR #676 used custom protocol, now obsolete.
@@ -4949,11 +4949,11 @@ Deadline risk: HIGH
**Notes**
- Day 95 update (refreshed 2026-04-05). Open PRs: 92 (up from 76 earlier today, +16 new PRs). Open bugs: 536 (stable). Session tracker issue: #3075.
- Day 95 update (final refresh 2026-04-05). Open PRs: 97 (up from 92, +5 new PRs). Open bugs: 701 (up from 536, +165 agent-driven). Session tracker issue: #3075.
- Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. UAT pool supervisor, PR reviewer pool, implementation pool, and spec updater agents all running.
- Milestone totals continued to grow due to agent-driven issue creation: M3 (317→334), M4 (141→163), M5 (169→179), M6 (263 stable), M7 (232 stable), M8 (634 stable), M9 (393 stable).
- Milestone completions (Day 95 refreshed): M3 67% (223/334), M4 63% (103/163), M5 70% (126/179), M6 67% (175/263), M7 55% (127/232), M8 52% (332/634), M9 27% (105/393).
- M3 and M4 completion percentages declined from earlier Day 95 reading (M3: 70%→67%, M4: 72%→63%) because agent-driven issue creation is outpacing closures.
- Milestone totals continued to grow due to agent-driven issue creation: M3 (334→340), M4 (163→164), M5 (179 stable), M6 (263→298), M7 (232→272), M8 (634→745), M9 (393→412).
- Milestone completions (Day 95 final): M3 66% (224/340), M4 63% (103/164), M5 70% (126/179), M6 59% (176/298), M7 47% (127/272), M8 45% (338/745), M9 26% (108/412).
- M6, M7, M8, M9 completion percentages declined significantly as agent-driven issue creation outpaced closures. Open bugs surged from 536 to 701 (+165).
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
- UAT pool supervisor (#3075) and spec updater agents are running autonomously, continuing to discover and file spec compliance issues.
- PR #3073 (docs/timeline-day95-refresh) is open with updated milestone data — this entry supersedes it.
@@ -4965,34 +4965,34 @@ Deadline risk: HIGH
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-04-28 | +61d | CRITICAL — 111 open issues; agent-driven expansion outpacing closures |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-02 | +61d | CRITICAL — 60 open issues; completion dropped 72%→63% |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-02 | +57d | HIGH — 53 open issues; 70% complete |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-10 | +61d | HIGH — 88 open issues; 67% complete |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-05-25 | +58d | HIGH — 105 open issues; 55% complete |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-06-20 | N/A | HIGH — 302 open issues; 52% complete |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-10 | N/A | MEDIUM — 288 open issues; 27% complete |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-05 | +68d | CRITICAL — 116 open issues; agent-driven expansion outpacing closures |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-10 | +69d | CRITICAL — 61 open issues; completion at 63% |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-08 | +63d | HIGH — 53 open issues; 70% complete |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-20 | +71d | HIGH — 122 open issues; 59% complete |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-05 | +69d | HIGH — 145 open issues; 47% complete |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-01 | N/A | HIGH — 407 open issues; 45% complete |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-01 | N/A | HIGH — 304 open issues; 26% complete |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-02 | MEDIUM | 53 open issues in v3.4.0; continued agent-driven expansion |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-02 | CRITICAL | 60 open issues in v3.3.0; UAT spec compliance bugs ongoing; completion dropped |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-04-28 | CRITICAL | 111 open issues in v3.2.0; agent-driven expansion outpacing closures |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 536 open bugs; continued agent-driven bug creation |
| Track T (Testing) | Active | Ongoing | HIGH | 92 open PRs need review; UAT pool supervisor active (#3075) |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-08 | HIGH | 53 open issues in v3.4.0; continued agent-driven expansion |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-10 | CRITICAL | 61 open issues in v3.3.0; UAT spec compliance bugs ongoing |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-05 | CRITICAL | 116 open issues in v3.2.0; agent-driven expansion outpacing closures |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 701 open bugs; continued agent-driven bug creation |
| Track T (Testing) | Active | Ongoing | HIGH | 97 open PRs need review; UAT pool supervisor active (#3075) |
#### Developer forecast
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|------|-------------------|--------------|------|-------|
| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance; 92 open PRs |
| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance; 97 open PRs |
| Luis | -21d behind | active | HIGH | M6 (v3.5.0) features; security hardening; audit session; PR review pool |
| Hamza | -21d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews |
| Aditya | -21d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 536 open bugs triage |
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 701 open bugs triage |
| Rui | -21d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
| Mike/Brian | N/A | standby | LOW | N/A |
@@ -5004,16 +5004,16 @@ Milestone per developer as of Day 95 (2026-04-05).
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 111 open | 223/334 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 60 open | 103/163 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 116 open | 224/340 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 61 open | 103/164 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 53 open | 126/179 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 88 open | 175/263 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 105 open | 127/232 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 302 open | 332/634 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 288 open | 105/393 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1007 open** | **1191/2198 closed** |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 122 open | 176/298 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 145 open | 127/272 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 407 open | 338/745 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 304 open | 108/412 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1208 open** | **1373/2581 closed** |
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 (refreshed 2026-04-05). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M3 grew from 317→334, M4 grew from 141→163, M5 grew from 169→179 due to continued agent activity.
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 (final refresh 2026-04-05). Most open issues are unassigned. Agent-driven issue creation continues across all milestones. M3 grew from 334→340, M4 from 163→164, M6 from 263→298, M7 from 232→272, M8 from 634→745, M9 from 393→412 due to continued agent activity. Open bugs surged from 536 to 701.
#### Story point allocation