docs(timeline): update schedule adherence Day 95 update 3 (2026-04-05) #3056

Closed
freemo wants to merge 1 commits from docs/timeline-day-95-2026-04-05-update3 into master
+63 -60
View File
@@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 536 open bugs | 76 open PRs | Session 3 active
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 682 open bugs | 91 open PRs | Session 3 active
Project starts 2026-02-03
saturday are closed
@@ -21,13 +21,13 @@ today is 2026-04-05
today is colored in #FF6666
' ================================================================
' GANTT CHART UPDATE LOG (Day 95 — 2026-04-05)
' Changes: Day 95 update. Open PRs: 64→76 (+12). Open bugs: 389→536 (+147 agent-driven).
' GANTT CHART UPDATE LOG (Day 95 — 2026-04-05 update 3)
' Changes: Day 95 update 3. Open PRs: 64→91 (+27). Open bugs: 389→682 (+293 agent-driven).
' Open issues: continued agent-driven expansion across all milestones.
' M3 70% (222/317), M4 72% (101/141), M5 75% (126/169), M6 67% (175/263),
' M7 55% (127/232), M8 52% (332/634), M9 27% (105/393).
' Session 3 active. UAT pool supervisor and spec updater agents running.
' New session tracker issues: #2874 (progress report), #2875 (UAT pool), #2876 (spec updater).
' M3 69% (222/323), M4 64% (101/159), M5 71% (126/178), M6 63% (174/277),
' M7 50% (127/253), M8 46% (333/721), M9 26% (105/400).
' Session 3 active. UAT pool supervisor (#2875) and spec updater (#2876) running.
' New branches: fix/*, feat/*, improvement/*, spec/* branches active.
' ================================================================
<style>
@@ -229,7 +229,7 @@ ganttDiagram {
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
[M3] starts at [M2]'s end
[M3] is 70% completed
[M3] is 69% completed
[M3] is colored in LightSkyBlue/SteelBlue
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
@@ -250,7 +250,7 @@ ganttDiagram {
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
[M4] starts at [M3]'s end
[M4] is 72% completed
[M4] is 64% completed
[M4] is colored in LightSkyBlue/SteelBlue
@@ -281,12 +281,12 @@ ganttDiagram {
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
[M5] starts at [M4]'s end
[M5] is 75% completed
[M5] is 71% completed
[M5] is colored in LightSkyBlue/SteelBlue
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
[M6] starts at [M5]'s end
[M6] is 67% completed
[M6] is 63% completed
[M6] is colored in LightSkyBlue/SteelBlue
[Subplans + Parallelism (#368)] as [SUBP] on {Luis} {Brent} requires 2 days
@@ -296,7 +296,7 @@ ganttDiagram {
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
[LARGE] starts 2026-03-17
[LARGE] is 55% completed
[LARGE] is 50% completed
[LARGE] is colored in LightSkyBlue/SteelBlue
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
@@ -398,15 +398,15 @@ legend right
| v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs |
| v3.6.0 | Mar 27 | 2 | 100 | Deferred work |
----
**Risk Register (Day 95 — 2026-04-05)**
**Risk Register (Day 95 update 3 — 2026-04-05)**
|= Epic |= Completion |= Risk |= Blocker |
| M3 (#357) | 70% | **CRITICAL** | 95 open issues in v3.2.0 |
| M4 (#358) | 72% | **HIGH** | 40 open issues in v3.3.0 |
| M5 (#359) | 75% | **HIGH** | 43 open issues in v3.4.0 |
| M6 (#360) | 67% | **HIGH** | 88 open issues in v3.5.0 |
| M7 (#361) | 55% | **HIGH** | 105 open issues in v3.6.0 |
| M8 (#362) | 52% | **HIGH** | 302 open issues in v3.7.0 (agent expansion) |
| SEC (#363) | 27% | **HIGH** | 288 open issues in v3.8.0 (agent expansion) |
| M3 (#357) | 69% | **CRITICAL** | 101 open issues in v3.2.0 |
| M4 (#358) | 64% | **HIGH** | 58 open issues in v3.3.0 |
| M5 (#359) | 71% | **HIGH** | 52 open issues in v3.4.0 |
| M6 (#360) | 63% | **HIGH** | 103 open issues in v3.5.0 |
| M7 (#361) | 50% | **HIGH** | 126 open issues in v3.6.0 |
| M8 (#362) | 46% | **HIGH** | 388 open issues in v3.7.0 (agent expansion) |
| SEC (#363) | 26% | **HIGH** | 295 open issues in v3.8.0 (agent expansion) |
----
**Color Key**
|= Color |= Meaning |
@@ -418,7 +418,7 @@ legend right
----
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
~1649 total story points | ~3300 estimated hours
**536 open bugs — 76 open PRs — Session 3 active (16 workers, ~71 agents)**
**682 open bugs — 91 open PRs — Session 3 active (16 workers, ~71 agents)**
end legend
@endgantt
@@ -1951,7 +1951,7 @@ legend right
----
271 Issues | 29 Epics | 9 Legendaries | 7 Milestones
~1649 total story points | ~3300 estimated hours
**536 open bugs — 76 open PRs — Session 3 active (16 workers, ~71 agents)**
**682 open bugs — 91 open PRs — Session 3 active (16 workers, ~71 agents)**
end legend
@endgantt
@@ -1963,13 +1963,13 @@ This section provides a high-level overview of the CleverAgents implementation r
### Current Status Summary
As of Day 95 (2026-04-05), the project has **76 open PRs** and **~2800+ open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **536 open bugs** (continued agent-driven expansion from 389). M8 (v3.7.0) is now **52% complete** (332/634 issues closed — milestone grew from 438→634). M9 (v3.8.0) is **27% complete** (105/393 issues closed).
As of Day 95 (2026-04-05, update 3), the project has **91 open PRs** and **~3000+ open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **682 open bugs** (continued agent-driven expansion from 389). M8 (v3.7.0) is now **46% complete** (333/721 issues closed — milestone grew from 438→721). M9 (v3.8.0) is **26% complete** (105/400 issues closed).
**M1, M2 fully complete. M3 (v3.2.0)**: 70% complete (222/317), 95 open issues. **M4 (v3.3.0)**: 72% complete (101/141), 40 open issues. **M5 (v3.4.0)**: 75% complete (126/169), 43 open issues. **M6 (v3.5.0)**: 67% complete (175/263), 88 open issues. **M7 (v3.6.0)**: 55% complete (127/232), 105 open issues. **M8 (v3.7.0)**: 52% complete (332/634), 302 open issues. **M9 (v3.8.0)**: 27% complete (105/393), 288 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
**M1, M2 fully complete. M3 (v3.2.0)**: 69% complete (222/323), 101 open issues. **M4 (v3.3.0)**: 64% complete (101/159), 58 open issues. **M5 (v3.4.0)**: 71% complete (126/178), 52 open issues. **M6 (v3.5.0)**: 63% complete (174/277), 103 open issues. **M7 (v3.6.0)**: 50% complete (127/253), 126 open issues. **M8 (v3.7.0)**: 46% complete (333/721), 388 open issues. **M9 (v3.8.0)**: 26% complete (105/400), 295 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 536 Open Bugs — Session 3 Active (Day 95: Continued Agent Expansion)"
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 682 Open Bugs — Session 3 Active (Day 95 update 3: Continued Agent Expansion)"
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **76** (up from 64). Open bugs at **536** (continued agent-driven expansion from 389). M8 (v3.7.0) at 52% (332/634 closed — milestone grew from 438→634). M9 (v3.8.0) at 27% (105/393 closed). New session tracker issues: #2874 (progress report), #2875 (UAT pool supervisor), #2876 (spec updater). **Current priorities**: (1) **Triage 536 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 76 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push**52% complete, 302 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 70% (95 open), M4 at 72% (40 open), M5 at 75% (43 open).
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **91** (up from 64). Open bugs at **682** (continued agent-driven expansion from 389). M8 (v3.7.0) at 46% (333/721 closed — milestone grew from 438→721). M9 (v3.8.0) at 26% (105/400 closed). UAT pool supervisor (#2875) and spec updater (#2876) agents running. New fix/* and improvement/* branches active. **Current priorities**: (1) **Triage 682 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 91 open PRs** — TUI features, security fixes, spec compliance, domain model fixes. (3) **Continue M8 push**46% complete, 388 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 69% (101 open), M4 at 64% (58 open), M5 at 71% (52 open).
### Parallel Workstreams
@@ -2285,18 +2285,18 @@ Items without an assigned milestone represent backlog work to be addressed after
### Schedule Risk Summary
As of Day 95 (2026-04-05), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **76** (up from 64). Open bugs at **536** (continued agent-driven expansion from 389). M8 (v3.7.0) at **52% complete** (332/634 closed — milestone grew from 438→634). M9 (v3.8.0) at **27% complete** (105/393 closed). Critical path: 76 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 52% with 302 issues remaining; 536 open bugs need TDD counterparts and systematic triage.
As of Day 95 (2026-04-05, update 3), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **91** (up from 64). Open bugs at **682** (continued agent-driven expansion from 389). M8 (v3.7.0) at **46% complete** (333/721 closed — milestone grew from 438→721). M9 (v3.8.0) at **26% complete** (105/400 closed). Critical path: 91 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 46% with 388 issues remaining; 682 open bugs need TDD counterparts and systematic triage.
**Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry.
**Day 53 Session 3 actions**: (a) 16 parallel workers started. (b) 73+ PRs merged including ACMS UKO runtime (#1312), PermissionsScreen TUI (#1307), actor thought blocks (#1298), DatabaseResourceHandler (#1293), ACMS pipeline Phase 2 (#1287), DevcontainerHandler (#1286), async audit (#1279), serve CLI (#1272), LSP hover/definitions (#1240), domain event wiring (#1215), plan prompt command (#1212), M6 E2E tests (#1277), @tdd_expected_fail cleanup (#1229), persona export/import (#1338), first-run experience (#1391), session export/import (#1392). (c) UAT supervisor fleet (cycles 11-131) launched — discovered 100+ spec compliance bugs across CLI rich output, YAML config handling, and actor compiler. (d) Security bug-hunt PRs opened: #1412 (concurrency), #1409 (error handling), #1419 (hardcoded secrets). (e) Late-day: 4 more PRs merged (#1498, #1481, #1479, #1338), 18 new fix PRs opened (#1506-#1517) targeting UAT findings. (f) End-of-day CLI fix wave: 18 more PRs merged (#1574, #1573, #1570, #1569, #1567, #1566, #1565, #1563, #1562, #1558, #1556, #1554 and others) — open bugs reduced from **143 to 6**, open PRs at **74**.
**Critical path blockers** (ranked):
1. **76 open PRs need review** — continued agent-driven PR creation. All require review before merge.
2. **536 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued agent-driven expansion.
3. **M3-M7 backlog**95+40+43+88+105 open issues across M3-M7. All milestones regressed as agents added new issues.
4. **M8 (v3.7.0) at 52%** — 302 issues remaining (milestone grew from 438→634). Continued agent-driven expansion.
5. **M9 (v3.8.0) at 27%** — 288 issues remaining (milestone grew from 359→393). Significant expansion.
1. **91 open PRs need review** — continued agent-driven PR creation. All require review before merge.
2. **682 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued agent-driven expansion.
3. **M3-M7 backlog**101+58+52+103+126 open issues across M3-M7. All milestones regressed as agents added new issues.
4. **M8 (v3.7.0) at 46%** — 388 issues remaining (milestone grew from 438→721). Continued agent-driven expansion.
5. **M9 (v3.8.0) at 26%** — 295 issues remaining (milestone grew from 359→400). Significant expansion.
**Spec changes impact assessment (Day 31)**: ACP→A2A rename affects 10 source files, 13 classes, 640+ test references across 22 files. Zero A2A code exists — migration not started. All open PRs that touch ACP modules will need additional rebase work after #688/#689 merge. TUI spec adds ~1,500 lines with 18 ASCII mockups defining Textual-based UI — PR #667 was a placeholder that predates this spec. Server architecture adopts JSON-RPC 2.0 standard — PR #676 used custom protocol, now obsolete.
@@ -4949,13 +4949,16 @@ Deadline risk: HIGH
**Notes**
- Day 95 update. Open PRs increased from 64 → 76 (+12 new PRs). Open bugs increased from 389 → 536 (+147 agent-driven expansion).
- Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. New session tracker issues created: #2874 (autonomous build progress report), #2875 (UAT pool supervisor v3.7.0), #2876 (spec updater).
- Milestone totals continued to grow due to agent-driven issue creation: M3 (296→317), M4 (130→141), M5 (163→169), M6 (259→263), M7 (213→232), M8 (438→634), M9 (359→393).
- Milestone completions (Day 95): M3 70% (222/317), M4 72% (101/141), M5 75% (126/169), M6 67% (175/263), M7 55% (127/232), M8 52% (332/634), M9 27% (105/393).
- M8 (v3.7.0) made significant progress: 19% → 52% complete (81→332 closed issues), though milestone also expanded from 438→634 total issues.
- Day 95 update 3. Open PRs increased from 64 → 91 (+27 new PRs). Open bugs increased from 389 → 682 (+293 agent-driven expansion).
- Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. Session tracker issues: #2874 (autonomous build progress report), #2875 (UAT pool supervisor v3.7.0), #2876 (spec updater).
- Milestone totals continued to grow due to agent-driven issue creation: M3 (296→323), M4 (130→159), M5 (163→178), M6 (259→277), M7 (213→253), M8 (438→721), M9 (359→400).
- Milestone completions (Day 95 update 3): M3 69% (222/323), M4 64% (101/159), M5 71% (126/178), M6 63% (174/277), M7 50% (127/253), M8 46% (333/721), M9 26% (105/400).
- M8 (v3.7.0) progress: 19% → 46% complete (81→333 closed issues), though milestone also expanded from 438→721 total issues.
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
- UAT pool supervisor (#2875) and spec updater (#2876) agents are running autonomously, continuing to discover and file spec compliance issues.
- New fix/* branches active: fix/automation-profile-list-output-structure, fix/ci-optimize-e2e-tests-push, fix/concurrency-cost-tracker-record-usage, fix/domain-repository-protocols, fix/mcp-tool-result-data-type, fix/plan-resume-fields-persistence, fix/tool-lifecycle-domain-model-missing-execute-hook, fix/validation-attach-rejects-plain-tools.
- New improvement/* branches: improvement/agent-implementers-domain-model-verification, improvement/agent-product-builder-no-direct-merge.
- New spec/* branch: spec/update-v3.7.0-plan-errors-command.
#### Milestone forecast
@@ -4964,24 +4967,24 @@ Deadline risk: HIGH
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-04-25 | +58d | CRITICAL |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-04-28 | +57d | HIGH |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-04-28 | +53d | HIGH |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-05 | +56d | HIGH |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-05-20 | +53d | HIGH |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-06-15 | N/A | HIGH |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-05 | N/A | MEDIUM |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-01 | +64d | CRITICAL |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-08 | +67d | HIGH |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-05 | +60d | HIGH |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-12 | +63d | HIGH |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-05-30 | +63d | HIGH |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-06-25 | N/A | HIGH |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-15 | N/A | MEDIUM |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-04-28 | MEDIUM | 43 open issues in v3.4.0; continued agent-driven expansion |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-04-28 | HIGH | 40 open issues in v3.3.0; UAT spec compliance bugs ongoing |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-04-25 | HIGH | 95 open issues in v3.2.0; agent-driven expansion |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 536 open bugs; continued agent-driven bug creation |
| Track T (Testing) | Active | Ongoing | HIGH | 76 open PRs need review; UAT pool supervisor active (#2875) |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-05 | MEDIUM | 52 open issues in v3.4.0; continued agent-driven expansion |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-08 | HIGH | 58 open issues in v3.3.0; UAT spec compliance bugs ongoing |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-01 | HIGH | 101 open issues in v3.2.0; agent-driven expansion |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 682 open bugs; continued agent-driven bug creation |
| Track T (Testing) | Active | Ongoing | HIGH | 91 open PRs need review; UAT pool supervisor active (#2875) |
#### Developer forecast
@@ -4991,28 +4994,28 @@ Deadline risk: HIGH
| Luis | -21d behind | active | HIGH | M6 (v3.5.0) features; security hardening; audit session |
| Hamza | -21d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource |
| Aditya | -21d behind | active | HIGH | M5 features; TDD counterparts; domain model work |
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 536 open bugs triage |
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 682 open bugs triage |
| Rui | -21d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt |
| Mike/Brian | N/A | standby | LOW | N/A |
#### Task inventory
Milestone per developer as of Day 95 (2026-04-05).
Milestone per developer as of Day 95 update 3 (2026-04-05).
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 95 open | 222/317 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 40 open | 101/141 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 43 open | 126/169 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 88 open | 175/263 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 105 open | 127/232 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 302 open | 332/634 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 288 open | 105/393 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~961 open** | **1294/2245 closed** |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 101 open | 222/323 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 58 open | 101/159 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 52 open | 126/178 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 103 open | 174/277 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 126 open | 127/253 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 388 open | 333/721 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 295 open | 105/400 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1123 open** | **1288/2311 closed** |
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95. Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M8 grew from 438→634, M9 grew from 359→393 due to continued agent activity.
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 update 3. Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M8 grew from 438→721, M9 grew from 359→400 due to continued agent activity.
#### Story point allocation