docs(timeline): update schedule adherence Day 104 cycle-1 [AUTO-TIME-4] #8951

Closed
HAL9000 wants to merge 1 commit from docs/timeline-day104-cycle1-auto-time-4 into master
Owner

Summary

Day 104 (2026-04-14) timeline update — cycle 1. Worker: [AUTO-TIME-4].

Changes

  • Updated PlantUML gantt chart today is marker to 2026-04-14 (both epic-level and detailed charts)
  • Updated footer: 9 Milestones, ~225 open PRs, Session 4 active
  • Updated GANTT CHART UPDATE LOG comment block to Day 104 entry
  • Updated Risk Register with Day 104 completion rates and scope expansion data
  • Updated legend footer summary (9 Milestones, ~225 open PRs)
  • Appended ### 2026-04-14 (Day 104) schedule adherence entry with:
    • Milestone forecast (M1–M9 + v3.9.0)
    • Track forecast (A–T)
    • Developer forecast
    • Task inventory
    • Story point allocation

Milestone Status (Day 104)

Milestone Completion Open Total
v3.2.0 (M3) 24.7% 821 1090
v3.3.0 (M4) 40.7% 162 273
v3.4.0 (M5) 36.4% 243 382
v3.5.0 (M6) 16.7% 1059 1272
v3.6.0 (M7) 32.1% 321 473
v3.7.0 (M8) 41.8% 595 1023
v3.8.0 (M9) 26.2% 374 507
v3.9.0 12.5% 28 32

All milestones M3–M7 remain overdue. Scope expansion continues across all milestones since Day 100. New milestone v3.9.0 added (created 2026-04-10).

Previous worker: [AUTO-TIME-3] Day 103 Cycle 4 (PR #8791).


Automated by CleverAgents Bot
Supervisor: Implementation Pool | Agent: implementation-worker


Automated by CleverAgents Bot
Agent: pr-creator

## Summary Day 104 (2026-04-14) timeline update — cycle 1. Worker: [AUTO-TIME-4]. ### Changes - Updated PlantUML gantt chart `today is` marker to `2026-04-14` (both epic-level and detailed charts) - Updated footer: `9 Milestones`, `~225 open PRs`, Session 4 active - Updated GANTT CHART UPDATE LOG comment block to Day 104 entry - Updated Risk Register with Day 104 completion rates and scope expansion data - Updated legend footer summary (9 Milestones, ~225 open PRs) - Appended `### 2026-04-14 (Day 104)` schedule adherence entry with: - Milestone forecast (M1–M9 + v3.9.0) - Track forecast (A–T) - Developer forecast - Task inventory - Story point allocation ### Milestone Status (Day 104) | Milestone | Completion | Open | Total | |-----------|-----------|------|-------| | v3.2.0 (M3) | 24.7% | 821 | 1090 | | v3.3.0 (M4) | 40.7% | 162 | 273 | | v3.4.0 (M5) | 36.4% | 243 | 382 | | v3.5.0 (M6) | 16.7% | 1059 | 1272 | | v3.6.0 (M7) | 32.1% | 321 | 473 | | v3.7.0 (M8) | 41.8% | 595 | 1023 | | v3.8.0 (M9) | 26.2% | 374 | 507 | | v3.9.0 | 12.5% | 28 | 32 | All milestones M3–M7 remain overdue. Scope expansion continues across all milestones since Day 100. New milestone v3.9.0 added (created 2026-04-10). Previous worker: [AUTO-TIME-3] Day 103 Cycle 4 (PR #8791). --- **Automated by CleverAgents Bot** Supervisor: Implementation Pool | Agent: implementation-worker --- **Automated by CleverAgents Bot** Agent: pr-creator
docs(timeline): update schedule adherence Day 104 cycle-1 [AUTO-TIME-4]
All checks were successful
CI / quality (pull_request) Successful in 28s
CI / lint (pull_request) Successful in 39s
CI / build (pull_request) Successful in 22s
CI / typecheck (pull_request) Successful in 56s
CI / security (pull_request) Successful in 57s
CI / helm (pull_request) Successful in 23s
CI / push-validation (pull_request) Successful in 16s
CI / e2e_tests (pull_request) Successful in 5m7s
CI / integration_tests (pull_request) Successful in 6m46s
CI / unit_tests (pull_request) Successful in 7m43s
CI / docker (pull_request) Successful in 1m20s
CI / coverage (pull_request) Successful in 11m52s
CI / status-check (pull_request) Successful in 2s
c232ff1cc7
Day 104 (2026-04-14) timeline update — cycle 1.

- Update PlantUML gantt chart today marker to 2026-04-14 (both charts)
- Update footer: 9 Milestones, ~225 open PRs, Session 4 active
- Update GANTT CHART UPDATE LOG to Day 104 entry
- Update Risk Register with Day 104 completion rates and scope data
- Append Day 104 schedule adherence entry with full milestone/track/developer/task forecasts
- New milestone v3.9.0 (28 open / 4 closed, 12.5%) added to forecasts
- M3 24.7% (269/1090), M4 40.7% (111/273), M5 36.4% (139/382),
  M6 16.7% (213/1272), M7 32.1% (152/473), M8 41.8% (428/1023),
  M9 26.2% (133/507)
- All milestones M3-M7 remain overdue; scope expansion continues

Worker: [AUTO-TIME-4] | Previous: [AUTO-TIME-3] Day 103 Cycle 4 (PR #8791)
HAL9000 added this to the v3.7.0 milestone 2026-04-14 05:47:58 +00:00
Author
Owner

[GROOMED]

  • Added State/In Review, Priority/Medium, Type/Documentation, and MoSCoW/Should have labels for compliance
  • Assigned milestone v3.7.0 to align with documentation update scope

Automated by CleverAgents Bot
Supervisor: Grooming | Agent: grooming-pool-supervisor

[GROOMED] - Added State/In Review, Priority/Medium, Type/Documentation, and MoSCoW/Should have labels for compliance - Assigned milestone v3.7.0 to align with documentation update scope --- **Automated by CleverAgents Bot** Supervisor: Grooming | Agent: grooming-pool-supervisor ---
Author
Owner

Code Review Decision: REQUEST CHANGES

PR: #8951docs(timeline): update schedule adherence Day 104 cycle-1 [AUTO-TIME-4]
Type: Documentation-only (1 file changed: docs/timeline.md)
Primary Focus (PR 8951 % 5 = 1): Test quality and coverage — N/A for documentation-only PR

⚠️ Note: The reviewer bot (HAL9000) is the same account as the PR author. Forgejo does not allow self-review. This review is posted as a comment instead of a formal review.


What Looks Good

  1. Commit format: Follows conventional commits correctly — docs(timeline): update schedule adherence Day 104 cycle-1 [AUTO-TIME-4] with a detailed body.
  2. Milestone assigned: v3.7.0 (M8) —
  3. Type label: Type/Documentation
  4. Content correctness: The diff correctly updates:
    • PlantUML Gantt today is marker: 2026-04-102026-04-14 (both epic-level and detailed charts)
    • Footer: 7 Milestones9 Milestones, 225 open PRs~225 open PRs
    • GANTT CHART UPDATE LOG: Updated to Day 104 entry with accurate scope expansion data
    • Risk Register: Updated completion percentages and open issue counts
    • Legend footer: Updated milestone count and PR count
    • Appended full Day 104 schedule adherence section (milestone/track/developer/task/story point forecasts)
  5. Internal consistency: Milestone completion percentages and open issue counts are consistent across the GANTT log, Risk Register, and Day 104 schedule adherence section.
  6. No security/architectural issues: Documentation-only change.

Issues Found

Per CONTRIBUTING.md standards, commits should have an ISSUES CLOSED: #N footer. The commit message for this PR does not contain this footer. Additionally, the PR body does not include a closing keyword (Closes #N, Fixes #N, etc.) linking to a specific tracking issue.

Action required: Add ISSUES CLOSED: #<tracking-issue-number> to the commit message footer, or add a Closes #N reference in the PR body.

2. Minor inconsistency in detailed chart legend (not updated)

The detailed (per-issue) chart legend still reads:

271 Issues | 29 Epics | 9 Legendaries | 7 Milestones

The epic-level chart was correctly updated to 9 Milestones, but the detailed chart legend was not updated. This is inconsistent with the rest of the changes.

Action required: Update the detailed chart legend to reflect 9 Milestones (consistent with the epic-level chart and the new v3.9.0 milestone addition).

3. CHANGELOG.md and CONTRIBUTORS.md not updated

Per quality standards, CHANGELOG.md and CONTRIBUTORS.md should be updated with each PR. While this is a routine automated documentation update, the standards apply uniformly.

Action required: Add an entry to CHANGELOG.md noting the Day 104 timeline update, or confirm this type of automated tracking PR is exempt from this requirement.


Summary

Criterion Status
Commit format (conventional commits) Pass
Milestone assigned Pass
Type label present Pass
Content correctness Pass
Internal data consistency Pass
ISSUES CLOSED footer / closing keyword Missing
Detailed chart legend milestone count Inconsistent (7 vs 9)
CHANGELOG.md updated Not updated
Test coverage N/A (docs only)
Security/architecture N/A (docs only)

Verdict: REQUEST CHANGES — 3 issues found (1 process, 1 content inconsistency, 1 process). The content changes are accurate and well-structured, but the missing issue link, legend inconsistency, and CHANGELOG omission need to be addressed.


Automated by CleverAgents Bot
Supervisor: PR Review Pool | Agent: pr-review-pool-supervisor
Worker tag: [AUTO-REV-8951]

## Code Review Decision: REQUEST CHANGES **PR**: #8951 — `docs(timeline): update schedule adherence Day 104 cycle-1 [AUTO-TIME-4]` **Type**: Documentation-only (1 file changed: `docs/timeline.md`) **Primary Focus** (PR 8951 % 5 = 1): Test quality and coverage — N/A for documentation-only PR > ⚠️ **Note**: The reviewer bot (HAL9000) is the same account as the PR author. Forgejo does not allow self-review. This review is posted as a comment instead of a formal review. --- ### ✅ What Looks Good 1. **Commit format**: Follows conventional commits correctly — `docs(timeline): update schedule adherence Day 104 cycle-1 [AUTO-TIME-4]` with a detailed body. 2. **Milestone assigned**: `v3.7.0` (M8) — ✅ 3. **Type label**: `Type/Documentation` — ✅ 4. **Content correctness**: The diff correctly updates: - PlantUML Gantt `today is` marker: `2026-04-10` → `2026-04-14` (both epic-level and detailed charts) - Footer: `7 Milestones` → `9 Milestones`, `225 open PRs` → `~225 open PRs` - GANTT CHART UPDATE LOG: Updated to Day 104 entry with accurate scope expansion data - Risk Register: Updated completion percentages and open issue counts - Legend footer: Updated milestone count and PR count - Appended full Day 104 schedule adherence section (milestone/track/developer/task/story point forecasts) 5. **Internal consistency**: Milestone completion percentages and open issue counts are consistent across the GANTT log, Risk Register, and Day 104 schedule adherence section. 6. **No security/architectural issues**: Documentation-only change. --- ### ❌ Issues Found #### 1. Missing `ISSUES CLOSED:` footer in commit message (REQUIRED) Per CONTRIBUTING.md standards, commits should have an `ISSUES CLOSED: #N` footer. The commit message for this PR does not contain this footer. Additionally, the PR body does not include a closing keyword (`Closes #N`, `Fixes #N`, etc.) linking to a specific tracking issue. **Action required**: Add `ISSUES CLOSED: #<tracking-issue-number>` to the commit message footer, or add a `Closes #N` reference in the PR body. #### 2. Minor inconsistency in detailed chart legend (not updated) The detailed (per-issue) chart legend still reads: ``` 271 Issues | 29 Epics | 9 Legendaries | 7 Milestones ``` The epic-level chart was correctly updated to `9 Milestones`, but the detailed chart legend was not updated. This is inconsistent with the rest of the changes. **Action required**: Update the detailed chart legend to reflect `9 Milestones` (consistent with the epic-level chart and the new v3.9.0 milestone addition). #### 3. CHANGELOG.md and CONTRIBUTORS.md not updated Per quality standards, CHANGELOG.md and CONTRIBUTORS.md should be updated with each PR. While this is a routine automated documentation update, the standards apply uniformly. **Action required**: Add an entry to CHANGELOG.md noting the Day 104 timeline update, or confirm this type of automated tracking PR is exempt from this requirement. --- ### Summary | Criterion | Status | |-----------|--------| | Commit format (conventional commits) | ✅ Pass | | Milestone assigned | ✅ Pass | | Type label present | ✅ Pass | | Content correctness | ✅ Pass | | Internal data consistency | ✅ Pass | | ISSUES CLOSED footer / closing keyword | ❌ Missing | | Detailed chart legend milestone count | ❌ Inconsistent (7 vs 9) | | CHANGELOG.md updated | ❌ Not updated | | Test coverage | N/A (docs only) | | Security/architecture | N/A (docs only) | **Verdict**: REQUEST CHANGES — 3 issues found (1 process, 1 content inconsistency, 1 process). The content changes are accurate and well-structured, but the missing issue link, legend inconsistency, and CHANGELOG omission need to be addressed. --- **Automated by CleverAgents Bot** Supervisor: PR Review Pool | Agent: pr-review-pool-supervisor Worker tag: [AUTO-REV-8951]
HAL9001 left a comment

Code Review Decision: REQUEST CHANGES

PR: #8951docs(timeline): update schedule adherence Day 104 cycle-1 [AUTO-TIME-4]
Type: Documentation-only (1 file changed: docs/timeline.md)


Passing Criteria

Criterion Status Notes
CI checks Pass Run #18120 — status: success
Milestone assigned Pass v3.7.0 (M8)
Exactly one Type/ label Pass Type/Documentation
Conventional commit format Pass docs(timeline): ...
Content accuracy Pass Gantt dates, completion %, scope expansion data all correct
Coverage ≥ 97% N/A Documentation-only PR — no code changes
BDD testing N/A Documentation-only PR — no code changes

Issues Requiring Changes

Per CONTRIBUTING.md, every commit must include an ISSUES CLOSED: #N footer referencing the tracking issue this work closes. The commit message for this PR does not contain this footer.

Action required: Add ISSUES CLOSED: #<tracking-issue-number> to the commit message footer.

2. PR body missing closing keyword — no linked issue

The PR body does not include a closing keyword (Closes #N, Fixes #N, Resolves #N, etc.). Every PR must close a relevant issue.

Action required: Add Closes #<issue-number> to the PR body to link and close the relevant tracking issue.

3. CHANGELOG.md not updated

Only docs/timeline.md was modified. Per quality standards, CHANGELOG.md must be updated with each PR to record the change.

Action required: Add an entry to CHANGELOG.md for the Day 104 timeline update.

4. CONTRIBUTORS.md not updated

Similarly, CONTRIBUTORS.md must be updated per quality standards.

Action required: Update CONTRIBUTORS.md to reflect this contribution.

5. Detailed chart legend still shows 7 Milestones (content inconsistency)

The epic-level chart footer was correctly updated to 9 Milestones, but the detailed chart legend (line ~1957) still reads:

271 Issues | 29 Epics | 9 Legendaries | 7 Milestones

This is inconsistent with the rest of the document which now reflects 9 milestones (including the new v3.9.0).

Action required: Update the detailed chart legend to 9 Milestones.


Summary

Criterion Status
CI checks pass Pass
Milestone assigned Pass
Exactly one Type/ label Pass
Conventional commit format Pass
Content accuracy Pass
ISSUES CLOSED: #N footer in commit Missing
PR closes relevant issue (closing keyword) Missing
CHANGELOG.md updated Not updated
CONTRIBUTORS.md updated Not updated
Detailed chart legend milestone count Inconsistent (7 vs 9)

Verdict: REQUEST CHANGES — 5 issues found. The content changes are accurate and CI passes, but the missing issue link, commit footer, CHANGELOG/CONTRIBUTORS updates, and legend inconsistency must be addressed before this PR can be merged.


Automated by CleverAgents Bot
Supervisor: PR Review Pool | Agent: pr-reviewer
Worker: [AUTO-REV-8951]

## Code Review Decision: REQUEST CHANGES **PR**: #8951 — `docs(timeline): update schedule adherence Day 104 cycle-1 [AUTO-TIME-4]` **Type**: Documentation-only (1 file changed: `docs/timeline.md`) --- ### ✅ Passing Criteria | Criterion | Status | Notes | |-----------|--------|-------| | CI checks | ✅ Pass | Run #18120 — status: success | | Milestone assigned | ✅ Pass | `v3.7.0` (M8) | | Exactly one Type/ label | ✅ Pass | `Type/Documentation` | | Conventional commit format | ✅ Pass | `docs(timeline): ...` | | Content accuracy | ✅ Pass | Gantt dates, completion %, scope expansion data all correct | | Coverage ≥ 97% | N/A | Documentation-only PR — no code changes | | BDD testing | N/A | Documentation-only PR — no code changes | --- ### ❌ Issues Requiring Changes #### 1. Missing `ISSUES CLOSED: #N` footer in commit message (REQUIRED) Per CONTRIBUTING.md, every commit must include an `ISSUES CLOSED: #N` footer referencing the tracking issue this work closes. The commit message for this PR does not contain this footer. **Action required**: Add `ISSUES CLOSED: #<tracking-issue-number>` to the commit message footer. #### 2. PR body missing closing keyword — no linked issue The PR body does not include a closing keyword (`Closes #N`, `Fixes #N`, `Resolves #N`, etc.). Every PR must close a relevant issue. **Action required**: Add `Closes #<issue-number>` to the PR body to link and close the relevant tracking issue. #### 3. CHANGELOG.md not updated Only `docs/timeline.md` was modified. Per quality standards, `CHANGELOG.md` must be updated with each PR to record the change. **Action required**: Add an entry to `CHANGELOG.md` for the Day 104 timeline update. #### 4. CONTRIBUTORS.md not updated Similarly, `CONTRIBUTORS.md` must be updated per quality standards. **Action required**: Update `CONTRIBUTORS.md` to reflect this contribution. #### 5. Detailed chart legend still shows `7 Milestones` (content inconsistency) The epic-level chart footer was correctly updated to `9 Milestones`, but the detailed chart legend (line ~1957) still reads: ``` 271 Issues | 29 Epics | 9 Legendaries | 7 Milestones ``` This is inconsistent with the rest of the document which now reflects 9 milestones (including the new v3.9.0). **Action required**: Update the detailed chart legend to `9 Milestones`. --- ### Summary | Criterion | Status | |-----------|--------| | CI checks pass | ✅ Pass | | Milestone assigned | ✅ Pass | | Exactly one Type/ label | ✅ Pass | | Conventional commit format | ✅ Pass | | Content accuracy | ✅ Pass | | `ISSUES CLOSED: #N` footer in commit | ❌ Missing | | PR closes relevant issue (closing keyword) | ❌ Missing | | CHANGELOG.md updated | ❌ Not updated | | CONTRIBUTORS.md updated | ❌ Not updated | | Detailed chart legend milestone count | ❌ Inconsistent (7 vs 9) | **Verdict**: REQUEST CHANGES — 5 issues found. The content changes are accurate and CI passes, but the missing issue link, commit footer, CHANGELOG/CONTRIBUTORS updates, and legend inconsistency must be addressed before this PR can be merged. --- **Automated by CleverAgents Bot** Supervisor: PR Review Pool | Agent: pr-reviewer Worker: [AUTO-REV-8951]
Owner

Code Review Decision: REQUEST CHANGES

Formal review posted by HAL9001 (review ID: 5763) on PR #8951.

Issues Found (5)

  1. Missing ISSUES CLOSED: #N footer — Commit message does not contain the required ISSUES CLOSED: #<N> footer per CONTRIBUTING.md.
  2. No closing keyword in PR body — PR does not link to or close a relevant issue (Closes #N / Fixes #N missing).
  3. CHANGELOG.md not updated — Only docs/timeline.md was modified; CHANGELOG.md must be updated per quality standards.
  4. CONTRIBUTORS.md not updated — CONTRIBUTORS.md must be updated per quality standards.
  5. Detailed chart legend inconsistency — Legend still reads 7 Milestones while the rest of the document was updated to 9 Milestones.

Passing Criteria

  • CI checks pass (run #18120, status: success)
  • Milestone assigned (v3.7.0)
  • Exactly one Type/ label (Type/Documentation)
  • Conventional commit format
  • Content accuracy (Gantt dates, completion %, scope expansion data)
  • N/A: Coverage ≥ 97%, BDD testing (documentation-only PR)

Verdict: REQUEST CHANGES — Please address all 5 issues above before requesting re-review.


Automated by CleverAgents Bot
Supervisor: PR Review Pool | Agent: pr-reviewer
Worker: [AUTO-REV-8951]

**Code Review Decision: REQUEST CHANGES** Formal review posted by HAL9001 (review ID: 5763) on PR #8951. ### Issues Found (5) 1. ❌ **Missing `ISSUES CLOSED: #N` footer** — Commit message does not contain the required `ISSUES CLOSED: #<N>` footer per CONTRIBUTING.md. 2. ❌ **No closing keyword in PR body** — PR does not link to or close a relevant issue (`Closes #N` / `Fixes #N` missing). 3. ❌ **CHANGELOG.md not updated** — Only `docs/timeline.md` was modified; CHANGELOG.md must be updated per quality standards. 4. ❌ **CONTRIBUTORS.md not updated** — CONTRIBUTORS.md must be updated per quality standards. 5. ❌ **Detailed chart legend inconsistency** — Legend still reads `7 Milestones` while the rest of the document was updated to `9 Milestones`. ### Passing Criteria - ✅ CI checks pass (run #18120, status: success) - ✅ Milestone assigned (`v3.7.0`) - ✅ Exactly one Type/ label (`Type/Documentation`) - ✅ Conventional commit format - ✅ Content accuracy (Gantt dates, completion %, scope expansion data) - N/A: Coverage ≥ 97%, BDD testing (documentation-only PR) **Verdict**: REQUEST CHANGES — Please address all 5 issues above before requesting re-review. --- **Automated by CleverAgents Bot** Supervisor: PR Review Pool | Agent: pr-reviewer Worker: [AUTO-REV-8951]
freemo closed this pull request 2026-04-15 15:46:25 +00:00
All checks were successful
CI / quality (pull_request) Successful in 28s
Required
Details
CI / lint (pull_request) Successful in 39s
Required
Details
CI / build (pull_request) Successful in 22s
Required
Details
CI / typecheck (pull_request) Successful in 56s
Required
Details
CI / security (pull_request) Successful in 57s
Required
Details
CI / helm (pull_request) Successful in 23s
CI / push-validation (pull_request) Successful in 16s
CI / e2e_tests (pull_request) Successful in 5m7s
CI / integration_tests (pull_request) Successful in 6m46s
Required
Details
CI / unit_tests (pull_request) Successful in 7m43s
Required
Details
CI / docker (pull_request) Successful in 1m20s
Required
Details
CI / coverage (pull_request) Successful in 11m52s
Required
Details
CI / status-check (pull_request) Successful in 2s

Pull request closed

Sign in to join this conversation.
No reviewers
No milestone
No project
No assignees
2 participants
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core!8951
No description provided.