@@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
|
||||
@startgantt
|
||||
|
||||
title CleverAgents Core — Epic-Level Project Schedule
|
||||
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 536 open bugs | 76 open PRs | Session 3 active
|
||||
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 691 open bugs | 93 open PRs | Session 3 active
|
||||
|
||||
Project starts 2026-02-03
|
||||
saturday are closed
|
||||
@@ -22,12 +22,12 @@ today is colored in #FF6666
|
||||
|
||||
' ================================================================
|
||||
' GANTT CHART UPDATE LOG (Day 95 — 2026-04-05)
|
||||
' Changes: Day 95 update. Open PRs: 64→76 (+12). Open bugs: 389→536 (+147 agent-driven).
|
||||
' Changes: Day 95 update (refresh). Open PRs: 76→93 (+17). Open bugs: 536→691 (+155 agent-driven).
|
||||
' Open issues: continued agent-driven expansion across all milestones.
|
||||
' M3 70% (222/317), M4 72% (101/141), M5 75% (126/169), M6 67% (175/263),
|
||||
' M7 55% (127/232), M8 52% (332/634), M9 27% (105/393).
|
||||
' M3 67% (224/334), M4 63% (103/163), M5 70% (126/179), M6 60% (176/294),
|
||||
' M7 47% (127/268), M8 45% (336/743), M9 26% (108/408).
|
||||
' Session 3 active. UAT pool supervisor and spec updater agents running.
|
||||
' New session tracker issues: #2874 (progress report), #2875 (UAT pool), #2876 (spec updater).
|
||||
' Milestone totals grew: M3 317→334, M4 141→163, M5 169→179, M6 263→294, M7 232→268, M8 634→743, M9 393→408.
|
||||
' ================================================================
|
||||
|
||||
<style>
|
||||
@@ -229,7 +229,7 @@ ganttDiagram {
|
||||
|
||||
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
|
||||
[M3] starts at [M2]'s end
|
||||
[M3] is 70% completed
|
||||
[M3] is 67% completed
|
||||
[M3] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
|
||||
@@ -250,13 +250,13 @@ ganttDiagram {
|
||||
|
||||
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
|
||||
[M4] starts at [M3]'s end
|
||||
[M4] is 72% completed
|
||||
[M4] is 63% completed
|
||||
[M4] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
|
||||
[Security + Safety Hardening (#362)] as [SEC] on {Luis} requires 3 days
|
||||
[SEC] starts 2026-03-02
|
||||
[SEC] is 78% completed
|
||||
[SEC] is 70% completed
|
||||
[SEC] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Provider Fixes + Runtime (#363)] as [PROV] on {Luis} requires 2 days
|
||||
@@ -281,12 +281,12 @@ ganttDiagram {
|
||||
|
||||
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
|
||||
[M5] starts at [M4]'s end
|
||||
[M5] is 75% completed
|
||||
[M5] is 70% completed
|
||||
[M5] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
|
||||
[M6] starts at [M5]'s end
|
||||
[M6] is 67% completed
|
||||
[M6] is 60% completed
|
||||
[M6] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Subplans + Parallelism (#368)] as [SUBP] on {Luis} {Brent} requires 2 days
|
||||
@@ -296,7 +296,7 @@ ganttDiagram {
|
||||
|
||||
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
|
||||
[LARGE] starts 2026-03-17
|
||||
[LARGE] is 55% completed
|
||||
[LARGE] is 47% completed
|
||||
[LARGE] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
|
||||
@@ -398,15 +398,15 @@ legend right
|
||||
| v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs |
|
||||
| v3.6.0 | Mar 27 | 2 | 100 | Deferred work |
|
||||
----
|
||||
**Risk Register (Day 95 — 2026-04-05)**
|
||||
**Risk Register (Day 95 refresh — 2026-04-05)**
|
||||
|= Epic |= Completion |= Risk |= Blocker |
|
||||
| M3 (#357) | 70% | **CRITICAL** | 95 open issues in v3.2.0 |
|
||||
| M4 (#358) | 72% | **HIGH** | 40 open issues in v3.3.0 |
|
||||
| M5 (#359) | 75% | **HIGH** | 43 open issues in v3.4.0 |
|
||||
| M6 (#360) | 67% | **HIGH** | 88 open issues in v3.5.0 |
|
||||
| M7 (#361) | 55% | **HIGH** | 105 open issues in v3.6.0 |
|
||||
| M8 (#362) | 52% | **HIGH** | 302 open issues in v3.7.0 (agent expansion) |
|
||||
| SEC (#363) | 27% | **HIGH** | 288 open issues in v3.8.0 (agent expansion) |
|
||||
| M3 (#357) | 67% | **CRITICAL** | 110 open issues in v3.2.0 (grew 317→334) |
|
||||
| M4 (#358) | 63% | **CRITICAL** | 60 open issues in v3.3.0 (grew 141→163) |
|
||||
| M5 (#359) | 70% | **HIGH** | 53 open issues in v3.4.0 (grew 169→179) |
|
||||
| M6 (#360) | 60% | **HIGH** | 118 open issues in v3.5.0 (grew 263→294) |
|
||||
| M7 (#361) | 47% | **HIGH** | 141 open issues in v3.6.0 (grew 232→268) |
|
||||
| M8 (#362) | 45% | **HIGH** | 407 open issues in v3.7.0 (grew 634→743) |
|
||||
| SEC (#363) | 26% | **HIGH** | 300 open issues in v3.8.0 (grew 393→408) |
|
||||
----
|
||||
**Color Key**
|
||||
|= Color |= Meaning |
|
||||
@@ -418,7 +418,7 @@ legend right
|
||||
----
|
||||
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
|
||||
~1649 total story points | ~3300 estimated hours
|
||||
**536 open bugs — 76 open PRs — Session 3 active (16 workers, ~71 agents)**
|
||||
**691 open bugs — 93 open PRs — Session 3 active (16 workers, ~71 agents)**
|
||||
end legend
|
||||
|
||||
@endgantt
|
||||
@@ -1963,13 +1963,13 @@ This section provides a high-level overview of the CleverAgents implementation r
|
||||
|
||||
### Current Status Summary
|
||||
|
||||
As of Day 95 (2026-04-05), the project has **76 open PRs** and **~2800+ open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **536 open bugs** (continued agent-driven expansion from 389). M8 (v3.7.0) is now **52% complete** (332/634 issues closed — milestone grew from 438→634). M9 (v3.8.0) is **27% complete** (105/393 issues closed).
|
||||
As of Day 95 (2026-04-05), the project has **93 open PRs** and **~1332 open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **691 open bugs** (continued agent-driven expansion from 536). M8 (v3.7.0) is now **45% complete** (336/743 issues closed — milestone grew from 634→743). M9 (v3.8.0) is **26% complete** (108/408 issues closed).
|
||||
|
||||
**M1, M2 fully complete. M3 (v3.2.0)**: 70% complete (222/317), 95 open issues. **M4 (v3.3.0)**: 72% complete (101/141), 40 open issues. **M5 (v3.4.0)**: 75% complete (126/169), 43 open issues. **M6 (v3.5.0)**: 67% complete (175/263), 88 open issues. **M7 (v3.6.0)**: 55% complete (127/232), 105 open issues. **M8 (v3.7.0)**: 52% complete (332/634), 302 open issues. **M9 (v3.8.0)**: 27% complete (105/393), 288 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
|
||||
**M1, M2 fully complete. M3 (v3.2.0)**: 67% complete (224/334), 110 open issues. **M4 (v3.3.0)**: 63% complete (103/163), 60 open issues. **M5 (v3.4.0)**: 70% complete (126/179), 53 open issues. **M6 (v3.5.0)**: 60% complete (176/294), 118 open issues. **M7 (v3.6.0)**: 47% complete (127/268), 141 open issues. **M8 (v3.7.0)**: 45% complete (336/743), 407 open issues. **M9 (v3.8.0)**: 26% complete (108/408), 300 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
|
||||
|
||||
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 536 Open Bugs — Session 3 Active (Day 95: Continued Agent Expansion)"
|
||||
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 691 Open Bugs — Session 3 Active (Day 95 refresh: Continued Agent Expansion)"
|
||||
|
||||
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **76** (up from 64). Open bugs at **536** (continued agent-driven expansion from 389). M8 (v3.7.0) at 52% (332/634 closed — milestone grew from 438→634). M9 (v3.8.0) at 27% (105/393 closed). New session tracker issues: #2874 (progress report), #2875 (UAT pool supervisor), #2876 (spec updater). **Current priorities**: (1) **Triage 536 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 76 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push** — 52% complete, 302 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 70% (95 open), M4 at 72% (40 open), M5 at 75% (43 open).
|
||||
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **93** (up from 76). Open bugs at **691** (continued agent-driven expansion from 536). Milestone totals grew: M3 317→334, M4 141→163, M5 169→179, M6 263→294, M7 232→268, M8 634→743, M9 393→408. M8 (v3.7.0) at 45% (336/743 closed). M9 (v3.8.0) at 26% (108/408 closed). Session tracker issues: #2874 (progress report), #2875 (UAT pool supervisor), #2876 (spec updater). **Current priorities**: (1) **Triage 691 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 93 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push** — 45% complete, 407 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 67% (110 open), M4 at 63% (60 open), M5 at 70% (53 open).
|
||||
|
||||
### Parallel Workstreams
|
||||
|
||||
@@ -2075,7 +2075,7 @@ The following major areas are fully or substantially implemented:
|
||||
|
||||
### What Remains To Be Done
|
||||
|
||||
The majority of the specification's domain models, services, CLI commands, and infrastructure modules are now implemented. M1 and M2 are fully complete. M3-M7 are the active development front with all milestones overdue. **Session 3 (Day 53, 2026-04-02) is active with 16 parallel workers and ~71 total agents**. 73+ PRs merged since session start. M8 (v3.7.0) is now **36% complete** (55/152 closed). M9 (v3.8.0) is **40% complete** (64/160 closed). Open bugs at **35** (up from 6 — UAT/bug-hunt wave). 79 open PRs need review and merge. The following areas still require completion:
|
||||
The majority of the specification's domain models, services, CLI commands, and infrastructure modules are now implemented. M1 and M2 are fully complete. M3-M7 are the active development front with all milestones overdue. **Session 3 (Day 53, 2026-04-02) is active with 16 parallel workers and ~71 total agents**. 73+ PRs merged since session start. M8 (v3.7.0) is now **45% complete** (336/743 closed — milestone grew from 634→743). M9 (v3.8.0) is **26% complete** (108/408 closed). Open bugs at **691** (continued agent-driven expansion). 93 open PRs need review and merge. The following areas still require completion:
|
||||
|
||||
- **Lingering `@tdd_expected_fail` tag cleanup (3 files)**:
|
||||
- \#647 (Container.resolve crash, M3) — TDD PR #670 still awaiting merge (Aditya). 5+ days in review.
|
||||
@@ -2186,48 +2186,50 @@ Key constraints:
|
||||
|
||||
**Goal**: Decisions are recorded during Strategize and Execute phases and persisted to the database. Users can view the decision tree (`plan tree`), inspect individual decisions (`plan explain`), manage invariants (`invariant add/list/remove`), and correct decisions (`plan correct --mode revert|append`) with selective subtree recomputation.
|
||||
|
||||
**Current status**: **36 open / 236 total (85%).** 200 issues closed. Bugs largely resolved via CLI fix wave. All remaining bugs at Priority/Critical per policy. Open PRs targeting v3.2.0 need review and merge.
|
||||
**Current status**: **110 open / 334 total (67%).** 224 issues closed. Milestone grew from 317→334 due to agent-driven issue creation. All remaining bugs at Priority/Critical per policy. Open PRs targeting v3.2.0 need review and merge.
|
||||
|
||||
**Key remaining work**:
|
||||
|
||||
- **4 open bugs**: #647 (Container.resolve — TDD PR #1053 near merge), #620/#980 (skill add regression — TDD PR #1110 approved, fix PR #1120 reviewed), #797 (actor list DB — TDD #841 open, Priority escalated to Critical), #783 (init --yes — **STALLED**, TDD merged but bugfix not started, escalated to @aditya).
|
||||
- **TDD pipeline progress**: PR #1053 near merge (1 outstanding review). PR #1110 approved. Bug #783 stalled — escalation posted Day 43.
|
||||
- **M3 ETA: ~2026-04-10** (43 days past original target). 35 open issues remaining. Active PRs: #1185 (test fix), #1155 (TDD quality gate).
|
||||
- **110 open issues** — milestone expanded significantly from agent-driven issue creation.
|
||||
- **4 known open bugs**: #647 (Container.resolve — TDD PR #1053 near merge), #620/#980 (skill add regression — TDD PR #1110 approved, fix PR #1120 reviewed), #797 (actor list DB — TDD #841 open, Priority escalated to Critical), #783 (init --yes — **STALLED**, TDD merged but bugfix not started, escalated to @aditya).
|
||||
- **M3 ETA: ~2026-05-01** (64 days past original target). 110 open issues remaining. Active PRs: #1185 (test fix), #1155 (TDD quality gate).
|
||||
|
||||
#### Milestone 4: Corrections + Subplans + Checkpoints (Target: Mar 2, ETA: ~Mar 22)
|
||||
|
||||
**Goal**: Plans can spawn child plans (subplans) during execution. Subplans execute in parallel with configurable concurrency limits. Results are merged back using three-way merge strategies. Correction engine supports revert and append modes. Checkpointing enables rollback to previous plan states.
|
||||
|
||||
**Current status**: **25 open / 124 total (80%).** 99 issues closed. Active PRs targeting v3.3.0 need review and merge. Bug fixes largely resolved via CLI fix wave.
|
||||
**Current status**: **60 open / 163 total (63%).** 103 issues closed. Milestone grew from 141→163 due to agent-driven issue creation. Active PRs targeting v3.3.0 need review and merge.
|
||||
|
||||
**Key remaining work**:
|
||||
|
||||
- **60 open issues** — milestone expanded significantly from 141→163 due to agent-driven issue creation.
|
||||
- **Bug #822 (checkpoint rollback)** — TDD #839 CLOSED. **Fix NOT STARTED.** Jeff must create `bugfix/m4-checkpoint-real-rollback` immediately.
|
||||
- **Bug #932 (plan apply --yes)** — TDD PR #958 needs rebase and merge. Fix assigned to Rui.
|
||||
- **3 new bugs without TDD**: #1023 (E2E init), #1024 (SQLite URL), #1025 (plan correct auto-resolve). TDD counterparts must be created.
|
||||
- Secret masking (#573, Luis — PR #656, merge conflict, no reviews)
|
||||
- M4 ETA: ~2026-03-22 (20 days past original target).
|
||||
- M4 ETA: ~2026-05-10 (69 days past original target).
|
||||
|
||||
#### Milestone 5: ACMS v1 + Context Scaling (Target: Mar 6, ETA: ~Mar 22)
|
||||
|
||||
**Goal**: The Advanced Context Management System v1 is operational. Projects with 10,000+ files can be indexed and queried. The context assembly pipeline produces scoped, budget-constrained context views for actors. Hot/warm/cold storage tiers manage context lifecycle.
|
||||
|
||||
**Current status**: **16 open / 142 total (89%).** 126 issues closed. Active PRs targeting v3.4.0 need review and merge. Bug fixes largely resolved via CLI fix wave.
|
||||
**Current status**: **53 open / 179 total (70%).** 126 issues closed. Milestone grew from 169→179 due to agent-driven issue creation. Active PRs targeting v3.4.0 need review and merge.
|
||||
|
||||
**Key remaining work**:
|
||||
|
||||
- **53 open issues** — milestone expanded from 169→179 due to agent-driven issue creation.
|
||||
- **Bug #821 (ACMS tier service)** — TDD #840 (Brent) stalled 3+ days. Must be unblocked.
|
||||
- **Bug #1022 (InvariantService memory-only)** — **NO TDD. Needs creation.**
|
||||
- **Bug #1028 (ACMS pipeline wiring)** — TDD #1029 created (Rui). Not started.
|
||||
- ACMS context features (6 issues #846-#851, assigned to Aditya).
|
||||
- M5 E2E validation (PR #811 in review, 15 comments).
|
||||
- M5 ETA: ~2026-03-22 (16 days past original target).
|
||||
- M5 ETA: ~2026-05-05 (60 days past original target).
|
||||
|
||||
#### Milestone 6: Autonomy Hardening (Target: Mar 10, ETA: ~Mar 14)
|
||||
|
||||
**Goal**: The system can autonomously execute a large-scale task (e.g., porting a substantial codebase) using hierarchical plan decomposition with 4+ levels of subplans, decision correction with selective subtree recomputation, parallel execution scaling to 10+ concurrent subplans, and validation-gated apply. **Note**: Server stubs previously in this milestone have been moved to M9 (v3.8.0) following the ACP→A2A protocol adoption and server architecture redesign (ADR-047/048). TUI features moved to M8 (v3.7.0).
|
||||
|
||||
**Current status**: **46 open / 214 total (79%).** 168 issues closed. Active PRs targeting v3.5.0 need review and merge. Bug fixes largely resolved via CLI fix wave. M6 advanced from 77% to 79% with end-of-day merges.
|
||||
**Current status**: **118 open / 294 total (60%).** 176 issues closed. Milestone grew from 263→294 due to agent-driven issue creation. Active PRs targeting v3.5.0 need review and merge.
|
||||
|
||||
**Key remaining work**:
|
||||
|
||||
@@ -2237,7 +2239,7 @@ Key constraints:
|
||||
- **Event system (Luis)**: Fix-then-revalidate (#714, PR #711), event bus refinements.
|
||||
- **Output rendering (#550, Rui)**: PR #812 in round 3+ review (10 comments, security concerns, incomplete fixes pattern).
|
||||
- **CLI polish (#210, Brent)**, diagnostic dashboard (#580, Brent).
|
||||
- M6 ETA: ~2026-03-25 (15 days past original target).
|
||||
- M6 ETA: ~2026-05-20 (71 days past original target).
|
||||
|
||||
#### Milestone 7: Advanced Concepts & Deferred Features (v3.6.0, Target: Mar 28)
|
||||
|
||||
@@ -2263,7 +2265,7 @@ Key constraints:
|
||||
|
||||
**Issues**: #694 (MainScreen, Jeff), #695 (Persona system, Aditya), #696 (TuiMaterializer, Jeff).
|
||||
|
||||
**Current status**: **61% complete (36/59 issues closed), 23 open issues.** Active Session 3 push. Merged today: PermissionsScreen (#1307), actor thought blocks (#1298), session-driven editing (#1306), shell danger detection (#1284), session export/import (#1269, #1392), persona export/import (#1338), first-run experience (#1391), ACMS graph backend (#1282), Helm CI (#1267), E2E porting task (#1296), LLM actors wired (#1304), Prometheus metrics (#1308). Open PRs: MainScreen (#1302), TuiMaterializer A2A (#1294), Permission Question Widget (#1268), PostgreSQL backend (#1118), AWS CloudResource (#1280). Security bug-hunt: #1412, #1409, #1419.
|
||||
**Current status**: **45% complete (336/743 issues closed), 407 open issues.** Active Session 3 push. Milestone grew from 634→743 due to continued agent-driven issue creation. Open PRs: MainScreen (#1302), TuiMaterializer A2A (#1294), Permission Question Widget (#1268), PostgreSQL backend (#1118), AWS CloudResource (#1280). Security bug-hunt: #1412, #1409, #1419. 93 open PRs across all milestones need review and merge.
|
||||
|
||||
**No deadline assigned.** Active development underway as part of Session 3 v3.7.0 push.
|
||||
|
||||
@@ -2285,18 +2287,18 @@ Items without an assigned milestone represent backlog work to be addressed after
|
||||
|
||||
### Schedule Risk Summary
|
||||
|
||||
As of Day 95 (2026-04-05), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **76** (up from 64). Open bugs at **536** (continued agent-driven expansion from 389). M8 (v3.7.0) at **52% complete** (332/634 closed — milestone grew from 438→634). M9 (v3.8.0) at **27% complete** (105/393 closed). Critical path: 76 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 52% with 302 issues remaining; 536 open bugs need TDD counterparts and systematic triage.
|
||||
As of Day 95 (2026-04-05), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **93** (up from 76). Open bugs at **691** (continued agent-driven expansion from 536). M8 (v3.7.0) at **45% complete** (336/743 closed — milestone grew from 634→743). M9 (v3.8.0) at **26% complete** (108/408 closed). Critical path: 93 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 45% with 407 issues remaining; 691 open bugs need TDD counterparts and systematic triage.
|
||||
|
||||
**Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry.
|
||||
|
||||
**Day 53 Session 3 actions**: (a) 16 parallel workers started. (b) 73+ PRs merged including ACMS UKO runtime (#1312), PermissionsScreen TUI (#1307), actor thought blocks (#1298), DatabaseResourceHandler (#1293), ACMS pipeline Phase 2 (#1287), DevcontainerHandler (#1286), async audit (#1279), serve CLI (#1272), LSP hover/definitions (#1240), domain event wiring (#1215), plan prompt command (#1212), M6 E2E tests (#1277), @tdd_expected_fail cleanup (#1229), persona export/import (#1338), first-run experience (#1391), session export/import (#1392). (c) UAT supervisor fleet (cycles 11-131) launched — discovered 100+ spec compliance bugs across CLI rich output, YAML config handling, and actor compiler. (d) Security bug-hunt PRs opened: #1412 (concurrency), #1409 (error handling), #1419 (hardcoded secrets). (e) Late-day: 4 more PRs merged (#1498, #1481, #1479, #1338), 18 new fix PRs opened (#1506-#1517) targeting UAT findings. (f) End-of-day CLI fix wave: 18 more PRs merged (#1574, #1573, #1570, #1569, #1567, #1566, #1565, #1563, #1562, #1558, #1556, #1554 and others) — open bugs reduced from **143 to 6**, open PRs at **74**.
|
||||
|
||||
**Critical path blockers** (ranked):
|
||||
1. **76 open PRs need review** — continued agent-driven PR creation. All require review before merge.
|
||||
2. **536 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued agent-driven expansion.
|
||||
3. **M3-M7 backlog** — 95+40+43+88+105 open issues across M3-M7. All milestones regressed as agents added new issues.
|
||||
4. **M8 (v3.7.0) at 52%** — 302 issues remaining (milestone grew from 438→634). Continued agent-driven expansion.
|
||||
5. **M9 (v3.8.0) at 27%** — 288 issues remaining (milestone grew from 359→393). Significant expansion.
|
||||
1. **93 open PRs need review** — continued agent-driven PR creation. All require review before merge.
|
||||
2. **691 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued agent-driven expansion.
|
||||
3. **M3-M7 backlog** — 110+60+53+118+141 open issues across M3-M7. All milestones regressed as agents added new issues.
|
||||
4. **M8 (v3.7.0) at 45%** — 407 issues remaining (milestone grew from 634→743). Continued agent-driven expansion.
|
||||
5. **M9 (v3.8.0) at 26%** — 300 issues remaining (milestone grew from 393→408). Significant expansion.
|
||||
|
||||
**Spec changes impact assessment (Day 31)**: ACP→A2A rename affects 10 source files, 13 classes, 640+ test references across 22 files. Zero A2A code exists — migration not started. All open PRs that touch ACP modules will need additional rebase work after #688/#689 merge. TUI spec adds ~1,500 lines with 18 ASCII mockups defining Textual-based UI — PR #667 was a placeholder that predates this spec. Server architecture adopts JSON-RPC 2.0 standard — PR #676 used custom protocol, now obsolete.
|
||||
|
||||
@@ -4949,11 +4951,11 @@ Deadline risk: HIGH
|
||||
|
||||
**Notes**
|
||||
|
||||
- Day 95 update. Open PRs increased from 64 → 76 (+12 new PRs). Open bugs increased from 389 → 536 (+147 agent-driven expansion).
|
||||
- Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. New session tracker issues created: #2874 (autonomous build progress report), #2875 (UAT pool supervisor v3.7.0), #2876 (spec updater).
|
||||
- Milestone totals continued to grow due to agent-driven issue creation: M3 (296→317), M4 (130→141), M5 (163→169), M6 (259→263), M7 (213→232), M8 (438→634), M9 (359→393).
|
||||
- Milestone completions (Day 95): M3 70% (222/317), M4 72% (101/141), M5 75% (126/169), M6 67% (175/263), M7 55% (127/232), M8 52% (332/634), M9 27% (105/393).
|
||||
- M8 (v3.7.0) made significant progress: 19% → 52% complete (81→332 closed issues), though milestone also expanded from 438→634 total issues.
|
||||
- Day 95 update (refreshed from Forgejo API). Open PRs increased from 76 → 93 (+17 new PRs). Open bugs increased from 536 → 691 (+155 agent-driven expansion).
|
||||
- Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. Session tracker issues: #2874 (autonomous build progress report), #2875 (UAT pool supervisor v3.7.0), #2876 (spec updater).
|
||||
- Milestone totals continued to grow due to agent-driven issue creation: M3 (317→334), M4 (141→163), M5 (169→179), M6 (263→294), M7 (232→268), M8 (634→743), M9 (393→408).
|
||||
- Milestone completions (Day 95 refresh): M3 67% (224/334), M4 63% (103/163), M5 70% (126/179), M6 60% (176/294), M7 47% (127/268), M8 45% (336/743), M9 26% (108/408).
|
||||
- Completion percentages declined across all active milestones as agent-driven issue creation outpaced closures. M4 dropped from 72%→63%, M6 from 67%→60%, M7 from 55%→47%, M8 from 52%→45%.
|
||||
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
|
||||
- UAT pool supervisor (#2875) and spec updater (#2876) agents are running autonomously, continuing to discover and file spec compliance issues.
|
||||
|
||||
@@ -4964,24 +4966,24 @@ Deadline risk: HIGH
|
||||
|-----------|---------------|-------|------|
|
||||
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
|
||||
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-04-25 | +58d | CRITICAL |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-04-28 | +57d | HIGH |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-04-28 | +53d | HIGH |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-05 | +56d | HIGH |
|
||||
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-05-20 | +53d | HIGH |
|
||||
| M8 (v3.7.0) | (no deadline) -> ETA 2026-06-15 | N/A | HIGH |
|
||||
| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-05 | N/A | MEDIUM |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-01 | +64d | CRITICAL |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-10 | +69d | CRITICAL |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-05 | +60d | HIGH |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-20 | +71d | HIGH |
|
||||
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-10 | +74d | HIGH |
|
||||
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-01 | N/A | HIGH |
|
||||
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-01 | N/A | MEDIUM |
|
||||
|
||||
#### Track forecast
|
||||
|
||||
| Track | Status | ETA | Risk | Blocking |
|
||||
|-------|--------|-----|------|----------|
|
||||
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
|
||||
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-04-28 | MEDIUM | 43 open issues in v3.4.0; continued agent-driven expansion |
|
||||
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-04-28 | HIGH | 40 open issues in v3.3.0; UAT spec compliance bugs ongoing |
|
||||
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-04-25 | HIGH | 95 open issues in v3.2.0; agent-driven expansion |
|
||||
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 536 open bugs; continued agent-driven bug creation |
|
||||
| Track T (Testing) | Active | Ongoing | HIGH | 76 open PRs need review; UAT pool supervisor active (#2875) |
|
||||
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-05 | MEDIUM | 53 open issues in v3.4.0; continued agent-driven expansion |
|
||||
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-10 | CRITICAL | 60 open issues in v3.3.0; UAT spec compliance bugs ongoing |
|
||||
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-01 | CRITICAL | 110 open issues in v3.2.0; agent-driven expansion |
|
||||
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 691 open bugs; continued agent-driven bug creation |
|
||||
| Track T (Testing) | Active | Ongoing | HIGH | 93 open PRs need review; UAT pool supervisor active (#2875) |
|
||||
|
||||
#### Developer forecast
|
||||
|
||||
@@ -4991,28 +4993,28 @@ Deadline risk: HIGH
|
||||
| Luis | -21d behind | active | HIGH | M6 (v3.5.0) features; security hardening; audit session |
|
||||
| Hamza | -21d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource |
|
||||
| Aditya | -21d behind | active | HIGH | M5 features; TDD counterparts; domain model work |
|
||||
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 536 open bugs triage |
|
||||
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 691 open bugs triage |
|
||||
| Rui | -21d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt |
|
||||
| Mike/Brian | N/A | standby | LOW | N/A |
|
||||
|
||||
#### Task inventory
|
||||
|
||||
Milestone per developer as of Day 95 (2026-04-05).
|
||||
Milestone per developer as of Day 95 refresh (2026-04-05).
|
||||
|
||||
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
|
||||
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 95 open | 222/317 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 40 open | 101/141 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 43 open | 126/169 |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 88 open | 175/263 |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 105 open | 127/232 |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 302 open | 332/634 |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 288 open | 105/393 |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~961 open** | **1294/2245 closed** |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 110 open | 224/334 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 60 open | 103/163 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 53 open | 126/179 |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 118 open | 176/294 |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 141 open | 127/268 |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 407 open | 336/743 |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 300 open | 108/408 |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1189 open** | **1300/2489 closed** |
|
||||
|
||||
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95. Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M8 grew from 438→634, M9 grew from 359→393 due to continued agent activity.
|
||||
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 refresh. Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M8 grew from 634→743, M9 grew from 393→408 due to continued agent activity.
|
||||
|
||||
#### Story point allocation
|
||||
|
||||
|
||||