@@ -10,26 +10,27 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-10 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~25 open bugs | 225 open PRs | Session 4 active
footer Generated 2026-04-14 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~354 open PRs | 5044 open issues | AUTO-TIME-1
Project starts 2026-02-03
saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-10
today is 2026-04-14
today is colored in #FF6666
' ================================================================
' GANTT CHART UPDATE LOG (Day 100 — 2026-04-10)
' Changes: Day 100 refresh (cycle 2). Session 4 active (issue #4799, 32 workers).
' Open PRs: 221→225 (new PRs opened by agents). Open bugs: ~25 (Type/Bug label).
' M3 32% (249/770, scope expanded!), M4 49% (108/220), M5 43% (133/313),
' M6 18% (197/1085, scope massively expanded!), M7 38% (150/400),
' M8 45% (425/944), M9 28% (131/475).
' Massive scope expansion across all milestones since Day 98.
' pr-merge-pool-supervisor added as 17th supervisor. PR review reduced to 1 approval.
' git worktree sandbox merged. ACMS indexing pipeline wired.
' GANTT CHART UPDATE LOG (Day 104 — 2026-04-14) [AUTO-TIME-1]
' Changes: Schedule adherence check. v3.0.0 CLOSED (163 issues, 100%).
' v3.1.0 CLOSED (108 issues, 100%). Active milestones v3.2.0v3.9.0.
' M3 (v3.2.0) 24.8% (269/1086, 817 open). M4 (v3.3.0) 39.9% (109/273, 164 open).
' M5 (v3.4.0) 36.4% (139/382, 243 open). M6 (v3.5.0) 16.8% (212/1264, 1052 open).
' M7 (v3.6.0) 32.5% (152/468, 316 open). M8 (v3.7.0) 42.3% (427/1011, 584 open).
' M9 (v3.8.0) 26.3% (133/506, 373 open). v3.9.0 16.7% (4/24, 20 open).
' Total open issues: 5,044. Open PRs: 354.
' Milestones v3.2.0v3.6.0 are past their planned due dates.
' v3.7.0v3.9.0 have no assigned deadlines.
' ================================================================
<style>
@@ -231,7 +232,7 @@ ganttDiagram {
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
[M3] starts at [M2]'s end
[M3] is 65% completed
[M3] is 25% completed
[M3] is colored in LightSkyBlue/SteelBlue
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
@@ -252,13 +253,13 @@ ganttDiagram {
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
[M4] starts at [M3]'s end
[M4] is 60% completed
[M4] is 40% completed
[M4] is colored in LightSkyBlue/SteelBlue
[Security + Safety Hardening (#362)] as [SEC] on {Luis} requires 3 days
[SEC] starts 2026-03-02
[SEC] is 80% completed
[SEC] is 36% completed
[SEC] is colored in LightSkyBlue/SteelBlue
[Provider Fixes + Runtime (#363)] as [PROV] on {Luis} requires 2 days
@@ -283,12 +284,12 @@ ganttDiagram {
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
[M5] starts at [M4]'s end
[M5] is 68% completed
[M5] is 36% completed
[M5] is colored in LightSkyBlue/SteelBlue
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
[M6] starts at [M5]'s end
[M6] is 55% completed
[M6] is 17% completed
[M6] is colored in LightSkyBlue/SteelBlue
@@ -299,7 +300,7 @@ ganttDiagram {
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
[LARGE] starts 2026-03-17
[LARGE] is 43% completed
[LARGE] is 42% completed
[LARGE] is colored in LightSkyBlue/SteelBlue
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
@@ -319,13 +320,13 @@ ganttDiagram {
[Post-MVP Deferred Work (#366)] as [POST] on {Luis} {Hamza} {Jeff} {Rui} {Brent} requires 8 days
[POST] starts at [M6]'s end
[POST] is 0% completed
[POST] is colored in #E8E8E8/Silver
[POST] is 33% completed
[POST] is colored in LightSkyBlue/SteelBlue
[Multi-Agent RDF System (#367)] as [RDF] on {Aditya} requires 5 days
[RDF] starts 2026-03-24
[RDF] is 0% completed
[RDF] is colored in #E8E8E8/Silver
[RDF] is 33% completed
[RDF] is colored in LightSkyBlue/SteelBlue
' ── v3.6.0 MILESTONE ─────────────────────────────────────────
' Gate: All post-MVP deferred work
@@ -401,15 +402,18 @@ legend right
| v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs |
| v3.6.0 | Mar 27 | 2 | 100 | Deferred work |
----
**Risk Register (Day 100 — 2026-04-10)**
|= Epic |= Completion |= Risk |= Blocker |
| M3 (#357) | 32% | **CRITICAL** | 521 open issues in v3.2.0 (scope expanded 320→770) |
| M4 (#358) | 49% | **CRITICAL** | 112 open issues in v3.3.0 |
| M5 (#359) | 43% | **HIGH** | 180 open issues in v3.4.0 |
| M6 (#360) | 18% | **CRITICAL** | 888 open issues in v3.5.0 (massive scope expansion) |
| M7 (#361) | 38% | **HIGH** | 250 open issues in v3.6.0 |
| M8 (#362) | 45% | **HIGH** | 519 open issues in v3.7.0 |
| SEC (#363) | 28% | **HIGH** | 344 open issues in v3.8.0 |
**Risk Register (Day 104 — 2026-04-14) [AUTO-TIME-1]**
|= Milestone |= Completion |= Risk |= Blocker |
| v3.0.0 | 100% ✅ | **CLOSED** | Complete — 163 issues closed |
| v3.1.0 | 100% ✅ | **CLOSED** | Complete — 108 issues closed |
| v3.2.0 | 24.8% | **CRITICAL** | 817 open issues; past due 2026-02-26 |
| v3.3.0 | 39.9% | **CRITICAL** | 164 open issues; past due 2026-03-02 |
| v3.4.0 | 36.4% | **CRITICAL** | 243 open issues; past due 2026-03-06 |
| v3.5.0 | 16.8% | **CRITICAL** | 1052 open issues; past due 2026-03-10 |
| v3.6.0 | 32.5% | **HIGH** | 316 open issues; past due 2026-03-28 |
| v3.7.0 | 42.3% | **HIGH** | 584 open issues; no deadline |
| v3.8.0 | 26.3% | **HIGH** | 373 open issues; no deadline |
| v3.9.0 | 16.7% | **MEDIUM** | 20 open issues; no deadline |
----
**Color Key**
|= Color |= Meaning |
@@ -417,11 +421,12 @@ legend right
| <back:LightSkyBlue> </back> | In Progress |
| <back:#E8E8E8> </back> | Not Started |
| <back:Gold> <> </back> | Milestone Target |
| <back:#FF6666> | </back> | Today (2026-04-10) |
| <back:#FF6666> | </back> | Today (2026-04-14) |
----
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
~1649 total story points | ~3300 estimated hours
**~25 open bugs (Type/Bug) — 225 open PRs — Session 4 active (32 workers)**
**v3.0.0 ✅ CLOSED (163 issues) — v3.1.0 ✅ CLOSED (108 issues)**
**5,044 open issues — 354 open PRs — v3.2.0v3.9.0 active [AUTO-TIME-1 2026-04-14]**
end legend
@endgantt
@@ -445,7 +450,7 @@ saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-10
today is 2026-04-14
today is colored in #FF6666
<style>
@@ -1950,11 +1955,11 @@ legend right
| <back:LightSkyBlue> </back> | Issue: In Progress |
| <back:#E8E8E8> </back> | Issue: Not Started |
| <back:Gold> <> </back> | Milestone Target |
| <back:#FF6666> | </back> | Today (2026-04-10) |
| <back:#FF6666> | </back> | Today (2026-04-14) |
----
271 Issues | 29 Epics | 9 Legendaries | 7 Milestones
~1649 total story points | ~3300 estimated hours
**~5 open bugs (Type/Bug) — 219 open PRs — Session 4 active (32 workers)**
**v3.0.0 ✅ CLOSED — v3.1.0 ✅ CLOSED — 5,044 open issues — 354 open PRs [AUTO-TIME-1 2026-04-14]**
end legend
@endgantt
@@ -1966,13 +1971,13 @@ This section provides a high-level overview of the CleverAgents implementation r
### Current Status Summary
As of Day 100 (2026-04-10), the project has **225 open PRs** and **~2777 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~25 open bugs** (Type/Bug label; UAT issues tracked separately). M8 (v3.7.0) is now **45% complete** (425/944 issues closed). M3 (v3.2.0) at **32%** (249/770 — scope massively expanded), M4 (v3.3.0) at **49%** (108/220), M5 (v3.4.0) at **43%** (133/313), M6 (v3.5.0) at **18%** (197/1085 — scope massively expanded), M7 (v3.6.0) at **38%** (150/400).
As of 2026-04-14 [AUTO-TIME-1], the project has **354 open PRs** and **5,044 open issues** across active milestones. **v3.0.0 and v3.1.0 are CLOSED and 100% complete.** Active development spans v3.2.0v3.9.0. Milestones v3.2.0v3.6.0 are past their planned due dates. v3.7.0v3.9.0 have no assigned deadlines.
**M1, M2 fully complete. M3 (v3.2.0)**: 33% complete (248/757), 509 open issues — scope expanded massively. **M4 (v3.3.0)**: 49% complete (108/220), 112 open issues. **M5 (v3.4.0)**: 44% complete (133/301), 168 open issues. **M6 (v3.5.0)**: 18% complete (197/1065), 868 open issues — scope expanded massively. **M7 (v3.6.0)**: 38% complete (150/392), 242 open issues. **M8 (v3.7.0)**: 45% complete (423/938), 515 open issues. All milestones M3-M7 are **overdue**; M8 is in active v3.7.0 development.
**v3.0.0 ✅ CLOSED** (163 issues, 100% complete). **v3.1.0 ✅ CLOSED** (108 issues, 100% complete). **v3.2.0**: 24.8% complete (269 closed, 817 open) — past due 2026-02-26. **v3.3.0**: 39.9% complete (109 closed, 164 open) — past due 2026-03-02. **v3.4.0**: 36.4% complete (139 closed, 243 open) — past due 2026-03-06. **v3.5.0**: 16.8% complete (212 closed, 1052 open) — past due 2026-03-10. **v3.6.0**: 32.5% complete (152 closed, 316 open) — past due 2026-03-28. **v3.7.0**: 42.3% complete (427 closed, 584 open) — no deadline. **v3.8.0**: 26.3% complete (133 closed, 373 open) — no deadline. **v3.9.0**: 16.7% complete (4 closed, 20 open) — no deadline.
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — Massive Scope Expansion — Session 4 Active (Day 100: 219 Open PRs, M3/M6 Scope Exploded)"
!!! warning "Schedule Risk: v3.0.0 and v3.1.0 Complete — Milestones v3.2.0v3.6.0 Overdue — 5,044 Open Issues — 354 Open PRs [AUTO-TIME-1 2026-04-14]"
All milestones M3 through M7 have passed their target dates. **Session 4 active (launched 2026-04-08, issue #4799) with 32 parallel workers**. Open PRs at **219** (up from 1 — agents opened many new PRs). Open bugs at **~5** (Type/Bug label). Session tracker issue: #4799. **Current priorities**: (1) **M3 scope explosion**509 open issues (was 85 at Day 98); scope grew from 320 to 757 total. (2) **M6 scope explosion**868 open issues (was 450 at Day 98); scope grew from 638 to 1065 total. (3) **Merge 219 open PRs** — pr-merge-pool-supervisor added as 17th supervisor. (4) **Continue M8 push** — 45% complete, 515 issues remaining. (5) **Clear M4/M5 backlogs** — M4 at 49% (112 open), M5 at 44% (168 open).
**v3.0.0 ✅ CLOSED** (163 issues). **v3.1.0 ✅ CLOSED** (108 issues). All milestones v3.2.0 through v3.6.0 have passed their target dates. Open PRs at **354**. Total open issues: **5,044**. **Current priorities**: (1) **v3.2.0**817 open issues, 24.8% complete, past due 2026-02-26. (2) **v3.5.0**1,052 open issues, 16.8% complete, past due 2026-03-10. (3) **v3.7.0** — 584 open issues, 42.3% complete, no deadline. (4) **v3.3.0/v3.4.0/v3.6.0** — 164/243/316 open issues respectively. (5) **v3.8.0/v3.9.0** — 373/20 open issues, no deadlines.
### Parallel Workstreams
@@ -2140,18 +2145,21 @@ The following areas are substantially implemented and are no longer blocking:
The milestones and their target dates are:
| Milestone | Version | Target Date | Day # | Focus |
|-----------|---------|------------|-------|-------|
| M1 | v3.0.0 | 2026-02-15 | Day 7 | Minimal local source-code workflow |
| M2 | v3.1.0 | 2026-02-22 | Day 14 | Actor graphs + tool sources |
| M3 | v3.2.0 | 2026-02-26 | Day 18 | Decisions + validations + invariants |
| M4 | v3.3.0 | 2026-03-02 | Day 22 | Corrections + subplans + checkpoints |
| M5 | v3.4.0 | 2026-03-06 | Day 26 | ACMS v1 + context scaling |
| M6 | v3.5.0 | 2026-03-10 | Day 30 | Autonomy hardening |
| M7 | v3.6.0 | 2026-03-28 | Day 48 | Advanced Concepts & Deferred Features |
| M8 | v3.7.0 | Not set | N/A | TUI Implementation |
| M9 | v3.8.0 | Not Set | N/A | Server Implementation |
| Post-MVP | Not Set | Not Set | N/A | Deferred work |
| Milestone | Version | Target Date | Day # | Focus | Status |
|-----------|---------|------------|-------|-------|--------|
| M1 | v3.0.0 | 2026-02-15 | Day 7 | Minimal local source-code workflow | ✅ CLOSED (163 issues) |
| M2 | v3.1.0 | 2026-02-22 | Day 14 | Actor graphs + tool sources | ✅ CLOSED (108 issues) |
| M3 | v3.2.0 | 2026-02-26 | Day 18 | Decisions + validations + invariants | ⚠️ 24.8% (817 open) |
| M4 | v3.3.0 | 2026-03-02 | Day 22 | Corrections + subplans + checkpoints | ⚠️ 39.9% (164 open) |
| M5 | v3.4.0 | 2026-03-06 | Day 26 | ACMS v1 + context scaling | ⚠️ 36.4% (243 open) |
| M6 | v3.5.0 | 2026-03-10 | Day 30 | Autonomy hardening | ⚠️ 16.8% (1052 open) |
| M7 | v3.6.0 | 2026-03-28 | Day 48 | Advanced Concepts & Deferred Features | ⚠️ 32.5% (316 open) |
| M8 | v3.7.0 | Not set | N/A | TUI Implementation | 🔄 42.3% (584 open) |
| M9 | v3.8.0 | Not Set | N/A | Server Implementation | 🔄 26.3% (373 open) |
| M10 | v3.9.0 | Not Set | N/A | Extended features | 🔄 16.7% (20 open) |
| Post-MVP | Not Set | Not Set | N/A | Deferred work | 🔄 In Progress |
_Table updated by [AUTO-TIME-1] on 2026-04-14_
Day numbers are relative to the project kickoff on **February 9, 2026**.
@@ -2291,7 +2299,7 @@ Items without an assigned milestone represent backlog work to be addressed after
### Schedule Risk Summary
As of Day 96 (2026-04-06), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **108** (down from 183 — 75 PRs merged/closed!). Open bugs at **~878** (stable). M8 (v3.7.0) at **46% complete** (418/917 closed). M9 (v3.8.0) at **28% complete** (131/467 closed). Session tracker: #3775. Critical path: PR #3774 (Click 8.2+ fix) must be merged; 108 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 46% with 499 issues remaining; ~878 open bugs need TDD counterparts and systematic triage.
As of 2026-04-14 [AUTO-TIME-1], **v3.0.0 and v3.1.0 are CLOSED and 100% complete**. All milestones v3.2.0 through v3.6.0 are **overdue**. Open PRs at **354**. Total open issues: **5,044** across v3.2.0v3.9.0. v3.2.0 at **24.8%** (269/1086 closed, 817 open). v3.3.0 at **39.9%** (109/273 closed, 164 open). v3.4.0 at **36.4%** (139/382 closed, 243 open). v3.5.0 at **16.8%** (212/1264 closed, 1052 open). v3.6.0 at **32.5%** (152/468 closed, 316 open). v3.7.0 at **42.3%** (427/1011 closed, 584 open). v3.8.0 at **26.3%** (133/506 closed, 373 open). v3.9.0 at **16.7%** (4/24 closed, 20 open). Milestones v3.7.0v3.9.0 have no assigned deadlines.
**Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry.
@@ -5316,3 +5324,22 @@ Story points per developer per milestone.
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
### 2026-04-14 — Schedule Adherence Check [AUTO-TIME-1]
| Milestone | State | Open Issues | Closed Issues | Completion | Status |
|-----------|--------|-------------|---------------|------------|--------|
| v3.0.0 | CLOSED | 0 | 163 | 100% | ✅ Complete |
| v3.1.0 | CLOSED | 0 | 108 | 100% | ✅ Complete |
| v3.2.0 | OPEN | 817 | 269 | 24.8% | ⚠️ Behind (due 2026-02-26) |
| v3.3.0 | OPEN | 164 | 109 | 39.9% | ⚠️ Behind (due 2026-03-02) |
| v3.4.0 | OPEN | 243 | 139 | 36.4% | ⚠️ Behind (due 2026-03-06) |
| v3.5.0 | OPEN | 1052 | 212 | 16.8% | ⚠️ Behind (due 2026-03-10) |
| v3.6.0 | OPEN | 316 | 152 | 32.5% | ⚠️ Behind (due 2026-03-28) |
| v3.7.0 | OPEN | 584 | 427 | 42.3% | 🔄 In Progress (no deadline) |
| v3.8.0 | OPEN | 373 | 133 | 26.3% | 🔄 In Progress (no deadline) |
| v3.9.0 | OPEN | 20 | 4 | 16.7% | 🔄 In Progress (no deadline) |
**Summary**: v3.0.0 and v3.1.0 are complete. Active development spans v3.2.0v3.9.0 with 5,044 open issues and 354 open PRs. Milestones v3.2.0v3.6.0 are past their planned due dates. v3.7.0v3.9.0 have no assigned deadlines.
_Updated by [AUTO-TIME-1] on 2026-04-14_