Compare commits

...

1 Commits

Author SHA1 Message Date
freemo 4e9dafc1f4 docs(timeline): update schedule adherence Day 95 (2026-04-05)
CI / lint (pull_request) Successful in 28s
CI / quality (pull_request) Successful in 42s
CI / typecheck (pull_request) Successful in 48s
CI / security (pull_request) Successful in 1m2s
CI / build (pull_request) Successful in 32s
CI / helm (pull_request) Successful in 23s
CI / unit_tests (pull_request) Successful in 6m31s
CI / docker (pull_request) Successful in 1m17s
CI / coverage (pull_request) Successful in 10m45s
CI / e2e_tests (pull_request) Successful in 17m14s
CI / integration_tests (pull_request) Successful in 22m43s
CI / status-check (pull_request) Successful in 1s
CI / benchmark-publish (pull_request) Has been skipped
CI / benchmark-regression (pull_request) Successful in 57m9s
2026-04-05 16:37:30 +00:00
+49 -47
View File
@@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 536 open bugs | 92 open PRs | Session 3 active
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 778 open bugs | 168 open PRs | Session 3 active
Project starts 2026-02-03
saturday are closed
@@ -22,12 +22,12 @@ today is colored in #FF6666
' ================================================================
' GANTT CHART UPDATE LOG (Day 95 — 2026-04-05)
' Changes: Day 95 update (refreshed). Open PRs: 76→92 (+16). Open bugs: 536 (stable).
' Open issues: continued agent-driven expansion across all milestones.
' M3 67% (223/334), M4 63% (103/163), M5 70% (126/179), M6 67% (175/263),
' M7 55% (127/232), M8 52% (332/634), M9 27% (105/393).
' Changes: Day 95 final update. Open PRs: 92→168 (+76). Open bugs: 536→778 (+242).
' Open issues: 1515 total. Continued agent-driven expansion across all milestones.
' M3 64% (228/357), M4 60% (104/172), M5 68% (126/184), M6 55% (176/318),
' M7 43% (131/308), M8 43% (345/796), M9 25% (117/462).
' Session 3 active. UAT pool supervisor and spec updater agents running.
' Session tracker issue: #3075 (autonomous build progress report).
' Session tracker issue: #3377 (autonomous build progress report).
' ================================================================
<style>
@@ -1951,7 +1951,7 @@ legend right
----
271 Issues | 29 Epics | 9 Legendaries | 7 Milestones
~1649 total story points | ~3300 estimated hours
**536 open bugs — 76 open PRs — Session 3 active (16 workers, ~71 agents)**
**778 open bugs — 168 open PRs — Session 3 active (16 workers, ~71 agents)**
end legend
@endgantt
@@ -1963,13 +1963,13 @@ This section provides a high-level overview of the CleverAgents implementation r
### Current Status Summary
As of Day 95 (2026-04-05), the project has **76 open PRs** and **~2800+ open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **536 open bugs** (continued agent-driven expansion from 389). M8 (v3.7.0) is now **52% complete** (332/634 issues closed — milestone grew from 438→634). M9 (v3.8.0) is **27% complete** (105/393 issues closed).
As of Day 95 (2026-04-05), the project has **168 open PRs** and **1515 open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **778 open bugs** (continued agent-driven expansion from 536). M8 (v3.7.0) is now **43% complete** (345/796 issues closed — milestone grew from 634→796). M9 (v3.8.0) is **25% complete** (117/462 issues closed — milestone grew from 393→462).
**M1, M2 fully complete. M3 (v3.2.0)**: 70% complete (222/317), 95 open issues. **M4 (v3.3.0)**: 72% complete (101/141), 40 open issues. **M5 (v3.4.0)**: 75% complete (126/169), 43 open issues. **M6 (v3.5.0)**: 67% complete (175/263), 88 open issues. **M7 (v3.6.0)**: 55% complete (127/232), 105 open issues. **M8 (v3.7.0)**: 52% complete (332/634), 302 open issues. **M9 (v3.8.0)**: 27% complete (105/393), 288 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
**M1, M2 fully complete. M3 (v3.2.0)**: 64% complete (228/357), 129 open issues. **M4 (v3.3.0)**: 60% complete (104/172), 68 open issues. **M5 (v3.4.0)**: 68% complete (126/184), 58 open issues. **M6 (v3.5.0)**: 55% complete (176/318), 142 open issues. **M7 (v3.6.0)**: 43% complete (131/308), 177 open issues. **M8 (v3.7.0)**: 43% complete (345/796), 451 open issues. **M9 (v3.8.0)**: 25% complete (117/462), 345 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development.
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 536 Open Bugs — Session 3 Active (Day 95: Continued Agent Expansion)"
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 778 Open Bugs — Session 3 Active (Day 95: Continued Agent Expansion)"
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **76** (up from 64). Open bugs at **536** (continued agent-driven expansion from 389). M8 (v3.7.0) at 52% (332/634 closed — milestone grew from 438→634). M9 (v3.8.0) at 27% (105/393 closed). New session tracker issues: #2874 (progress report), #2875 (UAT pool supervisor), #2876 (spec updater). **Current priorities**: (1) **Triage 536 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 76 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push**52% complete, 302 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 70% (95 open), M4 at 72% (40 open), M5 at 75% (43 open).
All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **168** (up from 92 earlier today). Open bugs at **778** (continued agent-driven expansion from 536). M8 (v3.7.0) at 43% (345/796 closed — milestone grew from 634→796). M9 (v3.8.0) at 25% (117/462 closed — milestone grew from 393→462). Session tracker issue: #3377. **Current priorities**: (1) **Triage 778 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 168 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push**43% complete, 451 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 64% (129 open), M4 at 60% (68 open), M5 at 68% (58 open).
### Parallel Workstreams
@@ -2285,18 +2285,20 @@ Items without an assigned milestone represent backlog work to be addressed after
### Schedule Risk Summary
As of Day 95 (2026-04-05), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **76** (up from 64). Open bugs at **536** (continued agent-driven expansion from 389). M8 (v3.7.0) at **52% complete** (332/634 closed — milestone grew from 438→634). M9 (v3.8.0) at **27% complete** (105/393 closed). Critical path: 76 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 52% with 302 issues remaining; 536 open bugs need TDD counterparts and systematic triage.
As of Day 95 (2026-04-05), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **168** (up from 92 earlier today). Open bugs at **778** (continued agent-driven expansion from 536). M8 (v3.7.0) at **43% complete** (345/796 closed — milestone grew from 634→796). M9 (v3.8.0) at **25% complete** (117/462 closed — milestone grew from 393→462). Critical path: 168 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 43% with 451 issues remaining; 778 open bugs need TDD counterparts and systematic triage.
**Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry.
**Day 53 Session 3 actions**: (a) 16 parallel workers started. (b) 73+ PRs merged including ACMS UKO runtime (#1312), PermissionsScreen TUI (#1307), actor thought blocks (#1298), DatabaseResourceHandler (#1293), ACMS pipeline Phase 2 (#1287), DevcontainerHandler (#1286), async audit (#1279), serve CLI (#1272), LSP hover/definitions (#1240), domain event wiring (#1215), plan prompt command (#1212), M6 E2E tests (#1277), @tdd_expected_fail cleanup (#1229), persona export/import (#1338), first-run experience (#1391), session export/import (#1392). (c) UAT supervisor fleet (cycles 11-131) launched — discovered 100+ spec compliance bugs across CLI rich output, YAML config handling, and actor compiler. (d) Security bug-hunt PRs opened: #1412 (concurrency), #1409 (error handling), #1419 (hardcoded secrets). (e) Late-day: 4 more PRs merged (#1498, #1481, #1479, #1338), 18 new fix PRs opened (#1506-#1517) targeting UAT findings. (f) End-of-day CLI fix wave: 18 more PRs merged (#1574, #1573, #1570, #1569, #1567, #1566, #1565, #1563, #1562, #1558, #1556, #1554 and others) — open bugs reduced from **143 to 6**, open PRs at **74**.
**Day 95 final update**: Open PRs surged to **168** (from 92 earlier today) and open bugs to **778** (from 536) due to continued agent-driven UAT issue creation and PR generation. All milestones regressed in completion percentage as new issues were added faster than closures. Session tracker issue: #3377.
**Critical path blockers** (ranked):
1. **76 open PRs need review** — continued agent-driven PR creation. All require review before merge.
2. **536 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued agent-driven expansion.
3. **M3-M7 backlog**95+40+43+88+105 open issues across M3-M7. All milestones regressed as agents added new issues.
4. **M8 (v3.7.0) at 52%**302 issues remaining (milestone grew from 438→634). Continued agent-driven expansion.
5. **M9 (v3.8.0) at 27%**288 issues remaining (milestone grew from 359→393). Significant expansion.
1. **168 open PRs need review** — continued agent-driven PR creation. All require review before merge.
2. **778 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued agent-driven expansion.
3. **M3-M7 backlog**129+68+58+142+177 open issues across M3-M7. All milestones regressed as agents added new issues.
4. **M8 (v3.7.0) at 43%**451 issues remaining (milestone grew from 634→796). Continued agent-driven expansion.
5. **M9 (v3.8.0) at 25%**345 issues remaining (milestone grew from 393→462). Significant expansion.
**Spec changes impact assessment (Day 31)**: ACP→A2A rename affects 10 source files, 13 classes, 640+ test references across 22 files. Zero A2A code exists — migration not started. All open PRs that touch ACP modules will need additional rebase work after #688/#689 merge. TUI spec adds ~1,500 lines with 18 ASCII mockups defining Textual-based UI — PR #667 was a placeholder that predates this spec. Server architecture adopts JSON-RPC 2.0 standard — PR #676 used custom protocol, now obsolete.
@@ -4949,14 +4951,14 @@ Deadline risk: HIGH
**Notes**
- Day 95 update (refreshed 2026-04-05). Open PRs: 92 (up from 76 earlier today, +16 new PRs). Open bugs: 536 (stable). Session tracker issue: #3075.
- Day 95 final update (2026-04-05). Open PRs: 168 (surged from 92 earlier today, +76 new PRs). Open bugs: 778 (surged from 536, +242). Session tracker issue: #3377.
- Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. UAT pool supervisor, PR reviewer pool, implementation pool, and spec updater agents all running.
- Milestone totals continued to grow due to agent-driven issue creation: M3 (317→334), M4 (141→163), M5 (169→179), M6 (263 stable), M7 (232 stable), M8 (634 stable), M9 (393 stable).
- Milestone completions (Day 95 refreshed): M3 67% (223/334), M4 63% (103/163), M5 70% (126/179), M6 67% (175/263), M7 55% (127/232), M8 52% (332/634), M9 27% (105/393).
- M3 and M4 completion percentages declined from earlier Day 95 reading (M3: 70%→67%, M4: 72%→63%) because agent-driven issue creation is outpacing closures.
- Milestone totals continued to grow due to agent-driven issue creation: M3 (334→357), M4 (163→172), M5 (179→184), M6 (263→318), M7 (232→308), M8 (634→796), M9 (393→462).
- Milestone completions (Day 95 final): M3 64% (228/357), M4 60% (104/172), M5 68% (126/184), M6 55% (176/318), M7 43% (131/308), M8 43% (345/796), M9 25% (117/462).
- All completion percentages declined from earlier Day 95 reading because agent-driven issue creation is outpacing closures across all milestones.
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
- UAT pool supervisor (#3075) and spec updater agents are running autonomously, continuing to discover and file spec compliance issues.
- PR #3073 (docs/timeline-day95-refresh) is open with updated milestone data — this entry supersedes it.
- UAT pool supervisor (#3377) and spec updater agents are running autonomously, continuing to discover and file spec compliance issues.
- Total open issues: 1515 across all milestones.
#### Milestone forecast
@@ -4965,55 +4967,55 @@ Deadline risk: HIGH
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-04-28 | +61d | CRITICAL — 111 open issues; agent-driven expansion outpacing closures |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-02 | +61d | CRITICAL — 60 open issues; completion dropped 72%→63% |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-02 | +57d | HIGH — 53 open issues; 70% complete |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-10 | +61d | HIGH — 88 open issues; 67% complete |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-05-25 | +58d | HIGH — 105 open issues; 55% complete |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-06-20 | N/A | HIGH — 302 open issues; 52% complete |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-10 | N/A | MEDIUM — 288 open issues; 27% complete |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-05 | +68d | CRITICAL — 129 open issues; 64% complete; agent-driven expansion outpacing closures |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-10 | +69d | CRITICAL — 68 open issues; 60% complete; completion dropped 63%→60% |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-10 | +65d | HIGH — 58 open issues; 68% complete |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-20 | +71d | HIGH — 142 open issues; 55% complete; milestone grew 263→318 |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-05 | +69d | HIGH — 177 open issues; 43% complete; milestone grew 232→308 |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-10 | N/A | HIGH — 451 open issues; 43% complete; milestone grew 634→796 |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-01 | N/A | MEDIUM — 345 open issues; 25% complete; milestone grew 393→462 |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-02 | MEDIUM | 53 open issues in v3.4.0; continued agent-driven expansion |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-02 | CRITICAL | 60 open issues in v3.3.0; UAT spec compliance bugs ongoing; completion dropped |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-04-28 | CRITICAL | 111 open issues in v3.2.0; agent-driven expansion outpacing closures |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 536 open bugs; continued agent-driven bug creation |
| Track T (Testing) | Active | Ongoing | HIGH | 92 open PRs need review; UAT pool supervisor active (#3075) |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-10 | MEDIUM | 58 open issues in v3.4.0; continued agent-driven expansion |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-10 | CRITICAL | 68 open issues in v3.3.0; UAT spec compliance bugs ongoing; completion dropped 63%→60% |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-05 | CRITICAL | 129 open issues in v3.2.0; agent-driven expansion outpacing closures |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 778 open bugs; continued agent-driven bug creation (+242 today) |
| Track T (Testing) | Active | Ongoing | HIGH | 168 open PRs need review; UAT pool supervisor active (#3377) |
#### Developer forecast
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|------|-------------------|--------------|------|-------|
| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance; 92 open PRs |
| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance; 168 open PRs |
| Luis | -21d behind | active | HIGH | M6 (v3.5.0) features; security hardening; audit session; PR review pool |
| Hamza | -21d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews |
| Aditya | -21d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 536 open bugs triage |
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 778 open bugs triage |
| Rui | -21d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
| Mike/Brian | N/A | standby | LOW | N/A |
#### Task inventory
Milestone per developer as of Day 95 (2026-04-05).
Milestone per developer as of Day 95 final (2026-04-05).
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 111 open | 223/334 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 60 open | 103/163 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 53 open | 126/179 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 88 open | 175/263 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 105 open | 127/232 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 302 open | 332/634 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 288 open | 105/393 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1007 open** | **1191/2198 closed** |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 129 open | 228/357 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 68 open | 104/172 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 58 open | 126/184 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 142 open | 176/318 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 177 open | 131/308 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 451 open | 345/796 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 345 open | 117/462 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1370 open** | **1283/2553 closed** |
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 (refreshed 2026-04-05). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M3 grew from 317→334, M4 grew from 141→163, M5 grew from 169→179 due to continued agent activity.
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 final (2026-04-05). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M3 grew 334→357, M4 grew 163→172, M5 grew 179→184, M6 grew 263→318, M7 grew 232→308, M8 grew 634→796, M9 grew 393→462 due to continued agent activity.
#### Story point allocation