Compare commits

...

1 Commits

Author SHA1 Message Date
HAL9000 c6d38138d3 docs(timeline): [AUTO-TIME-1] update schedule adherence Day 103 cycle-1
CI / benchmark-publish (pull_request) Has been skipped
CI / helm (pull_request) Successful in 24s
CI / push-validation (pull_request) Successful in 25s
CI / build (pull_request) Successful in 28s
CI / lint (pull_request) Successful in 32s
CI / quality (pull_request) Successful in 51s
CI / typecheck (pull_request) Successful in 53s
CI / security (pull_request) Successful in 1m4s
CI / e2e_tests (pull_request) Successful in 3m0s
CI / integration_tests (pull_request) Successful in 11m4s
CI / unit_tests (pull_request) Successful in 11m7s
CI / docker (pull_request) Successful in 11s
CI / coverage (pull_request) Successful in 10m20s
CI / status-check (pull_request) Successful in 1s
CI / benchmark-regression (pull_request) Successful in 57m34s
2026-04-13 03:33:52 +00:00
+109 -3
View File
@@ -10,16 +10,27 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-10 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~25 open bugs | 225 open PRs | Session 4 active
footer Generated 2026-04-13 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~25 open bugs | ~225 open PRs | Session 5 active
Project starts 2026-02-03
saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-10
today is 2026-04-13
today is colored in #FF6666
' ================================================================
' ================================================================
' GANTT CHART UPDATE LOG (Day 103 — 2026-04-13)
' Changes: Day 103 refresh (cycle 1). Session 5 active (32 workers).
' CI failing on master. v3.9.0 milestone added (19 total issues, 21% complete).
' M3 27.5% (264/962), M4 45.8% (108/236), M5 39.5% (137/347),
' M6 17.0% (202/1187, scope expanded!), M7 35.1% (152/433),
' M8 44.6% (427/957), M9 27.0% (132/489), M10 21.1% (4/19).
' Scope expansion continues across M3, M5, M6, M7, M8, M9.
' v3.1.0 closed with 2 residual open issues (98.2% complete).
' ================================================================
' GANTT CHART UPDATE LOG (Day 100 — 2026-04-10)
' Changes: Day 100 refresh (cycle 2). Session 4 active (issue #4799, 32 workers).
@@ -445,7 +456,7 @@ saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-10
today is 2026-04-13
today is colored in #FF6666
<style>
@@ -5316,3 +5327,98 @@ Story points per developer per milestone.
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
### 2026-04-13 (Day 103)
**Summary**
Status: Behind 30+d
Deadline risk: CRITICAL
**Notes**
- Day 103 update (2026-04-13, [AUTO-TIME] cycle 1). Session 5 active (32 parallel workers). CI failing on master.
- v3.9.0 milestone newly tracked: 19 total issues (15 open / 4 closed), 21.1% complete.
- v3.1.0 (M2) closed with 2 residual open issues remaining (98.2% complete).
- Milestone completions (Day 103): M3 27.5% (264/962, was 32% Day 100 — scope expanded 770→962 +192), M4 45.8% (108/236, was 49%), M5 39.5% (137/347, was 43% — scope expanded 313→347 +34), M6 17.0% (202/1187, was 18% — scope expanded 1085→1187 +102), M7 35.1% (152/433, was 38% — scope expanded 400→433 +33), M8 44.6% (427/957, was 45% — scope expanded 944→957 +13), M9 27.0% (132/489, was 28% — scope expanded 475→489 +14).
- Continued scope expansion across all active milestones. Agent-driven issue creation ongoing at high velocity.
- CI pipeline failing on master branch — blocking automated validation and merge gates.
- Total open issues across all active milestones: 698+128+210+985+281+530+357+15 = 3,204 open issues.
#### Milestone forecast
| Milestone | Target -> ETA | Delta | Risk |
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE (2 residual) | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-07-01 | +125d | CRITICAL — 698 open issues; 27.5% complete (scope expanded 770→962) |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-25 | +84d | HIGH — 128 open issues; 45.8% complete |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-06-01 | +87d | HIGH — 210 open issues; 39.5% complete (scope expanded 313→347) |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-09-01 | +175d | CRITICAL — 985 open issues; 17.0% complete (scope expanded 1085→1187) |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-07-01 | +95d | HIGH — 281 open issues; 35.1% complete (scope expanded 400→433) |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-08-01 | N/A | HIGH — 530 open issues; 44.6% complete (scope expanded 944→957) |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-15 | N/A | MEDIUM — 357 open issues; 27.0% complete (scope expanded 475→489) |
| M10 (v3.9.0) | (no deadline) -> ETA 2026-06-01 | N/A | LOW — 15 open issues; 21.1% complete (new milestone) |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-06-01 | HIGH | 210 open issues in v3.4.0; scope expanded +34 since Day 100 |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-25 | HIGH | 128 open issues in v3.3.0 |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-07-01 | CRITICAL | 698 open issues in v3.2.0; scope expanded +192 since Day 100 |
| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | CI failing on master; ~25 open bugs; scope explosion across all milestones |
| Track T (Testing) | Active | Ongoing | CRITICAL | CI failing on master; 3,204 total open issues across active milestones |
#### Developer forecast
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|------|-------------------|--------------|------|-------|
| Jeff | -28d behind | active | HIGH | Session 5 supervisor; M3/M4/M5 backlog clearance; CI fix; architecture oversight |
| Luis | -28d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool |
| Hamza | -28d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews |
| Aditya | -28d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
| Brent | -28d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; CI investigation |
| Rui | -28d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
| Mike/Brian | N/A | standby | LOW | Infrastructure support |
#### Task inventory
Milestone per developer as of Day 103 (2026-04-13).
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 698 open | 264/962 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 128 open | 108/236 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 210 open | 137/347 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 985 open | 202/1187 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 281 open | 152/433 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 530 open | 427/957 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 357 open | 132/489 |
| M10 | N/A | N/A | N/A | N/A | N/A | N/A | 15 open | 4/19 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~3,204 open** | **1,582/4,782 closed** |
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 103 (2026-04-13). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues at high velocity. CI failing on master is a critical blocker.
#### Story point allocation
Story points per developer per milestone.
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~172 SP |
| M2 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~208 SP |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~104 SP |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~126 SP |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~129 SP |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~100 SP |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M10 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |