docs(timeline): update schedule adherence Day 99 (2026-04-09) cycle-5
CI / lint (pull_request) Successful in 26s
CI / quality (pull_request) Successful in 36s
CI / build (pull_request) Successful in 26s
CI / push-validation (pull_request) Successful in 30s
CI / security (pull_request) Successful in 1m1s
CI / helm (pull_request) Successful in 48s
CI / typecheck (pull_request) Successful in 1m23s
CI / e2e_tests (pull_request) Successful in 3m2s
CI / integration_tests (pull_request) Successful in 4m1s
CI / unit_tests (pull_request) Successful in 8m5s
CI / docker (pull_request) Successful in 19s
CI / coverage (pull_request) Successful in 13m4s
CI / status-check (pull_request) Successful in 1s
CI / benchmark-publish (pull_request) Has been skipped
CI / benchmark-regression (pull_request) Failing after 9h41m56s

- Append Day 99 schedule adherence entry with full milestone, track,
  developer, task inventory, and story point allocation tables
- Update gantt chart: today marker 2026-04-09, footer, update log
- Update Current Status Summary: 178 open PRs, ~3422 open bugs
- Milestone completions: M2 98% (108/110), M3 48% (248/514),
  M4 53% (108/203), M5 59% (132/223), M6 19% (193/1020),
  M7 40% (150/372), M8 45% (422/935), M9 28% (130/465)
- PRs #4219 (ACMS indexing) and #4218 (checkpoint wiring) merged
- Bug count tripled: ~878 to ~3422 (UAT pool high-velocity filing)

ISSUES CLOSED: #5782
This commit is contained in:
2026-04-09 14:44:20 +00:00
parent a3d644ca52
commit d8c8a6453c
+61 -60
View File
@@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-09 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~2861 open bugs | 145 open PRs | Session 4 active
footer Generated 2026-04-09 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3422 open bugs | 178 open PRs | Session 4 active
Project starts 2026-02-03
saturday are closed
@@ -22,13 +22,12 @@ today is colored in #FF6666
' ================================================================
' GANTT CHART UPDATE LOG (Day 99 — 2026-04-09)
' Changes: Day 99 refresh. Session 4 active (#4799, 32 workers).
' Open PRs: 1→145 (+144 new PRs opened by agents). Open bugs: ~878→~2861 (+1983 new bugs!).
' M3 62% (240/387, scope grew 320→387), M4 56% (108/191, scope grew 161→191),
' M5 69% (130/187, scope grew 183→187), M6 27% (192/711, scope grew 638→711),
' M7 47% (150/313), M8 47% (422/880), M9 29% (129/435).
' Massive bug explosion: 878→2861 open bugs (+1983). Agent-driven issue creation continues.
' All milestones M3-M7 remain overdue. M8/M9 in active development.
' Changes: Day 99 refresh. Session 4 active (issue #4799), 32 parallel workers.
' Open PRs: 1→178 (+177 new PRs). Open bugs: ~878→~3422 (+2544 new UAT bugs!).
' M3 48% (248/514), M4 53% (108/203), M5 59% (132/223), M6 19% (193/1020),
' M7 40% (150/372), M8 45% (422/935), M9 28% (130/465).
' PRs #4219 (ACMS indexing) and #4218 (checkpoint wiring) merged to master.
' Bug count tripled: ~878→~3422 (UAT pool filing bugs at very high velocity).
' ================================================================
<style>
@@ -400,15 +399,15 @@ legend right
| v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs |
| v3.6.0 | Mar 27 | 2 | 100 | Deferred work |
----
**Risk Register (Day 99 — 2026-04-09)**
**Risk Register (Day 96 — 2026-04-06)**
|= Epic |= Completion |= Risk |= Blocker |
| M3 (#357) | 62% | **CRITICAL** | 147 open issues in v3.2.0; scope grew 320→387 |
| M4 (#358) | 56% | **CRITICAL** | 83 open issues in v3.3.0; scope grew 161→191 |
| M5 (#359) | 69% | **HIGH** | 57 open issues in v3.4.0; scope grew 183→187 |
| M6 (#360) | 27% | **CRITICAL** | 519 open issues in v3.5.0; scope grew 638→711 |
| M7 (#361) | 47% | **HIGH** | 163 open issues in v3.6.0 |
| M8 (#362) | 47% | **HIGH** | 458 open issues in v3.7.0; scope grew 855→880 |
| SEC (#363) | 29% | **HIGH** | 306 open issues in v3.8.0; 2861 total open bugs! |
| M3 (#357) | 65% | **CRITICAL** | 131 open issues in v3.2.0 |
| M4 (#358) | 60% | **CRITICAL** | 74 open issues in v3.3.0 |
| M5 (#359) | 68% | **HIGH** | 63 open issues in v3.4.0 |
| M6 (#360) | 55% | **HIGH** | 147 open issues in v3.5.0 |
| M7 (#361) | 43% | **HIGH** | 198 open issues in v3.6.0 |
| M8 (#362) | 46% | **HIGH** | 499 open issues in v3.7.0 (agent expansion) |
| SEC (#363) | 28% | **HIGH** | 336 open issues in v3.8.0 (agent expansion) |
----
**Color Key**
|= Color |= Meaning |
@@ -420,7 +419,7 @@ legend right
----
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
~1649 total story points | ~3300 estimated hours
**~2861 open bugs — 145 open PRs — Session 4 active (32 workers, #4799)**
**~3,422 open bugs — 178 open PRs — Session 4 active (32 workers, full supervisor fleet)**
end legend
@endgantt
@@ -1949,11 +1948,11 @@ legend right
| <back:LightSkyBlue> </back> | Issue: In Progress |
| <back:#E8E8E8> </back> | Issue: Not Started |
| <back:Gold> <> </back> | Milestone Target |
| <back:#FF6666> | </back> | Today (2026-04-05) |
| <back:#FF6666> | </back> | Today (2026-04-09) |
----
271 Issues | 29 Epics | 9 Legendaries | 7 Milestones
~1649 total story points | ~3300 estimated hours
**878 open bugs — 183 open PRs — Session 3 active (16 workers, ~71 agents)**
**~3,422 open bugs — 178 open PRs — Session 4 active (32 workers, full supervisor fleet)**
end legend
@endgantt
@@ -1965,13 +1964,13 @@ This section provides a high-level overview of the CleverAgents implementation r
### Current Status Summary
As of Day 99 (2026-04-09), the project has **145 open PRs** (up from 1 — agents opened 144 new PRs) and **~1733 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~2861 open bugs** (massive increase from ~878 — +1983 new bugs filed by agents). M8 (v3.7.0) is now **47% complete** (422/880 issues closed). M3 (v3.2.0) at **62%** (240/387, scope grew 320→387), M4 (v3.3.0) at **56%** (108/191, scope grew 161→191), M5 (v3.4.0) at **69%** (130/187), M6 (v3.5.0) at **27%** (192/711, scope grew 638→711), M7 (v3.6.0) at **47%** (150/313).
As of Day 99 (2026-04-09), the project has **178 open PRs** (up from 1 — agents opened 177 new PRs) and **~2322 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~3,422 open bugs** (up from ~878 — UAT pool filing spec compliance issues at very high velocity). M8 (v3.7.0) is now **45% complete** (422/935 issues closed). M3 (v3.2.0) at **48%** (248/514), M4 (v3.3.0) at **53%** (108/203), M5 (v3.4.0) at **59%** (132/223 — PRs #4219 and #4218 merged!), M6 (v3.5.0) at **19%** (193/1020 — scope massively expanded from 638 to 1020 issues), M7 (v3.6.0) at **40%** (150/372), M9 (v3.8.0) at **28%** (130/465).
**M1, M2 fully complete. M3 (v3.2.0)**: 62% complete (240/387), 147 open issues. **M4 (v3.3.0)**: 56% complete (108/191), 83 open issues. **M5 (v3.4.0)**: 69% complete (130/187), 57 open issues. **M6 (v3.5.0)**: 27% complete (192/711), 519 open issues — scope continues to expand. **M7 (v3.6.0)**: 47% complete (150/313), 163 open issues. **M8 (v3.7.0)**: 47% complete (422/880), 458 open issues. **M9 (v3.8.0)**: 29% complete (129/435), 306 open issues. All milestones M3-M7 are **overdue**; M8/M9 are in active development.
**M1 fully complete. M2 (v3.1.0)**: 98% complete (108/110), 2 open issues. **M3 (v3.2.0)**: 48% complete (248/514), 266 open issues. **M4 (v3.3.0)**: 53% complete (108/203), 95 open issues. **M5 (v3.4.0)**: 59% complete (132/223), 91 open issues — PRs #4219 (ACMS indexing) and #4218 (checkpoint wiring) merged. **M6 (v3.5.0)**: 19% complete (193/1020), 827 open issues — scope expanded massively (+382 new issues since Day 98). **M7 (v3.6.0)**: 40% complete (150/372), 222 open issues. **M8 (v3.7.0)**: 45% complete (422/935), 513 open issues. **M9 (v3.8.0)**: 28% complete (130/465), 335 open issues. All milestones M3-M7 are **overdue**; M8/M9 are in active development.
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — ~2861 Open Bugs — Session 4 Active (Day 99: 145 Open PRs, Bug Count Exploded +1983)"
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — ~3,422 Open Bugs — Session 4 Active (Day 99: Bug Count Tripled, M6 Scope Expanded +382 Issues, 178 Open PRs)"
All milestones M3 through M7 have passed their target dates. **Session 4 active (launched 2026-04-08, #4799) with 32 parallel workers**. Open PRs at **145** (up from 1 — agents opened 144 new PRs). Open bugs at **~2861** (up from ~878 — massive +1983 bug explosion from agent-driven UAT and bug-hunter activity). Session tracker issue: #4799. **Current priorities**: (1) **Bug explosion triage**2861 open bugs requires systematic review and TDD counterpart creation. (2) **M6 scope explosion**519 open issues (scope grew 638→711); continued agent-driven expansion. (3) **Clear M3/M4/M5 backlogs** — M3 at 62% (147 open), M4 at 56% (83 open), M5 at 69% (57 open). (4) **Review 145 open PRs** — agents opened 144 new PRs since Day 98.
All milestones M3 through M7 have passed their target dates. **Session 4 active (launched 2026-04-08, issue #4799) with 32 parallel workers**. Open PRs at **178** (up from 1 — agents opened 177 new PRs). Open bugs at **~3,422** (tripled from ~878 — UAT pool filing bugs at very high velocity). Session tracker issue: #4799. **Current priorities**: (1) **Bug triage crisis**~3,422 open bugs (was ~878 at Day 98); UAT pool is discovering spec compliance issues at very high velocity. (2) **M6 scope explosion**827 open issues (was 450 at Day 98); scope expanded from 638 to 1020 total. (3) **Continue M8/M9 push** — M8 at 45% (513 open), M9 at 28% (335 open). (4) **Clear M3/M4/M5 backlogs** — M3 at 48% (266 open), M4 at 53% (95 open), M5 at 59% (91 open). (5) **Good news**: PRs #4219 (ACMS indexing) and #4218 (checkpoint wiring) merged to master — M5 progress.
### Parallel Workstreams
@@ -5233,14 +5232,16 @@ Deadline risk: CRITICAL
**Notes**
- Day 99 update (2026-04-09). Session 4 remains active (#4799, 32 parallel workers, full supervisor fleet).
- Open PRs surged from 1 to 145 (+144 new PRs opened by agents since Day 98). Agents are actively implementing features and fixes across all active milestones.
- Open bugs exploded from ~878 to ~2861 (+1983 new bugs). Bug-hunter, UAT, and spec-compliance agents filed massive volumes of new issues. This is the largest single-day bug increase recorded.
- Milestone scope continued to grow due to agent-driven issue creation: M3 (320→387, +67), M4 (161→191, +30), M5 (183→187, +4), M6 (638→711, +73), M7 (312→313, +1), M8 (855→880, +25), M9 new data (435 total, 129 closed).
- Milestone completion percentages dropped despite stable or growing closed counts, due to scope expansion outpacing closures: M3 73%→62%, M4 67%→56%, M5 71%→69%, M6 29%→27%, M7 48%→47%.
- M8 (v3.7.0) closed count grew: 403→422 (+19 issues closed). M9 (v3.8.0) now tracked: 129/435 = 29% complete, 306 open.
- Architecture review agent (issue #5158) and human liaison (issue #5157) both active. Backlog groomer (issue #5152) and system watchdog (issue #5150) running. Spec updater (issue #5145) and agent evolver (issue #5143) active.
- All milestones M3-M7 remain overdue. Critical path: triage 2861 open bugs, review 145 open PRs, continue M3/M4/M5 backlog clearance.
- Day 99 update (2026-04-09). Session 4 remains active (issue #4799) with 32 parallel workers and full supervisor fleet.
- Open PRs grew from 1 to 178 (+177 new PRs opened by agents across docs, spec, fix, and feat categories).
- Open bugs tripled: ~878 → ~3,422 (+2,544 new UAT bugs). UAT pool supervisor is filing spec compliance issues at very high velocity.
- Milestone scope expanded significantly across all milestones due to agent-driven issue creation: M2 (108→110, +2), M3 (320→514, +194), M4 (161→203, +42), M5 (183→223, +40), M6 (638→1020, +382), M7 (312→372, +60), M8 (855→935, +80), M9 (N/A→465 total).
- Milestone completions (Day 99 cycle-5): M2 98% (108/110), M3 48% (248/514), M4 53% (108/203), M5 59% (132/223), M6 19% (193/1020), M7 40% (150/372), M8 45% (422/935), M9 28% (130/465).
- **Progress**: PRs #4219 (ACMS indexing pipeline wiring) and #4218 (checkpoint wiring) merged to master — M5 closed 2 more issues (130→132 closed).
- Apparent completion percentages dropped across M3-M8 due to scope expansion outpacing closures: M3 73%→48%, M4 67%→53%, M5 71%→59%, M6 29%→19%, M7 48%→40%, M8 47%→45%.
- Critical UAT bugs filed include: #5467 (GRAPH actor subgraph nodes stub-only — Critical), #5479 (GitWorktreeSandbox merge conflict not surfaced — Critical), #5489 (E2E test missing plan diff step — Critical), #5506 (ToolRunner falls through to host on CONTAINER_REF — Critical), and 2,540+ additional UAT spec compliance bugs.
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
- 178 open PRs include multiple timeline update attempts (PRs #5448, #5214, #5185, #5085, #5578) and feature/fix PRs (#5271 ACMS ProjectIndexer, #5276 context settings defaults, #5286 orchestrator scaling to 32 workers).
#### Milestone forecast
@@ -5248,56 +5249,56 @@ Deadline risk: CRITICAL
| Milestone | Target -> ETA | Delta | Risk |
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-15 | +78d | CRITICAL — 147 open issues; 62% complete (scope grew 320→387, +67 new issues) |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-20 | +79d | CRITICAL — 83 open issues; 56% complete (scope grew 161→191, +30 new issues) |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-10 | +65d | HIGH — 57 open issues; 69% complete (scope grew 183→187) |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-07-15 | +127d | CRITICAL — 519 open issues; 27% complete (scope grew 638→711, +73 new issues) |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-05 | +69d | HIGH — 163 open issues; 47% complete |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-20 | N/A | HIGH — 458 open issues; 47% complete (scope grew 855→880) |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-10 | N/A | HIGH — 306 open issues; 29% complete; 2861 total open bugs |
| M2 (v3.1.0) | (2026-02-22) -> ETA 2026-04-15 | +52d | LOW — 2 open issues; 98% complete (nearly done) |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-25 | +88d | CRITICAL — 266 open issues; 48% complete (scope expanded 320→514) |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-20 | +79d | CRITICAL — 95 open issues; 53% complete (scope expanded 161→203) |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-18 | +73d | HIGH — 91 open issues; 59% complete (scope expanded 183→223; PRs #4219, #4218 merged) |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-08-20 | +162d | CRITICAL — 827 open issues; 19% complete (scope expanded 638→1020) |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-25 | +89d | HIGH — 222 open issues; 40% complete (scope expanded 312→372) |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-28 | N/A | HIGH — 513 open issues; 45% complete (scope expanded 855→935) |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-20 | N/A | MEDIUM — 335 open issues; 28% complete |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-10 | MEDIUM | 57 open issues in v3.4.0; scope grew +4 |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-20 | CRITICAL | 83 open issues in v3.3.0; scope grew +30; UAT spec compliance bugs ongoing |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-15 | CRITICAL | 147 open issues in v3.2.0; scope grew +67; agent-driven expansion outpacing closures |
| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | 2861 open bugs (+1983 in one day!); 145 open PRs need review |
| Track T (Testing) | Active | Ongoing | HIGH | 145 open PRs need review; UAT/bug-hunter agents filing bugs at high velocity |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-18 | HIGH | 91 open issues in v3.4.0; PRs #4219 (ACMS) and #4218 (checkpoint) merged; UAT bugs #5479, #5482 |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-20 | CRITICAL | 95 open issues in v3.3.0; UAT bugs #5467 (GRAPH subgraph stub), #5475 (actor version field) |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-25 | CRITICAL | 266 open issues in v3.2.0; scope expanded +194 new issues; #5489 (E2E missing plan diff) |
| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | ~3,422 open bugs (tripled from ~878); UAT pool filing at very high velocity |
| Track T (Testing) | Active | Ongoing | HIGH | 178 open PRs need review; #5506 (ToolRunner CONTAINER_REF fallthrough) critical |
#### Developer forecast
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|------|-------------------|--------------|------|-------|
| Jeff | -24d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight; PR review |
| Luis | -24d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool; bug triage |
| Hamza | -24d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews |
| Aditya | -24d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
| Brent | -24d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 2861 open bugs triage |
| Jeff | -24d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight; 178 open PRs |
| Luis | -24d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool; UAT bug triage |
| Hamza | -24d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PRs #4219 and #4218 merged |
| Aditya | -24d behind | active | HIGH | M5 features; TDD counterparts; domain model work; ACMS ProjectIndexer (#5271) |
| Brent | -24d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; ~3,422 open bugs triage |
| Rui | -24d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
| Mike/Brian | N/A | standby | LOW | Infrastructure support |
#### Task inventory
Milestone per developer as of Day 99 (2026-04-09).
Milestone per developer as of Day 99 cycle-5 (2026-04-09).
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 147 open | 240/387 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 83 open | 108/191 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 57 open | 130/187 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 519 open | 192/711 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 163 open | 150/313 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 458 open | 422/880 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 306 open | 129/435 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1733 open** | **1467/3200** |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 (2 new open) |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 266 open | 248/514 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 95 open | 108/203 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 91 open | 132/223 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 827 open | 193/1020 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 222 open | 150/372 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 513 open | 422/935 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 335 open | 130/465 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~2322 open** | **1489/3811 closed** |
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 99 (2026-04-09). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues at high velocity. Bug count exploded from ~878 to ~2861 (+1983) due to UAT pool, bug-hunter, and spec-compliance agents filing issues at unprecedented rate. M3 scope grew 320→387 (+67), M4 grew 161→191 (+30), M5 grew 183→187 (+4), M6 grew 638→711 (+73), M8 grew 855→880 (+25). M9 now tracked: 129/435 closed (29%).
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 99 cycle-5 (2026-04-09). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues at very high velocity across all milestones. Scope expanded significantly: M2 (+2), M3 (+194), M4 (+42), M5 (+40), M6 (+382), M7 (+60), M8 (+80), M9 (new: 465 total). Open bugs tripled from ~878 to ~3,422 due to UAT pool filing spec compliance issues at high velocity. Open PRs grew from 1 to 178 (+177 new PRs). PRs #4219 (ACMS indexing) and #4218 (checkpoint wiring) merged — M5 closed 2 more issues.
#### Story point allocation