docs(timeline): update schedule adherence Day 99 (2026-04-09) cycle-6
- Update today markers in both Gantt charts to 2026-04-09 - Update footer: ~3615 open bugs, 183 open PRs, Session 4 active - Update GANTT CHART UPDATE LOG to Day 99 with scope expansion details - Update risk register: M3 47%, M4 50%, M5 57%, M6 19%, M7 39%, M8 45% - Update legend color key today marker to 2026-04-09 - Update Schedule Risk Summary with Day 99 data - Update critical path blockers with current scope expansion info - Append Day 99 schedule adherence entry with full milestone/track/developer/task/SP tables - Key changes: massive scope expansion (M3 320->526, M6 638->1040), open bugs ~878->~3615, open PRs 1->183
This commit is contained in:
+120
-26
@@ -10,24 +10,24 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
|
||||
@startgantt
|
||||
|
||||
title CleverAgents Core — Epic-Level Project Schedule
|
||||
footer Generated 2026-04-08 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~878 open bugs | 1 open PR | Session 4 active
|
||||
footer Generated 2026-04-09 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3615 open bugs | 183 open PRs | Session 4 active
|
||||
|
||||
Project starts 2026-02-03
|
||||
saturday are closed
|
||||
sunday are closed
|
||||
printscale weekly zoom 2
|
||||
|
||||
today is 2026-04-08
|
||||
today is 2026-04-09
|
||||
today is colored in #FF6666
|
||||
|
||||
' ================================================================
|
||||
' GANTT CHART UPDATE LOG (Day 98 — 2026-04-08)
|
||||
' Changes: Day 98 refresh. New build session #4799 launched 2026-04-08.
|
||||
' Open PRs: 108→1 (massive merge wave). Open bugs: ~878 (stable).
|
||||
' M3 73% (235/320), M4 67% (108/161), M5 71% (130/183), M6 29% (188/638, scope expanded!),
|
||||
' M7 48% (150/312), M8 47% (403/855).
|
||||
' Progress since Day 96: M3 +8%, M4 +7%, M5 +3%, M7 +5%, M8 +1%.
|
||||
' M6 scope expanded massively: 327→638 total issues (+311 new issues added).
|
||||
' GANTT CHART UPDATE LOG (Day 99 — 2026-04-09)
|
||||
' Changes: Day 99 refresh. Session 4 active with 32 parallel workers.
|
||||
' Open PRs: 1→183 (new PRs opened by agents). Open bugs: ~878→~3615 (massive UAT expansion).
|
||||
' M3 47% (248/526), M4 50% (108/216), M5 57% (133/234), M6 19% (197/1040, scope expanded!),
|
||||
' M7 39% (150/381), M8 45% (422/935), M9 28% (130/466).
|
||||
' Massive scope expansion across all milestones due to agent-driven issue creation.
|
||||
' M6 grew from 638→1040 total issues (+402 new). M3 grew from 320→526 (+206 new).
|
||||
' Session 4 active. Session tracker issue: #4799.
|
||||
' ================================================================
|
||||
|
||||
@@ -400,14 +400,14 @@ legend right
|
||||
| v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs |
|
||||
| v3.6.0 | Mar 27 | 2 | 100 | Deferred work |
|
||||
----
|
||||
**Risk Register (Day 96 — 2026-04-06)**
|
||||
**Risk Register (Day 99 — 2026-04-09)**
|
||||
|= Epic |= Completion |= Risk |= Blocker |
|
||||
| M3 (#357) | 65% | **CRITICAL** | 131 open issues in v3.2.0 |
|
||||
| M4 (#358) | 60% | **CRITICAL** | 74 open issues in v3.3.0 |
|
||||
| M5 (#359) | 68% | **HIGH** | 63 open issues in v3.4.0 |
|
||||
| M6 (#360) | 55% | **HIGH** | 147 open issues in v3.5.0 |
|
||||
| M7 (#361) | 43% | **HIGH** | 198 open issues in v3.6.0 |
|
||||
| M8 (#362) | 46% | **HIGH** | 499 open issues in v3.7.0 (agent expansion) |
|
||||
| M3 (#357) | 47% | **CRITICAL** | 278 open issues in v3.2.0 (scope expanded +206) |
|
||||
| M4 (#358) | 50% | **CRITICAL** | 108 open issues in v3.3.0 (scope expanded) |
|
||||
| M5 (#359) | 57% | **CRITICAL** | 101 open issues in v3.4.0 (scope expanded) |
|
||||
| M6 (#360) | 19% | **CRITICAL** | 843 open issues in v3.5.0 (scope expanded +402) |
|
||||
| M7 (#361) | 39% | **HIGH** | 231 open issues in v3.6.0 (scope expanded) |
|
||||
| M8 (#362) | 45% | **HIGH** | 513 open issues in v3.7.0 (agent expansion) |
|
||||
| SEC (#363) | 28% | **HIGH** | 336 open issues in v3.8.0 (agent expansion) |
|
||||
----
|
||||
**Color Key**
|
||||
@@ -416,11 +416,11 @@ legend right
|
||||
| <back:LightSkyBlue> </back> | In Progress |
|
||||
| <back:#E8E8E8> </back> | Not Started |
|
||||
| <back:Gold> <> </back> | Milestone Target |
|
||||
| <back:#FF6666> | </back> | Today (2026-04-06) |
|
||||
| <back:#FF6666> | </back> | Today (2026-04-09) |
|
||||
----
|
||||
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
|
||||
~1649 total story points | ~3300 estimated hours
|
||||
**~878 open bugs — 108 open PRs — Session 3 active (16 workers, ~71 agents)**
|
||||
**~3615 open bugs — 183 open PRs — Session 4 active (32 workers)**
|
||||
end legend
|
||||
|
||||
@endgantt
|
||||
@@ -444,7 +444,7 @@ saturday are closed
|
||||
sunday are closed
|
||||
printscale weekly zoom 2
|
||||
|
||||
today is 2026-04-08
|
||||
today is 2026-04-09
|
||||
today is colored in #FF6666
|
||||
|
||||
<style>
|
||||
@@ -2290,19 +2290,19 @@ Items without an assigned milestone represent backlog work to be addressed after
|
||||
|
||||
### Schedule Risk Summary
|
||||
|
||||
As of Day 96 (2026-04-06), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **108** (down from 183 — 75 PRs merged/closed!). Open bugs at **~878** (stable). M8 (v3.7.0) at **46% complete** (418/917 closed). M9 (v3.8.0) at **28% complete** (131/467 closed). Session tracker: #3775. Critical path: PR #3774 (Click 8.2+ fix) must be merged; 108 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 46% with 499 issues remaining; ~878 open bugs need TDD counterparts and systematic triage.
|
||||
As of Day 99 (2026-04-09), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 4 is active with 32 parallel workers**. Open PRs now at **183**. Open bugs at **~3,615** (massive UAT expansion — agent-driven issue creation). M3 (v3.2.0) at **47% complete** (248/526 closed — scope expanded +206 issues). M4 (v3.3.0) at **50% complete** (108/216 closed). M5 (v3.4.0) at **57% complete** (133/234 closed). M6 (v3.5.0) at **19% complete** (197/1040 closed — scope expanded massively +402 issues). M7 (v3.6.0) at **39% complete** (150/381 closed). M8 (v3.7.0) at **45% complete** (422/935 closed). M9 (v3.8.0) at **28% complete** (130/466 closed). Session tracker: #4799. Critical path: massive scope expansion across all milestones; 183 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; ~3,615 open bugs need TDD counterparts and systematic triage.
|
||||
|
||||
**Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry.
|
||||
|
||||
**Day 53 Session 3 actions**: (a) 16 parallel workers started. (b) 73+ PRs merged including ACMS UKO runtime (#1312), PermissionsScreen TUI (#1307), actor thought blocks (#1298), DatabaseResourceHandler (#1293), ACMS pipeline Phase 2 (#1287), DevcontainerHandler (#1286), async audit (#1279), serve CLI (#1272), LSP hover/definitions (#1240), domain event wiring (#1215), plan prompt command (#1212), M6 E2E tests (#1277), @tdd_expected_fail cleanup (#1229), persona export/import (#1338), first-run experience (#1391), session export/import (#1392). (c) UAT supervisor fleet (cycles 11-131) launched — discovered 100+ spec compliance bugs across CLI rich output, YAML config handling, and actor compiler. (d) Security bug-hunt PRs opened: #1412 (concurrency), #1409 (error handling), #1419 (hardcoded secrets). (e) Late-day: 4 more PRs merged (#1498, #1481, #1479, #1338), 18 new fix PRs opened (#1506-#1517) targeting UAT findings. (f) End-of-day CLI fix wave: 18 more PRs merged (#1574, #1573, #1570, #1569, #1567, #1566, #1565, #1563, #1562, #1558, #1556, #1554 and others) — open bugs reduced from **143 to 6**, open PRs at **74**.
|
||||
|
||||
**Critical path blockers** (ranked):
|
||||
1. **PR #3774 must be fixed and merged** — Click 8.2+ compatibility fix with CI failures in push-validation and coverage. Blocks all milestone work.
|
||||
2. **108 open PRs need review** — significant reduction from 183 (75 PRs merged/closed on Day 96). Continued review velocity needed.
|
||||
3. **~878 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Stable at ~878.
|
||||
4. **M3-M7 backlog** — 131+74+63+147+198 open issues across M3-M7. Progress made: M3 +4%, M4 +3%, M5 +4%.
|
||||
5. **M8 (v3.7.0) at 46%** — 499 issues remaining (milestone grew from 880→917). Continued agent-driven expansion.
|
||||
6. **M9 (v3.8.0) at 28%** — 336 issues remaining (milestone grew from 465→467). Continued expansion.
|
||||
1. **Massive scope expansion** — M3 grew from 320→526 (+206), M4 grew to 216, M5 grew to 234, M6 grew from 638→1040 (+402), M7 grew to 381. Completion percentages dropped significantly despite continued closures.
|
||||
2. **183 open PRs need review** — significant increase from 1 open PR on Day 98. Agents opened many new PRs.
|
||||
3. **~3,615 open bugs** — massive increase from ~878 on Day 98. Agent-driven UAT expansion at high velocity.
|
||||
4. **M3-M7 backlog** — 278+108+101+843+231 open issues across M3-M7. All milestones overdue.
|
||||
5. **M8 (v3.7.0) at 45%** — 513 issues remaining (milestone grew from 855→935). Continued agent-driven expansion.
|
||||
6. **M9 (v3.8.0) at 28%** — 336 issues remaining. Continued expansion.
|
||||
|
||||
**Spec changes impact assessment (Day 31)**: ACP→A2A rename affects 10 source files, 13 classes, 640+ test references across 22 files. Zero A2A code exists — migration not started. All open PRs that touch ACP modules will need additional rebase work after #688/#689 merge. TUI spec adds ~1,500 lines with 18 ASCII mockups defining Textual-based UI — PR #667 was a placeholder that predates this spec. Server architecture adopts JSON-RPC 2.0 standard — PR #676 used custom protocol, now obsolete.
|
||||
|
||||
@@ -5223,3 +5223,97 @@ Story points per developer per milestone.
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
|
||||
|
||||
### 2026-04-09 (Day 99)
|
||||
|
||||
**Summary**
|
||||
|
||||
Status: Behind 20+d
|
||||
Deadline risk: CRITICAL
|
||||
|
||||
**Notes**
|
||||
|
||||
- Day 99 update (2026-04-09). Session 4 active (issue #4799) with 32 parallel workers targeting v3.2.0–v3.7.0 completion.
|
||||
- Massive scope expansion across all milestones since Day 98: M3 grew from 320→526 (+206 new issues), M4 grew to 216, M5 grew to 234, M6 grew from 638→1040 (+402 new issues), M7 grew to 381, M8 grew from 855→935 (+80 new issues).
|
||||
- Completion percentages dropped significantly due to scope expansion despite continued issue closures: M3 73%→47%, M4 67%→50%, M5 71%→57%, M6 29%→19%, M7 48%→39%, M8 47%→45%.
|
||||
- Open PRs surged from 1 to 183 as agents opened new fix/feature/docs PRs across all milestones.
|
||||
- Open bugs increased dramatically from ~878 to ~3,615 — agent-driven UAT expansion at high velocity. Bug count grew by ~2,737 in one day.
|
||||
- Milestone closures (absolute): M3 235→248 (+13 closed), M4 108→108 (stable), M5 130→133 (+3 closed), M6 188→197 (+9 closed), M7 150→150 (stable), M8 403→422 (+19 closed), M9 118→130 (+12 closed).
|
||||
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
|
||||
- Multiple timeline update PRs already open for Day 99 (#5085, #5185, #5214, #5578, #6213) — this is an additional cycle-6 refresh with latest Forgejo data.
|
||||
- Session 4 supervisor fleet continues autonomous operation. UAT pool, PR reviewer pool, implementation pool, and spec updater agents all running.
|
||||
|
||||
|
||||
#### Milestone forecast
|
||||
|
||||
| Milestone | Target -> ETA | Delta | Risk |
|
||||
|-----------|---------------|-------|------|
|
||||
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
|
||||
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-15 | +78d | CRITICAL — 278 open issues; 47% complete (scope expanded 320→526) |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-20 | +79d | CRITICAL — 108 open issues; 50% complete (scope expanded to 216) |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-20 | +75d | CRITICAL — 101 open issues; 57% complete (scope expanded to 234) |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-08-01 | +144d | CRITICAL — 843 open issues; 19% complete (scope expanded 638→1040) |
|
||||
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-20 | +84d | HIGH — 231 open issues; 39% complete (scope expanded to 381) |
|
||||
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-20 | N/A | HIGH — 513 open issues; 45% complete (scope expanded 855→935) |
|
||||
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-01 | N/A | MEDIUM — 336 open issues; 28% complete |
|
||||
|
||||
#### Track forecast
|
||||
|
||||
| Track | Status | ETA | Risk | Blocking |
|
||||
|-------|--------|-----|------|----------|
|
||||
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
|
||||
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-20 | HIGH | 101 open issues in v3.4.0; scope expanded to 234 total |
|
||||
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-20 | CRITICAL | 108 open issues in v3.3.0; scope expanded to 216 total |
|
||||
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-15 | CRITICAL | 278 open issues in v3.2.0; scope expanded 320→526 |
|
||||
| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | ~3,615 open bugs; massive agent-driven UAT expansion (+2,737 in one day) |
|
||||
| Track T (Testing) | Active | Ongoing | HIGH | 183 open PRs need review; UAT pool supervisor active (#4799) |
|
||||
|
||||
#### Developer forecast
|
||||
|
||||
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|
||||
|------|-------------------|--------------|------|-------|
|
||||
| Jeff | -24d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight; 183 open PRs |
|
||||
| Luis | -24d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool |
|
||||
| Hamza | -24d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews |
|
||||
| Aditya | -24d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
|
||||
| Brent | -24d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; ~3,615 open bugs triage |
|
||||
| Rui | -24d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
|
||||
| Mike/Brian | N/A | standby | LOW | Infrastructure support |
|
||||
|
||||
#### Task inventory
|
||||
|
||||
Milestone per developer as of Day 99 (2026-04-09).
|
||||
|
||||
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
|
||||
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 278 open | 248/526 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 108 open | 108/216 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 101 open | 133/234 |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 843 open | 197/1040 |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 231 open | 150/381 |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 513 open | 422/935 |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 336 open | 130/466 |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~2410 open** | **1484/3950** |
|
||||
|
||||
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 99 (2026-04-09). Massive scope expansion across all milestones due to agent-driven issue creation. M3 grew from 320→526 (+206), M6 grew from 638→1040 (+402), M8 grew from 855→935 (+80). Open bugs surged from ~878 to ~3,615 (+2,737 new UAT bugs). Open PRs surged from 1 to 183 as agents opened new fix/feature/docs PRs.
|
||||
|
||||
#### Story point allocation
|
||||
|
||||
Story points per developer per milestone.
|
||||
|
||||
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~172 SP |
|
||||
| M2 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~208 SP |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~104 SP |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~126 SP |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~129 SP |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~100 SP |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
|
||||
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
|
||||
|
||||