freemo c8f822cd79 docs(timeline): update schedule adherence Day 55 (2026-04-04)
- Append Day 55 (2026-04-04) schedule adherence entry with full
  milestone/track/developer/task/story-point tables
- PRIORITY: Issue #2597 (CI quality gates fix) flagged as CRITICAL
  blocker — master CI broken (lint, unit_tests, e2e_tests FAILING),
  ALL 75 open PRs blocked; PR #2629 open and in review
- Update gantt chart today marker to 2026-04-04 (both charts)
- Update gantt chart update log to Day 55 with current stats
- Update open PR count: 64 → 75; open bugs: 389 (stable)
- Update milestone completion from Forgejo API:
  M3 71% (220/311), M4 76% (100/132), M5 75% (126/167),
  M6 55% (127/229), M7 17% (103/596), M8 27% (105/387)
- Update Current Status Summary to Day 55 with #2597 CRITICAL warning
- M7 (v3.6.0) milestone expanded dramatically: 213→596 total issues
- Deadline risk elevated to CRITICAL due to CI blockage