- Append Day 55 (2026-04-04) schedule adherence entry with full milestone/track/developer/task/story-point tables - PRIORITY: Issue #2597 (CI quality gates fix) flagged as CRITICAL blocker — master CI broken (lint, unit_tests, e2e_tests FAILING), ALL 75 open PRs blocked; PR #2629 open and in review - Update gantt chart today marker to 2026-04-04 (both charts) - Update gantt chart update log to Day 55 with current stats - Update open PR count: 64 → 75; open bugs: 389 (stable) - Update milestone completion from Forgejo API: M3 71% (220/311), M4 76% (100/132), M5 75% (126/167), M6 55% (127/229), M7 17% (103/596), M8 27% (105/387) - Update Current Status Summary to Day 55 with #2597 CRITICAL warning - M7 (v3.6.0) milestone expanded dramatically: 213→596 total issues - Deadline risk elevated to CRITICAL due to CI blockage