freemo 3fe1974249 docs(timeline): update schedule adherence Day 53 (2026-04-02)
- Updated Day 53 entry with end-of-day data (32 PRs merged today)
- Open PRs: 119 → 86 (down 33)
- Open bugs: 40 → 65 (up 25, UAT testing discovered new issues)
- Milestone progress: M3 74%→79%, M4 74%→75%, M5 78%→87%, M6 69%→74%, M7 61%→71%, M8 50%→54%
- Updated gantt chart completion percentages and risk register
- Updated Current Status Summary with end-of-day figures
- Added Day 53 merge wave bullet to What Has Been Completed
- Updated What Remains To Be Done with current open counts
- Updated Schedule Risk Summary with UAT findings