forked from cleveragents/cleveragents-core
3fe1974249
- Updated Day 53 entry with end-of-day data (32 PRs merged today) - Open PRs: 119 → 86 (down 33) - Open bugs: 40 → 65 (up 25, UAT testing discovered new issues) - Milestone progress: M3 74%→79%, M4 74%→75%, M5 78%→87%, M6 69%→74%, M7 61%→71%, M8 50%→54% - Updated gantt chart completion percentages and risk register - Updated Current Status Summary with end-of-day figures - Added Day 53 merge wave bullet to What Has Been Completed - Updated What Remains To Be Done with current open counts - Updated Schedule Risk Summary with UAT findings