HAL9000 82b4401e44 docs(timeline): update schedule adherence Day 102 (2026-04-12)
Refresh Day 102 entries using Forgejo telemetry to capture scope expansion,
milestone progress, and active session data.

- Update today marker to 2026-04-12 in both Gantt charts
- Update Gantt update log for Day 102 (cycle 1)
- Update footer date and open PR count (225→257)
- Update Current Status Summary for Day 102
- Append Day 102 schedule adherence tables for milestones and tracks
- Note key merges: dual-account PR review arch, curl-only reviewer,
  spec Section 22, ATM centralization, supervisor fresh-launch fix
- Milestone scope growth: M3 770→948, M4 220→233, M5 313→345,
  M6 1085→1181, M7 400→433, M8 944→956, M9 475→489

ISSUES CLOSED: #7912