# Implementation Timeline ### Gantt Charts #### Epic-Level Schedule The following chart shows all milestones across the CleverAgents project with current completion status, risk levels, and schedule adherence tracking. Updated Day 103 Cycle 3 (2026-04-13 ~22:02 UTC) by AUTO-TIME supervisor. ```kroki-plantuml @startgantt title CleverAgents Core — Milestone Schedule (Day 103, Cycle 3) footer Generated 2026-04-13 ~22:02 UTC | Day 103 | Cycle 3 | AUTO-TIME supervisor active Project starts 2026-02-03 saturday are closed sunday are closed printscale weekly zoom 2 today is 2026-04-13 today is colored in #FF6666 ' ============================================================ ' GANTT CHART UPDATE LOG (Day 103 Cycle 3 — 2026-04-13 ~22:02 UTC) ' Changes: Cycle 3 refresh. Scope expansion detected in 60-min window. ' Tracking issue: #8519 ' M1 v3.0.0: CLOSED 100% (163/163) ' M2 v3.1.0: CLOSED 94.7% (108/113, 5 open — was 3, scope expanding!) ' M3 v3.2.0: 25.1% (269/1071, 802 open) CRITICAL — 46 days overdue ' M4 v3.3.0: 41.0% (109/266, 157 open) CRITICAL — 42 days overdue ' M5 v3.4.0: 36.5% (139/381, 242 open) HIGH — 38 days overdue ' M6 v3.5.0: 16.8% (212/1264, 1052 open) CRITICAL — 34 days overdue ' M7 v3.6.0: 32.6% (152/466, 314 open) HIGH — 16 days overdue ' M8 v3.7.0: 42.6% (427/1001, 574 open) HIGH — no deadline ' M9 v3.8.0: 27.1% (133/491, 358 open) HIGH — no deadline ' v3.9.0: 19.0% (4/21, 17 open) LOW — no deadline ' ALERT: +110 new open issues in 60 min, only +2 closed! ' CI not running on master since 2026-03-14 (issue #8508). ' AUTO-TIME supervisor active. Tracking issue #8519. ' ============================================================ -- Completed Milestones -- [v3.0.0 M1: Local Source-Code Workflow] lasts 10 days and is 100% complete [v3.0.0 M1: Local Source-Code Workflow] is colored in #00AA00 note bottom CLOSED 2026-03-16 163/163 issues closed (100%) Due: 2026-02-15 (29 days late) end note [v3.1.0 M2: Actor Compiler + LLM Integration] lasts 7 days and is 95% complete [v3.1.0 M2: Actor Compiler + LLM Integration] is colored in #AACC00 note bottom CLOSED 2026-03-16 (5 open issues remain — was 3!) 108/113 issues closed (94.7%) Due: 2026-02-22 (22 days late) ALERT: Scope expanding in closed milestone end note -- Active Milestones (CRITICAL RISK) -- [v3.2.0 M3: Decisions + Validations + Invariants] lasts 21 days and is 25% complete [v3.2.0 M3: Decisions + Validations + Invariants] is colored in #FF0000 note bottom CRITICAL RISK — 802 open issues (was 776, +26 in 60 min) 269/1071 issues closed (25.1%) Due: 2026-02-26 (46 days overdue) end note [v3.3.0 M4: Corrections + Subplans + Checkpoints] lasts 14 days and is 41% complete [v3.3.0 M4: Corrections + Subplans + Checkpoints] is colored in #FF4400 note bottom CRITICAL RISK — 157 open issues (was 148, +9 in 60 min) 109/266 issues closed (41.0%) Due: 2026-03-02 (42 days overdue) end note [v3.5.0 M6: Autonomy Hardening] lasts 14 days and is 17% complete [v3.5.0 M6: Autonomy Hardening] is colored in #FF0000 note bottom CRITICAL RISK — 1052 open issues (was 1032, +20 in 60 min) 212/1264 issues closed (16.8%) Due: 2026-03-10 (34 days overdue) end note -- Active Milestones (HIGH RISK) -- [v3.4.0 M5: ACMS v1 + Context Scaling] lasts 14 days and is 37% complete [v3.4.0 M5: ACMS v1 + Context Scaling] is colored in #FF6600 note bottom HIGH RISK — 242 open issues (was 233, +9 in 60 min) 139/381 issues closed (36.5%) Due: 2026-03-06 (38 days overdue) end note [v3.6.0 M7: Advanced Concepts] lasts 18 days and is 33% complete [v3.6.0 M7: Advanced Concepts] is colored in #FF8800 note bottom HIGH RISK — 314 open issues (was 296, +18 in 60 min) 152/466 issues closed (32.6%) Due: 2026-03-28 (16 days overdue) end note [v3.7.0 M8: TUI Implementation] lasts 21 days and is 43% complete [v3.7.0 M8: TUI Implementation] is colored in #FF8800 note bottom HIGH RISK — 574 open issues (was 548, +26 in 60 min) 427/1001 issues closed (42.6%) No deadline assigned end note -- Future Milestones -- [v3.8.0 M9: Server Implementation] lasts 21 days and is 27% complete [v3.8.0 M9: Server Implementation] is colored in #FFAA00 note bottom HIGH RISK — 358 open issues 133/491 issues closed (27.1%) No deadline assigned end note [v3.9.0: Documentation + Feature Updates] lasts 7 days and is 19% complete [v3.9.0: Documentation + Feature Updates] is colored in #FFCC00 note bottom LOW RISK — 17 open issues 4/21 issues closed (19.0%) No deadline assigned end note @endgantt ``` ## Schedule Adherence | Date | Day | Cycle | Milestone | Planned % | Actual % | Delta | Risk | Notes | |------|-----|-------|-----------|-----------|----------|-------|------|-------| | 2026-02-15 | D12 | — | v3.0.0 M1 | 100% | 0% | -100% | CRITICAL | M1 not started by due date | | 2026-02-22 | D19 | — | v3.1.0 M2 | 100% | 0% | -100% | CRITICAL | M2 not started by due date | | 2026-02-26 | D23 | — | v3.2.0 M3 | 100% | 0% | -100% | CRITICAL | M3 not started by due date | | 2026-03-02 | D27 | — | v3.3.0 M4 | 100% | 0% | -100% | CRITICAL | M4 not started by due date | | 2026-03-06 | D31 | — | v3.4.0 M5 | 100% | 0% | -100% | CRITICAL | M5 not started by due date | | 2026-03-10 | D35 | — | v3.5.0 M6 | 100% | 0% | -100% | CRITICAL | M6 not started by due date | | 2026-03-16 | D41 | — | v3.0.0 M1 | — | 100% | — | DONE | M1 closed (29 days late) | | 2026-03-16 | D41 | — | v3.1.0 M2 | — | 97.3% | — | PARTIAL | M2 closed with 3 open issues (22 days late) | | 2026-03-28 | D53 | — | v3.6.0 M7 | 100% | 0% | -100% | CRITICAL | M7 not started by due date | | 2026-04-09 | D99 | — | v3.2.0 M3 | 100% | 24.8% | -75.2% | CRITICAL | Day 99: 260/1047 closed | | 2026-04-09 | D99 | — | v3.3.0 M4 | 100% | 41.2% | -58.8% | CRITICAL | Day 99: 108/262 closed | | 2026-04-09 | D99 | — | v3.4.0 M5 | 100% | 36.9% | -63.1% | CRITICAL | Day 99: 138/374 closed | | 2026-04-09 | D99 | — | v3.5.0 M6 | 100% | 16.7% | -83.3% | CRITICAL | Day 99: 208/1247 closed | | 2026-04-09 | D99 | — | v3.6.0 M7 | 100% | 33.5% | -66.5% | CRITICAL | Day 99: 151/451 closed | | 2026-04-09 | D99 | — | v3.7.0 M8 | — | 43.6% | — | HIGH | Day 99: 426/977 closed | | 2026-04-10 | D100 | — | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Day 100: 269/1045 closed | | 2026-04-10 | D100 | — | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Day 100: 109/257 closed | | 2026-04-10 | D100 | — | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Day 100: 139/372 closed | | 2026-04-10 | D100 | — | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Day 100: 210/1242 closed | | 2026-04-10 | D100 | — | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Day 100: 152/448 closed | | 2026-04-10 | D100 | — | v3.7.0 M8 | — | 43.8% | — | HIGH | Day 100: 427/975 closed | | 2026-04-13 | D103 | C2 | v3.2.0 M3 | 100% | 25.7% | -74.3% | CRITICAL | Cycle 2: 269/1045 closed, 776 open | | 2026-04-13 | D103 | C2 | v3.3.0 M4 | 100% | 42.4% | -57.6% | CRITICAL | Cycle 2: 109/257 closed, 148 open | | 2026-04-13 | D103 | C2 | v3.4.0 M5 | 100% | 37.4% | -62.6% | CRITICAL | Cycle 2: 139/372 closed, 233 open | | 2026-04-13 | D103 | C2 | v3.5.0 M6 | 100% | 16.9% | -83.1% | CRITICAL | Cycle 2: 210/1242 closed, 1032 open | | 2026-04-13 | D103 | C2 | v3.6.0 M7 | 100% | 33.9% | -66.1% | CRITICAL | Cycle 2: 152/448 closed, 296 open | | 2026-04-13 | D103 | C2 | v3.7.0 M8 | — | 43.8% | — | HIGH | Cycle 2: 427/975 closed, 548 open | | 2026-04-13 | D103 | C2 | v3.8.0 M9 | — | 27.1% | — | HIGH | Cycle 2: 133/491 closed, 358 open | | 2026-04-13 | D103 | C2 | v3.9.0 | — | 19.0% | — | LOW | Cycle 2: 4/21 closed, 17 open | | 2026-04-13 | D103 | C3 | v3.1.0 M2 | — | 94.7% | — | ALERT | Cycle 3: 108/113 closed, 5 open (scope expanding in closed MS!) | | 2026-04-13 | D103 | C3 | v3.2.0 M3 | 100% | 25.1% | -74.9% | CRITICAL | Cycle 3: 269/1071 closed, 802 open (+26 in 60 min) | | 2026-04-13 | D103 | C3 | v3.3.0 M4 | 100% | 41.0% | -59.0% | CRITICAL | Cycle 3: 109/266 closed, 157 open (+9 in 60 min) | | 2026-04-13 | D103 | C3 | v3.4.0 M5 | 100% | 36.5% | -63.5% | CRITICAL | Cycle 3: 139/381 closed, 242 open (+9 in 60 min) | | 2026-04-13 | D103 | C3 | v3.5.0 M6 | 100% | 16.8% | -83.2% | CRITICAL | Cycle 3: 212/1264 closed, 1052 open (+20 in 60 min) | | 2026-04-13 | D103 | C3 | v3.6.0 M7 | 100% | 32.6% | -67.4% | CRITICAL | Cycle 3: 152/466 closed, 314 open (+18 in 60 min) | | 2026-04-13 | D103 | C3 | v3.7.0 M8 | — | 42.6% | — | HIGH | Cycle 3: 427/1001 closed, 574 open (+26 in 60 min) | | 2026-04-13 | D103 | C3 | v3.8.0 M9 | — | 27.1% | — | HIGH | Cycle 3: 133/491 closed, 358 open (unchanged) | ## Scope Expansion Alert (Cycle 2 → Cycle 3, ~60 min window) **CRITICAL**: In the 60-minute window between Cycle 2 and Cycle 3, all active milestones gained new open issues with minimal closures: | Milestone | Open C2 | Open C3 | Delta | Closed C2 | Closed C3 | Delta | |-----------|---------|---------|-------|-----------|-----------|-------| | v3.1.0 M2 | 3 | 5 | **+2** | 108 | 108 | 0 | | v3.2.0 M3 | 776 | 802 | **+26** | 269 | 269 | 0 | | v3.3.0 M4 | 148 | 157 | **+9** | 109 | 109 | 0 | | v3.4.0 M5 | 233 | 242 | **+9** | 139 | 139 | 0 | | v3.5.0 M6 | 1032 | 1052 | **+20** | 210 | 212 | +2 | | v3.6.0 M7 | 296 | 314 | **+18** | 152 | 152 | 0 | | v3.7.0 M8 | 548 | 574 | **+26** | 427 | 427 | 0 | **Total new open issues in 60 min: +110** | **Total new closed issues in 60 min: +2** ## Milestone Summaries ### v3.0.0 (M1) — CLOSED - **Status**: Complete - **Closed**: 2026-03-16 (29 days after due date 2026-02-15) - **Issues**: 163/163 closed (100%) - **Notes**: First milestone completed. Established local source-code workflow, git worktree sandbox, SQLite persistence, actor-based LLM path. ### v3.1.0 (M2) — CLOSED (scope expanding!) - **Status**: Closed but scope expanding — 5 open issues (was 3 at Cycle 2) - **Closed**: 2026-03-16 (22 days after due date 2026-02-22) - **Issues**: 108/113 closed (94.7%) — 5 open - **Notes**: Actor compiler and LLM integration complete. Open issue count growing despite milestone closure. LangGraph StateGraph compilation, MCP adapter, tool router operational. ### v3.2.0 (M3) — CRITICAL RISK - **Status**: Open — 46 days overdue (due 2026-02-26) - **Issues**: 269/1071 closed (25.1%) — 802 open (+26 in 60 min) - **Scope**: Massively expanded (was ~300 issues, now 1071 and growing) - **Blockers**: Decision recording system, invariant management, plan correction engine (revert/append modes) - **Key features**: `plan tree`, `plan explain`, `invariant add/list/remove`, `plan correct` - **Notes**: CI not running on master since 2026-03-14. E2E tests deleted (commit 8ea00f5). Scope growing faster than issues are being closed. ### v3.3.0 (M4) — CRITICAL RISK - **Status**: Open — 42 days overdue (due 2026-03-02) - **Issues**: 109/266 closed (41.0%) — 157 open (+9 in 60 min) - **Blockers**: Subplan spawning during execution, parallel subplan execution, three-way merge strategy, checkpoint creation and rollback - **Key features**: `plan rollback`, parallel execution with max_parallel, parent plan tracking - **Notes**: Depends on M3 completion for correction flow. ### v3.4.0 (M5) — HIGH RISK - **Status**: Open — 38 days overdue (due 2026-03-06) - **Issues**: 139/381 closed (36.5%) — 242 open (+9 in 60 min) - **Blockers**: ACMS v1 pipeline, context window management (hot/warm/cold tiers), 10k+ file indexing without timeout - **Key features**: `context list/add/show/clear`, budget enforcement, context assembly CLI - **Notes**: Context scaling is a major technical challenge. Budget constraints (max_file_size, max_total_size). ### v3.5.0 (M6) — CRITICAL RISK - **Status**: Open — 34 days overdue (due 2026-03-10) - **Issues**: 212/1264 closed (16.8%) — 1052 open (+20 in 60 min) - **Scope**: Massively expanded (was ~200 issues, now 1264 and growing) - **Blockers**: A2A facade session/plan lifecycle, event queue pub/sub, guard enforcement, autonomy hardening - **Key features**: Hierarchical decomposition (4+ levels), parallel execution (10+ concurrent), realistic porting task - **Notes**: Server stubs moved to M9 (ADR-047, ADR-048). TUI features moved to M8. Largest milestone by scope. ### v3.6.0 (M7) — HIGH RISK - **Status**: Open — 16 days overdue (due 2026-03-28) - **Issues**: 152/466 closed (32.6%) — 314 open (+18 in 60 min) - **Blockers**: Advanced context strategies, additional LLM backends, container tool execution, pluggable scope chain - **Key features**: ACP→A2A rename, cost/session budgets, safety profiles, E2E workflow spec tests - **Notes**: Advanced concepts milestone. Abstraction layers for TUI/Server included. ### v3.7.0 (M8) — HIGH RISK - **Status**: Open — No deadline assigned - **Issues**: 427/1001 closed (42.6%) — 574 open (+26 in 60 min) - **Blockers**: Textual TUI MainScreen, persona system (YAML-based), reference/command input (@, /, ! modes) - **Key features**: TuiMaterializer A2A integration, session persistence (SQLite), Dracula theme, multi-session tabs - **Notes**: TUI features moved here from M6. Highest absolute completion count (427 closed). ADR-044, ADR-045, ADR-046. ### v3.8.0 (M9) — HIGH RISK - **Status**: Open — No deadline assigned - **Issues**: 133/491 closed (27.1%) — 358 open (unchanged) - **Blockers**: A2A JSON-RPC 2.0 wire format, stdio/HTTP transports, LangGraph Platform RemoteGraph, FastAPI + A2A SDK - **Key features**: Authentication/authorization (API tokens, RBAC), entity sync, PostgreSQL backend, Docker/K8s/Helm - **Notes**: Server implementation. ADR-047 (A2A adoption), ADR-048 (server architecture). No deadline. ### v3.9.0 — LOW RISK - **Status**: Open — No deadline assigned - **Issues**: 4/21 closed (19.0%) — 17 open (unchanged) - **Notes**: Documentation and feature updates. Lowest priority milestone. ## Risk Register | Risk | Severity | Milestones Affected | Status | Mitigation | |------|----------|---------------------|--------|------------| | All active milestones overdue | CRITICAL | M3-M7 | Active | Increase automation, parallel workers | | Scope expanding faster than closing (+110 open in 60 min) | CRITICAL | All | ESCALATING | Scope freeze, prioritization | | CI not running on master (since 2026-03-14) | CRITICAL | All | Open (#8508) | Fix CI trigger configuration | | Massive scope expansion (M3: 1071, M6: 1264 issues) | CRITICAL | M3, M6 | Active | Scope management, prioritization | | 802 open issues in M3 alone | CRITICAL | M3 | Active | Focus automation on M3 | | 1052 open issues in M6 | CRITICAL | M6 | Active | Parallel worker pools | | E2E tests deleted (commit 8ea00f5, issue #8459) | HIGH | All | Open | Restore E2E test suite | | Open PR #8380 unmerged (Day 103 Timeline Update) | MEDIUM | Timeline | Open | Superseded by PR #8582 | | v3.1.0 closed with 5 open issues (growing) | MEDIUM | M2 | ESCALATING | Resolve remaining issues, prevent scope creep | ## Automation Activity Log | Date | Day | Cycle | Agent | Action | |------|-----|-------|-------|--------| | 2026-04-13 | D103 | C1 | AUTO-TIME | Supervisor started, tracking issue #8519 created | | 2026-04-13 | D103 | C2 | AUTO-TIME-1 | Timeline updated on branch auto-time-1-day103-cycle2, PR #8582 created | | 2026-04-13 | D103 | C3 | AUTO-TIME-2 | Timeline updated on branch auto-time-2-day103-cycle3, scope expansion alert added | --- **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor