# Implementation Timeline ### Gantt Charts #### Epic-Level Schedule The following chart shows all 29 epics across 9 legendary workstreams, 7 milestone gates with dependency arrows, cross-workstream connections, developer resource allocation, and a risk register. Milestones are linked to their gating epics via arrows showing what work must complete before each release. ```kroki-plantuml @startgantt title CleverAgents Core — Epic-Level Project Schedule footer Generated 2026-04-17 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3 open bugs | 328 open PRs | Session 4 active Project starts 2026-02-03 saturday are closed sunday are closed printscale weekly zoom 2 today is 2026-04-17 today is colored in #FF6666 ' ================================================================ ' GANTT CHART UPDATE LOG (Day 102 — 2026-04-12) ' Changes: Day 102 refresh (cycle 1). Session 4 active (issue #4799, 32 workers). ' Open PRs: 225→257 (+32 new PRs). Open bugs: ~25→3 (Type/Bug label, major bug-fix wave). ' M3 28% (262/948, scope expanded 770→948), M4 46% (108/233), M5 40% (137/345), ' M6 17% (201/1181, scope expanded 1085→1181), M7 35% (152/433), ' M8 45% (427/956), M9 27% (132/489). v3.9.0 milestone added (13 open, 4 closed). ' Significant bug-fix wave: open bugs dropped from ~25 to 3. ' Open PRs grew from 225 to 257 (+32 new agent-driven PRs). ' ================================================================ ' ================================================================ ' GANTT CHART UPDATE LOG (Day 104 — 2026-04-14) ' Changes: Day 104 refresh (cycle 1). Session 4 active (issue #4799, 32 workers). ' Scope expansion across all milestones since Day 102: ' M3 22.3% (273/1225, scope expanded 948→1225), M4 35.2% (111/315, scope expanded 233→315), ' M5 34.9% (142/407, scope expanded 345→407), M6 16.3% (220/1347, scope expanded 1181→1347), ' M7 31.2% (153/491, scope expanded 433→491), M8 41.2% (428/1038, scope expanded 956→1038), ' M9 26.6% (135/508, scope expanded 489→508), v3.9.0 7.0% (4/57, scope expanded 17→57). ' Completion percentages declining despite ongoing work — scope outpacing closures. ' ================================================================ ' ================================================================ ' GANTT CHART UPDATE LOG (Day 105 — 2026-04-15) ' Changes: Day 105 refresh (cycle 1). Session 5 active (32 workers). ' v3.0.0: 100% CLOSED, v3.1.0: 100% CLOSED. ' v3.2.0: 26% (321/1254), v3.3.0: 36% (117/329), v3.4.0: 37% (158/427), ' v3.5.0: 18% (244/1351), v3.6.0: 33% (162/491), v3.7.0: 42% (437/1040), ' v3.8.0: 29% (145/509), v3.9.0: 41% (24/59). ' Active milestone: v3.2.0 (933 open), v3.5.0 (1,107 open). ' ================================================================ ' ================================================================ ' GANTT CHART UPDATE LOG (Day 107 - 2026-04-17) ' Changes: Day 107 refresh (cycle 1). Session 4 active (issue #4799, 32 workers). ' v3.0.0 CLOSED (100%, 0 open/164 closed), v3.1.0 CLOSED (100%, 0 open/108 closed). ' M3 (v3.2.0) 25.0% (323/1291, 968 open), M4 (v3.3.0) 34.9% (118/338, 220 open), ' M5 (v3.4.0) 35.6% (158/444, 286 open), M6 (v3.5.0) 17.9% (247/1377, 1130 open), ' M7 (v3.6.0) 32.8% (162/494, 332 open), M8 (v3.7.0) 41.9% (438/1046, 608 open), ' M9 (v3.8.0) 28.2% (144/511, 367 open), v3.9.0 37.5% (24/64, 40 open). ' Open PRs: 257->328 (+71). AUTO-BUG-SUP frozen alert (issue #10222). ' ================================================================ ' ================================================================ ' PRE-REBASELINE FOUNDATION (Legendary #370) — Target: v3.0.0 ' Scope: Bug fixes, tests, docs, security from pre-rebaseline era ' Owner: Aditya (primary), Brent (docs) ' Story Points: 26 (all complete except PRE_TEST) ' ================================================================ -- Pre-Rebaseline Foundation (Legendary #370) | v3.0.0 -- [Core Functionality (#26)] as [PRE_CORE] on {Aditya} requires 5 days [PRE_CORE] starts 2026-02-03 [PRE_CORE] is 100% completed [PRE_CORE] is colored in PaleGreen/SeaGreen [Testing Framework (#24)] as [PRE_TEST] on {Aditya} requires 4 days [PRE_TEST] starts 2026-02-03 [PRE_TEST] is 0% completed [PRE_TEST] is colored in #E8E8E8/Silver [Documentation (#27)] as [PRE_DOC] on {Brent} requires 4 days [PRE_DOC] starts 2026-02-03 [PRE_DOC] is 100% completed [PRE_DOC] is colored in PaleGreen/SeaGreen [Bug Fixes (#25)] as [PRE_BUG] on {Aditya} requires 3 days [PRE_BUG] starts 2026-02-03 [PRE_BUG] is 100% completed [PRE_BUG] is colored in PaleGreen/SeaGreen [Security Enhancements (#28)] as [PRE_SEC] on {Aditya} requires 2 days [PRE_SEC] starts 2026-02-03 [PRE_SEC] is 100% completed [PRE_SEC] is colored in PaleGreen/SeaGreen ' ================================================================ ' FOUNDATION & INFRASTRUCTURE (Legendary #371 - DONE) — v3.0.0 ' Scope: Architecture, preserved LangChain work, QA pipeline, traceability ' Owner: Jeff (architecture), Brent (QA), Aditya (traceability) ' Story Points: 32 (all complete) ' ================================================================ -- Foundation & Infrastructure (Legendary #371 - DONE) | v3.0.0 -- [Foundation Phases 0-1 (#346)] as [FOUND] on {Jeff} requires 1 days [FOUND] starts 2026-02-09 [FOUND] is 100% completed [FOUND] is colored in PaleGreen/SeaGreen [Preserved Work (#347)] as [PRES] on {Jeff} requires 2 days [PRES] starts 2026-02-09 [PRES] is 100% completed [PRES] is colored in PaleGreen/SeaGreen [Quality Automation Q0 (#349)] as [QA] on {Brent} requires 2 days [QA] starts 2026-02-09 [QA] is 100% completed [QA] is colored in PaleGreen/SeaGreen [Commit Traceability (#348)] as [TRACE] on {Aditya} requires 2 days [TRACE] starts at [FOUND]'s end [TRACE] is 100% completed [TRACE] is colored in PaleGreen/SeaGreen ' ── v3.0.0 MILESTONE ───────────────────────────────────────── ' Gate: All pre-rebaseline + foundation work ' Deliverables: Domain models, QA pipeline (97% coverage), architecture -- v3.0.0 — Foundation Release (Feb 15) -- [v3.0.0 Release] as [MS1] happens 2026-02-15 ' ================================================================ ' PLAN LIFECYCLE — WORKSTREAM A (Legendary #372) — v3.1.0-v3.4.0 ' Scope: Plan/Action/Session models, persistence, CLI, config service ' Owner: Jeff (lead), Luis (persistence), Brent (testing), Aditya (docs) ' Story Points: 95 ' Critical Path: QA → A1A5 → A6A8 → ... → A9 ' ================================================================ -- Plan Lifecycle — Workstream A (Legendary #372) | v3.1.0 - v3.4.0 -- [Plan A1-A5: Models + Persistence (#350)] as [A1A5] on {Jeff} {Luis} {Brent} {Aditya} requires 5 days [A1A5] starts at [QA]'s end [A1A5] is 100% completed [A1A5] is colored in PaleGreen/SeaGreen [Plan A6-A8: Sessions + Config CLI (#351)] as [A6A8] on {Jeff} {Brent} {Luis} requires 3 days [A6A8] starts at [A1A5]'s end [A6A8] is 100% completed [A6A8] is colored in PaleGreen/SeaGreen [Execution Pipeline + Events (#361)] as [PIPE] on {Jeff} requires 2 days [PIPE] starts 2026-02-18 [PIPE] is 100% completed [PIPE] is colored in PaleGreen/SeaGreen [Config Service A9 (#352)] as [A9] on {Jeff} {Luis} requires 2 days [A9] starts 2026-03-06 [A9] is 0% completed [A9] is colored in #E8E8E8/Silver [Additional CLI Commands (#364)] as [CLI] on {Jeff} {Brent} requires 2 days [CLI] starts 2026-02-23 [CLI] is 100% completed [CLI] is colored in PaleGreen/SeaGreen [Concurrency + Cleanup (#365)] as [CONCUR] on {Luis} requires 2 days [CONCUR] starts 2026-02-23 [CONCUR] is 100% completed [CONCUR] is colored in PaleGreen/SeaGreen ' ================================================================ ' PROJECTS & RESOURCES — WORKSTREAM B (Legendary #373 - DONE) — v3.1.0 ' Scope: Resource registry, project model, sandbox, context policy ' Owner: Jeff (lead), Hamza (sandbox), Brent (testing) ' Story Points: 42 (all complete) ' ================================================================ -- Projects & Resources — Workstream B (Legendary #373 - DONE) | v3.1.0 -- [Projects + Resources B0-B2 (#353)] as [PROJ] on {Jeff} {Hamza} {Brent} requires 5 days [PROJ] starts at [QA]'s end [PROJ] is 100% completed [PROJ] is colored in PaleGreen/SeaGreen ' ── v3.1.0 MILESTONE ───────────────────────────────────────── ' Gate: Plan lifecycle models + Project resources + Actor schema + Exec pipeline ' Deliverables: Plan CRUD, resource registry, actor/skill/tool models -- v3.1.0 — Models + Schema Release (Feb 22) -- [v3.1.0 Release] as [MS2] happens 2026-02-22 ' ================================================================ ' ACTORS, SKILLS & TOOLS — WORKSTREAM C (Legendary #374) — v3.1.0-v3.3.0 ' Scope: Actor YAML, skill resolver, tool runtime, MCP adapter, tool sources ' Owner: Jeff (lead), Aditya (schema/docs), Luis (persistence), Brent (QA) ' Story Points: 158 ' COMPLETED: C0 100%, M1 100%, M2 100% — all actor/skill/tool work done ' ================================================================ -- Actors, Skills & Tools — Workstream C (Legendary #374) | v3.1.0 - v3.3.0 -- [Actor + Skill Schema C0 (#354)] as [C0] on {Jeff} {Aditya} {Luis} {Brent} requires 7 days [C0] starts 2026-02-11 [C0] is 100% completed [C0] is colored in PaleGreen/SeaGreen [Actor Runtime + Tool Exec (#355)] as [M1] on {Jeff} {Hamza} {Luis} {Brent} requires 3 days [M1] starts at [PROJ]'s end [M1] is 100% completed [M1] is colored in PaleGreen/SeaGreen [Actor Graphs + Tool Sources (#356)] as [M2] on {Aditya} {Jeff} {Luis} {Brent} {Hamza} requires 5 days [M2] starts at [M1]'s end [M2] is 100% completed [M2] is colored in PaleGreen/SeaGreen ' ── v3.2.0 MILESTONE ───────────────────────────────────────── ' Gate: Sessions + Actor runtime + Tool execution operational ' Deliverables: Session management, actor tool-calling runtime, sandbox apply -- v3.2.0 — Runtime + Sessions (Feb 26) -- [v3.2.0 Release] as [MS3] happens 2026-02-26 ' ================================================================ ' EXECUTION PIPELINE & DECISIONS (Legendary #375) — v3.2.0-v3.4.0 ' Scope: Decision model, validation pipeline, invariants, DoD gating ' Owner: Jeff (invariants), Luis (validation), Hamza (decisions), Brent (QA) ' Story Points: 64 ' ================================================================ -- Execution Pipeline & Decisions (Legendary #375) | v3.2.0 - v3.4.0 -- [Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days [M3] starts at [M2]'s end [M3] is 25% completed [M3] is colored in LightSkyBlue/SteelBlue ' ── v3.3.0 MILESTONE ───────────────────────────────────────── ' Gate: Tool source chain complete + Security hardening + Provider stability ' Deliverables: Actor graphs, MCP adapter, security fixes, provider controls -- v3.3.0 — Tool Sources + Security (Mar 02) -- [v3.3.0 Release] as [MS4] happens 2026-03-02 ' ================================================================ ' HARDENING, TESTING & SECURITY (Legendary #376) — v3.3.0-v3.5.0 ' Scope: Corrections, subplans, checkpoints, security fixes, provider fixes ' Owner: Luis (security/corrections), Jeff (phase reversion), Hamza (sandbox) ' Story Points: 58 ' RISK: SEC at 80% — safety profiles remaining ' ================================================================ -- Hardening, Testing & Security (Legendary #376) | v3.3.0 - v3.5.0 -- [Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days [M4] starts at [M3]'s end [M4] is 35% completed [M4] is colored in LightSkyBlue/SteelBlue [Security + Safety Hardening (#362)] as [SEC] on {Luis} requires 3 days [SEC] starts 2026-03-02 [SEC] is 28% completed [SEC] is colored in LightSkyBlue/SteelBlue [Provider Fixes + Runtime (#363)] as [PROV] on {Luis} requires 2 days [PROV] starts 2026-02-12 [PROV] is 100% completed [PROV] is colored in PaleGreen/SeaGreen ' ── v3.4.0 MILESTONE ───────────────────────────────────────── ' Gate: Decisions + Validations + CLI polish + Concurrency ' Deliverables: Decision tree, validation pipeline, invariants, CLI extensions -- v3.4.0 — Decisions + Validation (Mar 06) -- [v3.4.0 Release] as [MS5] happens 2026-03-06 ' ================================================================ ' DAY 14 REBASELINE MILESTONES (Legendary #377) — v3.4.0-v3.5.0 ' Scope: ACMS v1, context scaling, autonomy hardening, server stubs ' Owner: Hamza (ACMS/context), Jeff (services/CLI), Luis (autonomy) ' Story Points: 110 ' ================================================================ -- Day 14 Rebaseline Milestones (Legendary #377) | v3.4.0 - v3.5.0 -- [ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days [M5] starts at [M4]'s end [M5] is 36% completed [M5] is colored in LightSkyBlue/SteelBlue [Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days [M6] starts at [M5]'s end [M6] is 18% completed [M6] is colored in LightSkyBlue/SteelBlue [Subplans + Parallelism (#368)] as [SUBP] on {Luis} {Brent} requires 2 days [SUBP] starts 2026-02-23 [SUBP] is 100% completed [SUBP] is colored in PaleGreen/SeaGreen [Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days [LARGE] starts 2026-03-17 [LARGE] is 42% completed [LARGE] is colored in LightSkyBlue/SteelBlue ' ── v3.5.0 MILESTONE ───────────────────────────────────────── ' Gate: Corrections + Checkpoints + ACMS v1 + Context tiers ' Deliverables: Phase reversion, checkpoint/rollback, context pipeline, autonomy guardrails -- v3.5.0 — Corrections + Context (Mar 10) -- [v3.5.0 Release] as [MS6] happens 2026-03-10 ' ================================================================ ' POST-MVP DEFERRED WORK (Legendary #378) — v3.6.0 ' Scope: Virtual resources, remote clients, safety profiles, RDF, REPL ' Owner: Luis (clients/security), Hamza (resources), Rui (REPL), Jeff (UI) ' Story Points: 100 ' ================================================================ -- Post-MVP Deferred Work (Legendary #378) | v3.6.0 -- [Post-MVP Deferred Work (#366)] as [POST] on {Luis} {Hamza} {Jeff} {Rui} {Brent} requires 8 days [POST] starts at [M6]'s end [POST] is 0% completed [POST] is colored in #E8E8E8/Silver [Multi-Agent RDF System (#367)] as [RDF] on {Aditya} requires 5 days [RDF] starts 2026-03-24 [RDF] is 0% completed [RDF] is colored in #E8E8E8/Silver ' ── v3.6.0 MILESTONE ───────────────────────────────────────── ' Gate: All post-MVP deferred work ' Deliverables: Remote clients, safety enforcement, virtual resources, RDF, TUI -- v3.6.0 — Post-MVP Release (Mar 27) -- [v3.6.0 Release] as [MS7] happens 2026-03-27 ' ================================================================ ' DEPENDENCY ARROWS ' Simplified: milestone gates + critical path + key cross-links ' 21 arrows (reduced from 42 for readability) ' ================================================================ ' Milestone gates: one key deliverable per release [QA] -> [MS1] [A1A5] -> [MS2] [PROJ] -> [MS2] [M1] -> [MS3] [M2] -> [MS4] [M3] -> [MS5] [M4] -> [MS6] [POST] -> [MS7] [LARGE] -> [MS7] ' Critical path + cross-workstream dependencies [FOUND] -> [TRACE] [QA] -> [A1A5] [QA] -> [PROJ] [A1A5] -> [PIPE] [PROJ] -> [M1] [M1] -> [M2] [M2] -> [M3] [M3] -> [M4] [M4] -> [M5] [M5] -> [M6] [M6] -> [POST] [A6A8] -> [CLI] ' ================================================================ ' DEVELOPER ALLOCATION LEGEND ' ================================================================ legend right **CleverAgents Core — Epic-Level Schedule** ---- **Critical Path (longest dependency chain):** QA -> A1A5 -> PIPE -> M1 -> M2 -> M3 -> M4 -> M5 -> M6 -> POST ---- |= Developer |= Role |= Total Pts |= Est. Hours | | Jeff (freemo) | CTO / Lead Architect | 480 | ~960h | | Luis (CoreRasurae) | Sr. Python Architect | 338 | ~676h | | Aditya | Domain Expert (Agents) | 183 | ~366h | | Hamza (hamza.khyari) | Infrastructure / RDF | 171 | ~342h | | Brent (brent.edwards) | Quality / QA | 170 | ~340h | | Rui (hurui200320) | Testing | 8 | ~16h | ---- **Per-Milestone Allocation (done / total story points)** |= Dev |= v3.0.0 |= v3.1.0 |= v3.2.0 |= v3.3.0 |= v3.4.0 |= v3.5.0 |= v3.6.0 | | Jeff | 188/188 | 176/176 | 58/58 | 47/47 | 5/61 | 13/92 | 0/64 | | Luis | 16/16 | 29/29 | 21/21 | 29/34 | - | 0/39 | 0/24 | | Aditya | 128/128 | 86/86 | - | - | 0/8 | - | - | | Hamza | 19/19 | 5/5 | 13/23 | 32/32 | 0/37 | - | 0/29 | | Brent | 71/71 | 21/21 | 11/11 | 24/24 | 8/14 | 25/30 | 0/5 | | Rui | - | - | - | - | - | - | - | ---- **Milestone Scope** |= Milestone |= Target |= Epics |= SP |= Key Deliverables | | v3.0.0 | Feb 15 | 9 | 172 | Minimal local source-code workflow | | v3.1.0 | Feb 22 | 4 | 208 | Actor graphs + tool sources | | v3.2.0 | Feb 26 | 2 | 104 | Decisions + validations + invariants | | v3.3.0 | Mar 02 | 3 | 126 | Corrections + subplans + checkpoints | | v3.4.0 | Mar 06 | 3 | 129 | ACMS v1 + context scaling | | v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs | | v3.6.0 | Mar 27 | 2 | 100 | Deferred work | ---- **Risk Register (Day 100 — 2026-04-10)** |= Epic |= Completion |= Risk |= Blocker | | M3 (#357) | 32% | **CRITICAL** | 521 open issues in v3.2.0 (scope expanded 320→770) | | M4 (#358) | 49% | **CRITICAL** | 112 open issues in v3.3.0 | | M5 (#359) | 43% | **HIGH** | 180 open issues in v3.4.0 | | M6 (#360) | 18% | **CRITICAL** | 888 open issues in v3.5.0 (massive scope expansion) | | M7 (#361) | 38% | **HIGH** | 250 open issues in v3.6.0 | | M8 (#362) | 45% | **HIGH** | 519 open issues in v3.7.0 | | SEC (#363) | 28% | **HIGH** | 344 open issues in v3.8.0 | ---- **Color Key** |= Color |= Meaning | | | Completed (100%) | | | In Progress | | | Not Started | | <> | Milestone Target | | | | Today (2026-04-10) | ---- 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers ~1649 total story points | ~3300 estimated hours **~25 open bugs (Type/Bug) — 225 open PRs — Session 4 active (32 workers)** end legend @endgantt ``` #### Detailed Issue-Level Schedule (213 Issues) The following chart expands every epic into its individual issues, showing per-developer scheduling, completion status, and the full project timeline at the task level. ```kroki-plantuml @startgantt title CleverAgents Core - Detailed Project Gantt Chart ' NOTE: This chart contains ~250 tasks. Use a local PlantUML renderer ' (java -jar plantuml.jar docs/gantt-detailed.puml) for best results. ' Online renderers may truncate or time out. Project starts 2026-02-03 saturday are closed sunday are closed printscale weekly zoom 2 today is 2026-04-15 today is colored in #FF6666 @endgantt ``` ### 2026-04-19 (Day 109) **Summary** Status: Behind 25+d Deadline risk: CRITICAL **Notes** - Day 109 update (2026-04-19). Current milestone status snapshot. - Milestone completions (Day 109): M1 100% (164/164), M2 100% (108/108), M3 25.4% (331/1303), M4 35.6% (120/338), M5 35.5% (158/445), M6 17.8% (249/1399), M7 32.2% (161/500), M8 41.3% (438/1060), M9 28.1% (144/511), v3.9.0 35.8% (24/67). - Blockers: broken .nox/ symlinks affecting test execution. - Current completion estimate: ~65-70% across active milestones. - All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development. #### Milestone forecast | Milestone | Target -> ETA | Delta | Risk | |-----------|---------------|-------|------| | M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE | | M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE | | M3 (v3.2.0) | (2026-02-26) -> ETA 2026-07-15 | +140d | CRITICAL | | M4 (v3.3.0) | (2026-03-02) -> ETA 2026-06-01 | +91d | CRITICAL | | M5 (v3.4.0) | (2026-03-06) -> ETA 2026-06-15 | +101d | HIGH | | M6 (v3.5.0) | (2026-03-10) -> ETA 2026-09-01 | +175d | CRITICAL | | M7 (v3.6.0) | (2026-03-28) -> ETA 2026-07-01 | +95d | HIGH | | M8 (v3.7.0) | (no deadline) -> ETA 2026-08-01 | N/A | HIGH | | M9 (v3.8.0) | (no deadline) -> ETA 2026-08-15 | N/A | MEDIUM | | v3.9.0 | (no deadline) -> ETA 2026-09-01 | N/A | LOW | #### Schedule Adherence - 2026-04-18 | Date | Day | Cycle | Milestone | Planned % | Actual % | Delta | Risk | Notes | |------|-----|-------|-----------|-----------|----------|-------|------|-------| | 2026-04-18 | D107 | — | v3.2.0 M3 | ~50% | 25.7% | -24.3% | CRITICAL | 959 open issues | | 2026-04-18 | D107 | — | v3.3.0 M4 | ~60% | 35.5% | -24.5% | HIGH | 218 open issues | | 2026-04-18 | D107 | — | v3.4.0 M5 | ~60% | 35.5% | -24.5% | HIGH | 287 open issues | | 2026-04-18 | D107 | — | v3.5.0 M6 | ~50% | 18.1% | -31.9% | CRITICAL | 1,130 open issues | | 2026-04-18 | D107 | — | v3.6.0 M7 | ~60% | 32.8% | -27.2% | HIGH | 332 open issues | | 2026-04-18 | D107 | — | v3.7.0 M8 | — | 41.8% | — | HIGH | 608 open, ETA ~2026-07-04 | | 2026-04-18 | D107 | — | v3.8.0 M9 | — | 28.2% | — | MEDIUM | 367 open, ETA ~2026-09-06 | | 2026-04-18 | D107 | — | v3.9.0 | — | 37.5% | — | LOW | 40 open, ETA ~2026-05-10 | ## Daily Snapshot - 2026-04-18 | Milestone | Completed % | Open Issues | Risk Assessment | |-----------|-------------|-------------|-----------------| | v3.2.0 (M3) | 25.7% | 959 | 🔴 High | | v3.3.0 (M4) | 35.5% | 218 | 🔴 High | | v3.4.0 (M5) | 35.5% | 287 | 🔴 High | | v3.5.0 (M6) | 18.1% | 1,130 | 🔴 High | | v3.6.0 (M7) | 32.8% | 332 | 🔴 High | | v3.7.0 (M8) | 41.8% | 608 | 🟡 Medium | | v3.8.0 (M9) | 28.2% | 367 | 🟡 Medium | | v3.9.0 | 37.5% | 40 | 🟢 Low | **Automated by CleverAgents Bot** Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor