diff --git a/docs/timeline.md b/docs/timeline.md index 963b1cd39..a0a2ea398 100644 --- a/docs/timeline.md +++ b/docs/timeline.md @@ -10,16 +10,27 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto @startgantt title CleverAgents Core — Epic-Level Project Schedule -footer Generated 2026-04-10 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~25 open bugs | 225 open PRs | Session 4 active +footer Generated 2026-04-13 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~25 open bugs | ~225 open PRs | Session 5 active Project starts 2026-02-03 saturday are closed sunday are closed printscale weekly zoom 2 -today is 2026-04-10 +today is 2026-04-13 today is colored in #FF6666 +' ================================================================ + +' ================================================================ +' GANTT CHART UPDATE LOG (Day 103 — 2026-04-13) +' Changes: Day 103 refresh (cycle 1). Session 5 active (32 workers). +' CI failing on master. v3.9.0 milestone added (19 total issues, 21% complete). +' M3 27.5% (264/962), M4 45.8% (108/236), M5 39.5% (137/347), +' M6 17.0% (202/1187, scope expanded!), M7 35.1% (152/433), +' M8 44.6% (427/957), M9 27.0% (132/489), M10 21.1% (4/19). +' Scope expansion continues across M3, M5, M6, M7, M8, M9. +' v3.1.0 closed with 2 residual open issues (98.2% complete). ' ================================================================ ' GANTT CHART UPDATE LOG (Day 100 — 2026-04-10) ' Changes: Day 100 refresh (cycle 2). Session 4 active (issue #4799, 32 workers). @@ -445,7 +456,7 @@ saturday are closed sunday are closed printscale weekly zoom 2 -today is 2026-04-10 +today is 2026-04-13 today is colored in #FF6666