From 157b0d6b8c4befb3e480ef722eb5cd656614beec Mon Sep 17 00:00:00 2001 From: CleverThis Date: Fri, 10 Apr 2026 10:10:22 +0000 Subject: [PATCH] docs(timeline): update schedule adherence Day 100 (2026-04-10) Refresh Day 100 entries using Forgejo telemetry across both cycle snapshots to capture scope expansion, milestone progress, and active session data.\n\n- Update today marker and Gantt update log for Day 100\n- Capture scope expansion metrics and milestone completion percentages\n- Refresh risk register, status summary, and track/milestone forecasts\n- Append Day 100 cycle-2 schedule adherence tables for teams and milestones\n- Note infrastructure changes (review requirement, supervisor additions)\n\nISSUES CLOSED: #6975 --- docs/timeline.md | 130 +++++++++++++++++++++++------------------------ 1 file changed, 65 insertions(+), 65 deletions(-) diff --git a/docs/timeline.md b/docs/timeline.md index 5c73a029c..963b1cd39 100644 --- a/docs/timeline.md +++ b/docs/timeline.md @@ -10,25 +10,26 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto @startgantt title CleverAgents Core — Epic-Level Project Schedule -footer Generated 2026-04-09 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~2861 open bugs | 145 open PRs | Session 4 active +footer Generated 2026-04-10 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~25 open bugs | 225 open PRs | Session 4 active Project starts 2026-02-03 saturday are closed sunday are closed printscale weekly zoom 2 -today is 2026-04-09 +today is 2026-04-10 today is colored in #FF6666 ' ================================================================ -' GANTT CHART UPDATE LOG (Day 99 — 2026-04-09) -' Changes: Day 99 refresh. Session 4 active (#4799, 32 workers). -' Open PRs: 1→145 (+144 new PRs opened by agents). Open bugs: ~878→~2861 (+1983 new bugs!). -' M3 62% (240/387, scope grew 320→387), M4 56% (108/191, scope grew 161→191), -' M5 69% (130/187, scope grew 183→187), M6 27% (192/711, scope grew 638→711), -' M7 47% (150/313), M8 47% (422/880), M9 29% (129/435). -' Massive bug explosion: 878→2861 open bugs (+1983). Agent-driven issue creation continues. -' All milestones M3-M7 remain overdue. M8/M9 in active development. +' GANTT CHART UPDATE LOG (Day 100 — 2026-04-10) +' Changes: Day 100 refresh (cycle 2). Session 4 active (issue #4799, 32 workers). +' Open PRs: 221→225 (new PRs opened by agents). Open bugs: ~25 (Type/Bug label). +' M3 32% (249/770, scope expanded!), M4 49% (108/220), M5 43% (133/313), +' M6 18% (197/1085, scope massively expanded!), M7 38% (150/400), +' M8 45% (425/944), M9 28% (131/475). +' Massive scope expansion across all milestones since Day 98. +' pr-merge-pool-supervisor added as 17th supervisor. PR review reduced to 1 approval. +' git worktree sandbox merged. ACMS indexing pipeline wired. ' ================================================================