From 7c07a2c5881ba4fc00a6199f273b49a17986e2b0 Mon Sep 17 00:00:00 2001 From: CleverThis Date: Wed, 8 Apr 2026 15:40:22 +0000 Subject: [PATCH] docs(timeline): update schedule adherence Day 98 (2026-04-08) - Append Day 98 (2026-04-08) schedule adherence entry - Update gantt chart today marker to 2026-04-08 - Update gantt chart footer: 1445 open bugs, 131 open PRs, Session 4 active - Update gantt chart update log comment for Day 98 (Apr 8) - Update milestone percentages: M3 74%, M4 67%, M5 73%, M6 47%, M7 50%, M8 51%, M9 31% - Update Current Status Summary with Day 98 data - Update Schedule Risk Summary with Day 98 data - Update Milestone Roadmap sections with current issue counts - Add Day 98 completed work bullet to What Has Been Completed - Bug count: ~878 -> ~1445 (+567 new TDD/integration test failure issues) - Open PRs: 108 -> 131 (+23 net new since Day 96) - Session 4 (#4373) launched 2026-04-08 with 32 parallel workers --- docs/timeline.md | 192 +++++++++++++++++++++++++++++++++-------------- 1 file changed, 135 insertions(+), 57 deletions(-) diff --git a/docs/timeline.md b/docs/timeline.md index 9f93452ee..bdb40e210 100644 --- a/docs/timeline.md +++ b/docs/timeline.md @@ -10,23 +10,22 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto @startgantt title CleverAgents Core — Epic-Level Project Schedule -footer Generated 2026-04-06 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 878 open bugs | 108 open PRs | Session 3 active +footer Generated 2026-04-08 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 1445 open bugs | 131 open PRs | Session 4 active Project starts 2026-02-03 saturday are closed sunday are closed printscale weekly zoom 2 -today is 2026-04-06 +today is 2026-04-08 today is colored in #FF6666 ' ================================================================ -' GANTT CHART UPDATE LOG (Day 96 — 2026-04-06) -' Changes: Day 96 refresh. Open PRs: 183→108 (-75 PRs merged/closed!). Open bugs: ~878 (stable). -' M3 65% (246/377), M4 60% (109/183), M5 68% (136/199), M6 55% (180/327), -' M7 43% (152/350), M8 46% (418/917), M9 28% (131/467). -' Significant progress: M3 +4%, M4 +3%, M5 +4%, M7 +2%, M8 +5%, M9 +3%. -' Session 3 active. Session tracker issue: #3775. PR #3774 open (Click 8.2+ fix). +' GANTT CHART UPDATE LOG (Day 98 — 2026-04-08) +' Changes: Day 98 refresh (Apr 8). Open PRs: 108→131 (+23 net new since Day 96). Open bugs: ~878→1445 (+567 new TDD/integration test failure issues). +' M3 74% (235/317), M4 67% (108/161), M5 73% (130/177), M6 47% (186/396), +' M7 50% (150/301), M8 51% (402/795), M9 31% (128/412). +' Session 4 active (#4373). Session 3 closed. ' ================================================================