diff --git a/docs/timeline.md b/docs/timeline.md index c837e7d13..f192ffdf2 100644 --- a/docs/timeline.md +++ b/docs/timeline.md @@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto @startgantt title CleverAgents Core — Epic-Level Project Schedule -footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 536 open bugs | 92 open PRs | Session 3 active +footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 766 open bugs | 115 open PRs | Session 3 active Project starts 2026-02-03 saturday are closed @@ -22,10 +22,10 @@ today is colored in #FF6666 ' ================================================================ ' GANTT CHART UPDATE LOG (Day 95 — 2026-04-05) -' Changes: Day 95 update (refreshed). Open PRs: 76→92 (+16). Open bugs: 536 (stable). +' Changes: Day 95 update (final). Open PRs: 92→115 (+23). Open bugs: 536→766 (+230). ' Open issues: continued agent-driven expansion across all milestones. -' M3 67% (223/334), M4 63% (103/163), M5 70% (126/179), M6 67% (175/263), -' M7 55% (127/232), M8 52% (332/634), M9 27% (105/393). +' M3 64% (228/357), M4 60% (104/172), M5 69% (126/183), M6 55% (176/318), +' M7 43% (130/305), M8 43% (345/795), M9 25% (117/462). ' Session 3 active. UAT pool supervisor and spec updater agents running. ' Session tracker issue: #3075 (autonomous build progress report). ' ================================================================ @@ -400,13 +400,13 @@ legend right ---- **Risk Register (Day 95 — 2026-04-05 refreshed)** |= Epic |= Completion |= Risk |= Blocker | - | M3 (#357) | 67% | **CRITICAL** | 111 open issues in v3.2.0 | - | M4 (#358) | 63% | **CRITICAL** | 60 open issues in v3.3.0 | - | M5 (#359) | 70% | **HIGH** | 53 open issues in v3.4.0 | - | M6 (#360) | 67% | **HIGH** | 88 open issues in v3.5.0 | - | M7 (#361) | 55% | **HIGH** | 105 open issues in v3.6.0 | - | M8 (#362) | 52% | **HIGH** | 302 open issues in v3.7.0 (agent expansion) | - | SEC (#363) | 27% | **HIGH** | 288 open issues in v3.8.0 (agent expansion) | + | M3 (#357) | 64% | **CRITICAL** | 129 open issues in v3.2.0 | + | M4 (#358) | 60% | **CRITICAL** | 68 open issues in v3.3.0 | + | M5 (#359) | 69% | **HIGH** | 57 open issues in v3.4.0 | + | M6 (#360) | 55% | **HIGH** | 142 open issues in v3.5.0 | + | M7 (#361) | 43% | **HIGH** | 175 open issues in v3.6.0 | + | M8 (#362) | 43% | **HIGH** | 450 open issues in v3.7.0 (agent expansion) | + | SEC (#363) | 25% | **HIGH** | 345 open issues in v3.8.0 (agent expansion) | ---- **Color Key** |= Color |= Meaning | @@ -418,7 +418,7 @@ legend right ---- 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers ~1649 total story points | ~3300 estimated hours - **536 open bugs — 92 open PRs — Session 3 active (16 workers, ~71 agents)** + **766 open bugs — 115 open PRs — Session 3 active (16 workers, ~71 agents)** end legend @endgantt @@ -1951,7 +1951,7 @@ legend right ---- 271 Issues | 29 Epics | 9 Legendaries | 7 Milestones ~1649 total story points | ~3300 estimated hours - **536 open bugs — 76 open PRs — Session 3 active (16 workers, ~71 agents)** + **766 open bugs — 115 open PRs — Session 3 active (16 workers, ~71 agents)** end legend @endgantt @@ -1963,13 +1963,13 @@ This section provides a high-level overview of the CleverAgents implementation r ### Current Status Summary -As of Day 95 (2026-04-05), the project has **76 open PRs** and **~2800+ open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **536 open bugs** (continued agent-driven expansion from 389). M8 (v3.7.0) is now **52% complete** (332/634 issues closed — milestone grew from 438→634). M9 (v3.8.0) is **27% complete** (105/393 issues closed). +As of Day 95 (2026-04-05), the project has **115 open PRs** and **~3000+ open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **766 open bugs** (continued agent-driven expansion from 536). M8 (v3.7.0) is now **43% complete** (345/795 issues closed — milestone grew from 634→795). M9 (v3.8.0) is **25% complete** (117/462 issues closed). -**M1, M2 fully complete. M3 (v3.2.0)**: 70% complete (222/317), 95 open issues. **M4 (v3.3.0)**: 72% complete (101/141), 40 open issues. **M5 (v3.4.0)**: 75% complete (126/169), 43 open issues. **M6 (v3.5.0)**: 67% complete (175/263), 88 open issues. **M7 (v3.6.0)**: 55% complete (127/232), 105 open issues. **M8 (v3.7.0)**: 52% complete (332/634), 302 open issues. **M9 (v3.8.0)**: 27% complete (105/393), 288 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development. +**M1, M2 fully complete. M3 (v3.2.0)**: 64% complete (228/357), 129 open issues. **M4 (v3.3.0)**: 60% complete (104/172), 68 open issues. **M5 (v3.4.0)**: 69% complete (126/183), 57 open issues. **M6 (v3.5.0)**: 55% complete (176/318), 142 open issues. **M7 (v3.6.0)**: 43% complete (130/305), 175 open issues. **M8 (v3.7.0)**: 43% complete (345/795), 450 open issues. **M9 (v3.8.0)**: 25% complete (117/462), 345 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development. -!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 536 Open Bugs — Session 3 Active (Day 95: Continued Agent Expansion)" +!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 766 Open Bugs — Session 3 Active (Day 95 Final: Massive Agent Expansion)" - All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **76** (up from 64). Open bugs at **536** (continued agent-driven expansion from 389). M8 (v3.7.0) at 52% (332/634 closed — milestone grew from 438→634). M9 (v3.8.0) at 27% (105/393 closed). New session tracker issues: #2874 (progress report), #2875 (UAT pool supervisor), #2876 (spec updater). **Current priorities**: (1) **Triage 536 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 76 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push** — 52% complete, 302 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 70% (95 open), M4 at 72% (40 open), M5 at 75% (43 open). + All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **115** (up from 92 earlier today, +23 new PRs). Open bugs at **766** (up from 536, +230 agent-driven expansion). M8 (v3.7.0) at 43% (345/795 closed — milestone grew from 634→795). M9 (v3.8.0) at 25% (117/462 closed). Session tracker issue: #3075. **Current priorities**: (1) **Triage 766 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 115 open PRs** — TUI features, security fixes, spec compliance, A2A fixes. (3) **Continue M8 push** — 43% complete, 450 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 64% (129 open), M4 at 60% (68 open), M5 at 69% (57 open). ### Parallel Workstreams @@ -4949,14 +4949,14 @@ Deadline risk: HIGH **Notes** -- Day 95 update (refreshed 2026-04-05). Open PRs: 92 (up from 76 earlier today, +16 new PRs). Open bugs: 536 (stable). Session tracker issue: #3075. +- Day 95 final update (2026-04-05). Open PRs: 92→115 (+23 new PRs opened). Open bugs: 536→766 (+230 agent-driven expansion). Session tracker issue: #3075. - Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. UAT pool supervisor, PR reviewer pool, implementation pool, and spec updater agents all running. -- Milestone totals continued to grow due to agent-driven issue creation: M3 (317→334), M4 (141→163), M5 (169→179), M6 (263 stable), M7 (232 stable), M8 (634 stable), M9 (393 stable). -- Milestone completions (Day 95 refreshed): M3 67% (223/334), M4 63% (103/163), M5 70% (126/179), M6 67% (175/263), M7 55% (127/232), M8 52% (332/634), M9 27% (105/393). -- M3 and M4 completion percentages declined from earlier Day 95 reading (M3: 70%→67%, M4: 72%→63%) because agent-driven issue creation is outpacing closures. +- Milestone totals grew significantly due to continued agent-driven issue creation: M3 (334→357), M4 (163→172), M5 (179→183), M6 (263→318), M7 (232→305), M8 (634→795), M9 (393→462). +- Milestone completions (Day 95 final): M3 64% (228/357), M4 60% (104/172), M5 69% (126/183), M6 55% (176/318), M7 43% (130/305), M8 43% (345/795), M9 25% (117/462). +- Completion percentages declined across all milestones from earlier Day 95 reading because agent-driven issue creation is massively outpacing closures. - All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development. - UAT pool supervisor (#3075) and spec updater agents are running autonomously, continuing to discover and file spec compliance issues. -- PR #3073 (docs/timeline-day95-refresh) is open with updated milestone data — this entry supersedes it. +- 115 open PRs include: A2A JSON-RPC fixes (#3353), CLI fixes (#3347, #3334, #3302, #3303), invariant fixes (#3342, #3329, #3269), resource fixes (#3336, #3295, #3290, #3266, #3252, #3250, #3248, #3245, #3235), tool fixes (#3308, #3288, #3283), sandbox fix (#3263), validation fix (#3317), and many more. #### Milestone forecast @@ -4965,55 +4965,55 @@ Deadline risk: HIGH |-----------|---------------|-------|------| | M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE | | M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE | -| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-04-28 | +61d | CRITICAL — 111 open issues; agent-driven expansion outpacing closures | -| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-02 | +61d | CRITICAL — 60 open issues; completion dropped 72%→63% | -| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-02 | +57d | HIGH — 53 open issues; 70% complete | -| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-10 | +61d | HIGH — 88 open issues; 67% complete | -| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-05-25 | +58d | HIGH — 105 open issues; 55% complete | -| M8 (v3.7.0) | (no deadline) -> ETA 2026-06-20 | N/A | HIGH — 302 open issues; 52% complete | -| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-10 | N/A | MEDIUM — 288 open issues; 27% complete | +| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-05 | +68d | CRITICAL — 129 open issues; agent expansion outpacing closures; 64% complete | +| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-10 | +69d | CRITICAL — 68 open issues; completion dropped to 60% | +| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-10 | +65d | HIGH — 57 open issues; 69% complete | +| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-20 | +71d | HIGH — 142 open issues; dropped to 55% complete | +| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-05 | +69d | HIGH — 175 open issues; dropped to 43% complete | +| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-01 | N/A | HIGH — 450 open issues; 43% complete; milestone grew 634→795 | +| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-20 | N/A | HIGH — 345 open issues; 25% complete; milestone grew 393→462 | #### Track forecast | Track | Status | ETA | Risk | Blocking | |-------|--------|-----|------|----------| | Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None | -| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-02 | MEDIUM | 53 open issues in v3.4.0; continued agent-driven expansion | -| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-02 | CRITICAL | 60 open issues in v3.3.0; UAT spec compliance bugs ongoing; completion dropped | -| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-04-28 | CRITICAL | 111 open issues in v3.2.0; agent-driven expansion outpacing closures | -| Track Q (Quality automation) | Ongoing | N/A | HIGH | 536 open bugs; continued agent-driven bug creation | -| Track T (Testing) | Active | Ongoing | HIGH | 92 open PRs need review; UAT pool supervisor active (#3075) | +| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-10 | MEDIUM | 57 open issues in v3.4.0; continued agent-driven expansion | +| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-10 | CRITICAL | 68 open issues in v3.3.0; UAT spec compliance bugs ongoing; completion dropped to 60% | +| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-05 | CRITICAL | 129 open issues in v3.2.0; agent-driven expansion massively outpacing closures | +| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | 766 open bugs; massive agent-driven bug creation (+230 today) | +| Track T (Testing) | Active | Ongoing | HIGH | 115 open PRs need review; UAT pool supervisor active (#3075) | #### Developer forecast | Name | Days Ahead/Behind | Availability | Risk | Focus | |------|-------------------|--------------|------|-------| -| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance; 92 open PRs | +| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance; 115 open PRs | | Luis | -21d behind | active | HIGH | M6 (v3.5.0) features; security hardening; audit session; PR review pool | | Hamza | -21d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews | | Aditya | -21d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing | -| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 536 open bugs triage | +| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 766 open bugs triage | | Rui | -21d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing | | Mike/Brian | N/A | standby | LOW | N/A | #### Task inventory -Milestone per developer as of Day 95 (2026-04-05). +Milestone per developer as of Day 95 final (2026-04-05). | Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total | |-----------|------|--------|------|-------|-------|-----|------------|-------| | M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 | | M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 | -| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 111 open | 223/334 | -| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 60 open | 103/163 | -| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 53 open | 126/179 | -| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 88 open | 175/263 | -| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 105 open | 127/232 | -| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 302 open | 332/634 | -| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 288 open | 105/393 | -| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1007 open** | **1191/2198 closed** | +| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 129 open | 228/357 | +| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 68 open | 104/172 | +| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 57 open | 126/183 | +| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 142 open | 176/318 | +| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 175 open | 130/305 | +| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 450 open | 345/795 | +| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 345 open | 117/462 | +| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1366 open** | **1278/2688 closed** | -Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 (refreshed 2026-04-05). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M3 grew from 317→334, M4 grew from 141→163, M5 grew from 169→179 due to continued agent activity. +Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 final (2026-04-05). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation massively expanded all milestones today: M3 grew 334→357, M4 grew 163→172, M5 grew 179→183, M6 grew 263→318, M7 grew 232→305, M8 grew 634→795, M9 grew 393→462. Open bugs grew 536→766 (+230). Open PRs grew 92→115 (+23). #### Story point allocation