From 7224ba6f3b9288ba263948ffcbfe7ce593f23455 Mon Sep 17 00:00:00 2001 From: Jeffrey Phillips Freeman Date: Sat, 4 Apr 2026 15:25:15 +0000 Subject: [PATCH 1/3] docs(timeline): update schedule adherence Day 55 (2026-04-04) - Append Day 55 schedule adherence entry with full milestone/track/developer/task/SP tables - Mark Issue #2597 (Priority/Critical) as CRITICAL blocker: master CI gates broken - Update gantt chart today marker to 2026-04-04 - Update gantt chart update log to Day 55 with current stats - Update open bug count: 324 -> 480; open PR count: 61 -> 74 - Update milestone completion percentages from Forgejo API: M3 72% (218/303), M4 77% (100/130), M5 75% (126/167), M6 67% (174/259), M7 56% (127/228), M8 15% (88/577), M9 29% (105/368) - Update risk register to reflect #2597 CI breakage blocking all PRs - PR #2629 open to restore CI quality gates --- docs/timeline.md | 146 +++++++++++++++++++++++++++++++++++++---------- 1 file changed, 117 insertions(+), 29 deletions(-) diff --git a/docs/timeline.md b/docs/timeline.md index b1c02f0d3..3eb7b24ec 100644 --- a/docs/timeline.md +++ b/docs/timeline.md @@ -10,28 +10,25 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto @startgantt title CleverAgents Core — Epic-Level Project Schedule -footer Generated 2026-04-03 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 324 open bugs | 61 open PRs | Session 3 active +footer Generated 2026-04-04 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 480 open bugs | 74 open PRs | Session 3 active Project starts 2026-02-03 saturday are closed sunday are closed printscale weekly zoom 2 -today is 2026-04-03 +today is 2026-04-04 today is colored in #FF6666 ' ================================================================ -' GANTT CHART UPDATE LOG (Day 54 — 2026-04-03 end-of-day) -' Changes: 15 PRs merged today. Agents created 500+ new issues (M8: 185→413, M9: 242→340). -' Open PRs: 84→61 (-23 net after merges). Open bugs: 50→324 (+274 new bugs from agents). -' Open issues: ~500→~2362 (massive agent-driven expansion). -' M3 73% (213/291), M4 79% (100/127), M5 83% (125/151), M6 70% (175/251), -' M7 65% (125/193), M8 19% (78/413), M9 22% (75/340). -' PRs merged today: #2181 (TUI docs), #2050 (CHANGELOG), #2014 (domain refactor), -' #1999 (aiohttp CVE fix), #1990 (A2A JSON-RPC rename), #1969 (actor add panels), -' #1865 (TLS fix), #1841 (SSE formatter), #1810 (flaky test fix), #1775 (CI script), -' #1733 (actor examples), #1644 (CI cache), #1633 (CI parallelize), #1584 (nox CI), -' #1577 (plan workflow fix). +' GANTT CHART UPDATE LOG (Day 55 — 2026-04-04) +' Changes: Day 55 update. Issue #2597 CRITICAL — CI quality gates broken on master. +' Open PRs: 74 (was 61). Open bugs: 480 (was 324, +156 new bugs from agents). +' Open issues: ~2362+ (continued agent-driven expansion). +' M3 72% (218/303), M4 77% (100/130), M5 75% (126/167), M6 67% (174/259), +' M7 56% (127/228), M8 15% (88/577), M9 29% (105/368). +' CRITICAL: #2597 (fix/master-ci-quality-gates) — lint/unit_tests/e2e_tests FAILING. +' PR #2629 open to fix CI. All other PRs blocked until master is green. ' ================================================================