diff --git a/docs/timeline.md b/docs/timeline.md index b1c02f0d3..a85d0804b 100644 --- a/docs/timeline.md +++ b/docs/timeline.md @@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto @startgantt title CleverAgents Core — Epic-Level Project Schedule -footer Generated 2026-04-03 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 324 open bugs | 61 open PRs | Session 3 active +footer Generated 2026-04-03 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 447 open bugs | 68 open PRs | Session 3 active Project starts 2026-02-03 saturday are closed @@ -21,13 +21,14 @@ today is 2026-04-03 today is colored in #FF6666 ' ================================================================ -' GANTT CHART UPDATE LOG (Day 54 — 2026-04-03 end-of-day) -' Changes: 15 PRs merged today. Agents created 500+ new issues (M8: 185→413, M9: 242→340). -' Open PRs: 84→61 (-23 net after merges). Open bugs: 50→324 (+274 new bugs from agents). -' Open issues: ~500→~2362 (massive agent-driven expansion). -' M3 73% (213/291), M4 79% (100/127), M5 83% (125/151), M6 70% (175/251), -' M7 65% (125/193), M8 19% (78/413), M9 22% (75/340). -' PRs merged today: #2181 (TUI docs), #2050 (CHANGELOG), #2014 (domain refactor), +' GANTT CHART UPDATE LOG (Day 54 — 2026-04-03 updated) +' Changes: 17 PRs merged today (+2 since last update: #2399 noxfile DB template, #2371 timeline). +' Open PRs: 84→68 (-16 net). Open bugs: 50→447 (+397 new bugs from agents). +' Open issues: ~500→~2362+ (massive agent-driven expansion continues). +' M3 73% (218/299), M4 77% (100/130), M5 77% (126/164), M6 67% (174/259), +' M7 57% (127/224), M8 18% (82/447), M9 29% (105/366). +' PRs merged today: #2399 (noxfile DB template), #2371 (timeline update), +' #2181 (TUI docs), #2050 (CHANGELOG), #2014 (domain refactor), ' #1999 (aiohttp CVE fix), #1990 (A2A JSON-RPC rename), #1969 (actor add panels), ' #1865 (TLS fix), #1841 (SSE formatter), #1810 (flaky test fix), #1775 (CI script), ' #1733 (actor examples), #1644 (CI cache), #1633 (CI parallelize), #1584 (nox CI), @@ -233,7 +234,7 @@ ganttDiagram { [Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days [M3] starts at [M2]'s end -[M3] is 83% completed +[M3] is 73% completed [M3] is colored in LightSkyBlue/SteelBlue ' ── v3.3.0 MILESTONE ───────────────────────────────────────── @@ -259,7 +260,7 @@ ganttDiagram { [Security + Safety Hardening (#362)] as [SEC] on {Luis} requires 3 days [SEC] starts 2026-03-02 -[SEC] is 78% completed +[SEC] is 67% completed [SEC] is colored in LightSkyBlue/SteelBlue [Provider Fixes + Runtime (#363)] as [PROV] on {Luis} requires 2 days @@ -284,12 +285,12 @@ ganttDiagram { [ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days [M5] starts at [M4]'s end -[M5] is 87% completed +[M5] is 77% completed [M5] is colored in LightSkyBlue/SteelBlue [Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days [M6] starts at [M5]'s end -[M6] is 71% completed +[M6] is 57% completed [M6] is colored in LightSkyBlue/SteelBlue [Subplans + Parallelism (#368)] as [SUBP] on {Luis} {Brent} requires 2 days @@ -299,7 +300,7 @@ ganttDiagram { [Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days [LARGE] starts 2026-03-17 -[LARGE] is 75% completed +[LARGE] is 57% completed [LARGE] is colored in LightSkyBlue/SteelBlue ' ── v3.5.0 MILESTONE ───────────────────────────────────────── @@ -401,15 +402,15 @@ legend right | v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs | | v3.6.0 | Mar 27 | 2 | 100 | Deferred work | ---- - **Risk Register (Day 54 — end-of-day)** + **Risk Register (Day 54 — updated)** |= Epic |= Completion |= Risk |= Blocker | - | M3 (#357) | 73% | **CRITICAL** | 78 open issues in v3.2.0 | - | M4 (#358) | 79% | **HIGH** | 27 open issues in v3.3.0 | - | M5 (#359) | 83% | **HIGH** | 26 open issues in v3.4.0 | - | M6 (#360) | 70% | **HIGH** | 76 open issues in v3.5.0 | - | M7 (#361) | 65% | **HIGH** | 68 open issues in v3.6.0 | - | M8 (#362) | 19% | **CRITICAL** | 335 open issues in v3.7.0 (agent expansion) | - | SEC (#363) | 22% | **CRITICAL** | 265 open issues in v3.8.0 (agent expansion) | + | M3 (#357) | 73% | **CRITICAL** | 81 open issues in v3.2.0 | + | M4 (#358) | 77% | **HIGH** | 30 open issues in v3.3.0 | + | M5 (#359) | 77% | **HIGH** | 38 open issues in v3.4.0 | + | M6 (#360) | 67% | **HIGH** | 85 open issues in v3.5.0 | + | M7 (#361) | 57% | **HIGH** | 97 open issues in v3.6.0 | + | M8 (#362) | 18% | **CRITICAL** | 365 open issues in v3.7.0 (agent expansion) | + | SEC (#363) | 29% | **MEDIUM** | 261 open issues in v3.8.0 (agent expansion) | ---- **Color Key** |= Color |= Meaning | @@ -421,7 +422,7 @@ legend right ---- 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers ~1649 total story points | ~3300 estimated hours - **324 open bugs — 61 open PRs — Session 3 active (16 workers, ~71 agents)** + **447 open bugs — 68 open PRs — Session 3 active (16 workers, ~71 agents)** end legend @endgantt @@ -1954,7 +1955,7 @@ legend right ---- 271 Issues | 29 Epics | 9 Legendaries | 7 Milestones ~1649 total story points | ~3300 estimated hours - **324 open bugs — 61 open PRs — Session 3 active (16 workers, ~71 agents)** + **447 open bugs — 68 open PRs — Session 3 active (16 workers, ~71 agents)** end legend @endgantt @@ -1966,13 +1967,13 @@ This section provides a high-level overview of the CleverAgents implementation r ### Current Status Summary -As of Day 54 (2026-04-03, end-of-day), the project has **61 open PRs** and **~2362 open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. 15 PRs merged today. Bug count is **324 open bugs** (massive agent-driven expansion from 50 overnight). M8 (v3.7.0) is now **19% complete** (78/413 issues closed — milestone grew from 185→413). M9 (v3.8.0) is **22% complete** (75/340 issues closed — milestone grew from 242→340). +As of Day 54 (2026-04-03, updated), the project has **68 open PRs** and **~2362+ open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. 17 PRs merged today. Bug count is **447 open bugs** (agent-driven expansion continues). M8 (v3.7.0) is now **18% complete** (82/447 issues closed). M9 (v3.8.0) is **29% complete** (105/366 issues closed). -**M1, M2 fully complete. M3 (v3.2.0)**: 73% complete (213/291), 78 open issues. **M4 (v3.3.0)**: 79% complete (100/127), 27 open issues. **M5 (v3.4.0)**: 83% complete (125/151), 26 open issues. **M6 (v3.5.0)**: 70% complete (175/251), 76 open issues. **M7 (v3.6.0)**: 65% complete (125/193), 68 open issues. **M8 (v3.7.0)**: 19% complete (78/413), 335 open issues. **M9 (v3.8.0)**: 22% complete (75/340), 265 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development. +**M1, M2 fully complete. M3 (v3.2.0)**: 73% complete (218/299), 81 open issues. **M4 (v3.3.0)**: 77% complete (100/130), 30 open issues. **M5 (v3.4.0)**: 77% complete (126/164), 38 open issues. **M6 (v3.5.0)**: 67% complete (174/259), 85 open issues. **M7 (v3.6.0)**: 57% complete (127/224), 97 open issues. **M8 (v3.7.0)**: 18% complete (82/447), 365 open issues. **M9 (v3.8.0)**: 29% complete (105/366), 261 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development. -!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 324 Open Bugs — Session 3 Active (Day 54: Massive Agent Expansion)" +!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 360 Open Bugs — Session 3 Active (Day 54: Milestone Scope Expansion)" - All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. 15 PRs merged today (A2A JSON-RPC, actor panels, TLS fix, CI improvements, aiohttp CVE). Open PRs at **61** (down from 84 — merges outpaced new PRs). Open bugs at **324** (massive agent-driven expansion). M8 (v3.7.0) at 19% (78/413 closed — milestone grew from 185→413). M9 (v3.8.0) at 22% (75/340 closed — milestone grew from 242→340). **Current priorities**: (1) **Triage 324 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 61 open PRs** — CLI fix wave, TUI features, security fixes. (3) **Continue M8 push** — 19% complete, 335 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 73% (78 open), M4 at 79% (27 open), M5 at 83% (26 open). + All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. 17 PRs merged today (A2A JSON-RPC, actor panels, TLS fix, CI improvements, aiohttp CVE, noxfile DB template). Open PRs at **62**. Open bugs at **360** (agent-driven expansion). M8 (v3.7.0) at 19% (81/431 closed). M9 (v3.8.0) at 31% (105/344 closed). **Current priorities**: (1) **Triage 360 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 62 open PRs** — CLI fix wave, TUI features, security fixes. (3) **Continue M8 push** — 19% complete, 350 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 74% (76 open), M4 at 79% (27 open), M5 at 78% (35 open). ### Parallel Workstreams @@ -2288,18 +2289,18 @@ Items without an assigned milestone represent backlog work to be addressed after ### Schedule Risk Summary -As of Day 54 (2026-04-03, end-of-day), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. 15 PRs merged today. Open PRs now at **61** (down from 84 — merges outpaced new PRs). Open bugs at **324** (massive agent-driven expansion from 50). M8 (v3.7.0) at **19% complete** (78/413 closed — milestone grew from 185→413). M9 (v3.8.0) at **22% complete** (75/340 closed — milestone grew from 242→340). Critical path: 61 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 19% with 335 issues remaining; 324 open bugs need TDD counterparts and systematic triage. +As of Day 54 (2026-04-03, updated), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. 17 PRs merged today. Open PRs now at **68**. Open bugs at **447** (agent-driven expansion continues). M8 (v3.7.0) at **18% complete** (82/447 closed). M9 (v3.8.0) at **29% complete** (105/366 closed). Critical path: 68 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 18% with 365 issues remaining; 447 open bugs need TDD counterparts and systematic triage. **Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry. **Day 53 Session 3 actions**: (a) 16 parallel workers started. (b) 73+ PRs merged including ACMS UKO runtime (#1312), PermissionsScreen TUI (#1307), actor thought blocks (#1298), DatabaseResourceHandler (#1293), ACMS pipeline Phase 2 (#1287), DevcontainerHandler (#1286), async audit (#1279), serve CLI (#1272), LSP hover/definitions (#1240), domain event wiring (#1215), plan prompt command (#1212), M6 E2E tests (#1277), @tdd_expected_fail cleanup (#1229), persona export/import (#1338), first-run experience (#1391), session export/import (#1392). (c) UAT supervisor fleet (cycles 11-131) launched — discovered 100+ spec compliance bugs across CLI rich output, YAML config handling, and actor compiler. (d) Security bug-hunt PRs opened: #1412 (concurrency), #1409 (error handling), #1419 (hardcoded secrets). (e) Late-day: 4 more PRs merged (#1498, #1481, #1479, #1338), 18 new fix PRs opened (#1506-#1517) targeting UAT findings. (f) End-of-day CLI fix wave: 18 more PRs merged (#1574, #1573, #1570, #1569, #1567, #1566, #1565, #1563, #1562, #1558, #1556, #1554 and others) — open bugs reduced from **143 to 6**, open PRs at **74**. **Critical path blockers** (ranked): -1. **84 open PRs need review** — 5 new PRs opened overnight (fix/a2a-sse-event-formatter, fix/actor-add-rich-output, fix/ci-push-to-repository, fix/infra-tls-handshake-failure-git-dev, fix/test-infra-flaky-test-example). All require review before merge. -2. **50 open bugs need TDD counterparts** — agents created additional bugs overnight. Critical: #1782 (coverage 37%), #1791 (AmbiguousStep crash), #1789/#1768 (path traversal vulnerabilities). -3. **M3-M7 backlog** — 69+28+19+69+57 open issues across M3-M7. All milestones regressed as agents added new issues overnight. -4. **M8 (v3.7.0) at 29%** — 131 issues remaining (milestone grew from 152→185). Agents added 33 new issues overnight. -5. **M9 (v3.8.0) at 26%** — 178 issues remaining (milestone grew from 160→242). Massive expansion — 82 new issues added overnight. +1. **68 open PRs need review** — 17 PRs merged today; agents opened new PRs. Net open PRs at 68. +2. **447 open bugs need TDD counterparts** — agent-driven expansion continues. Critical: #1782 (coverage 37%), #1791 (AmbiguousStep crash), #1789/#1768 (path traversal vulnerabilities). +3. **M3-M7 backlog** — 81+30+38+85+97 open issues across M3-M7. Milestone totals grew as agents added new issues. +4. **M8 (v3.7.0) at 18%** — 365 issues remaining (milestone grew to 447). Agents continue adding issues. +5. **M9 (v3.8.0) at 29%** — 261 issues remaining (milestone at 366). Scope expanding. **Spec changes impact assessment (Day 31)**: ACP→A2A rename affects 10 source files, 13 classes, 640+ test references across 22 files. Zero A2A code exists — migration not started. All open PRs that touch ACP modules will need additional rebase work after #688/#689 merge. TUI spec adds ~1,500 lines with 18 ASCII mockups defining Textual-based UI — PR #667 was a placeholder that predates this spec. Server architecture adopts JSON-RPC 2.0 standard — PR #676 used custom protocol, now obsolete. @@ -4856,16 +4857,16 @@ Deadline risk: HIGH **Notes** -- Day 54 end-of-day update. 15 PRs merged today (A2A JSON-RPC compliance, actor add panels, TLS fix, CI parallelization, aiohttp CVE-2026-34515, flaky test fix, CHANGELOG restructure, domain refactor, nox CI, behave runner script, actor examples, CI cache consolidation, plan workflow fix, TUI docs, SSE formatter). +- Day 54 updated. 17 PRs merged today (A2A JSON-RPC compliance, actor add panels, TLS fix, CI parallelization, aiohttp CVE-2026-34515, flaky test fix, CHANGELOG restructure, domain refactor, nox CI, behave runner script, actor examples, CI cache consolidation, plan workflow fix, TUI docs, SSE formatter, noxfile DB template extension, timeline update). - Agents (UAT, bug-hunt, CI, test-infra) created 500+ new issues throughout the day, massively expanding M8 and M9 milestone totals. -- Open PRs: 84 (morning) → 61 (end-of-day, -23 net after 15 merges and new PRs opened) -- Open bugs: 50 (morning) → 324 (end-of-day, +274 new bugs from agent-driven expansion) -- Open issues: ~500 (morning) → ~2362 (end-of-day, massive agent-driven expansion) -- Milestone totals grew significantly: M3 (281→291), M4 (127→127), M5 (145→151), M6 (241→251), M7 (177→193), M8 (185→413), M9 (242→340) -- Milestone completions (end-of-day): M3 73% (213/291), M4 79% (100/127), M5 83% (125/151), M6 70% (175/251), M7 65% (125/193), M8 19% (78/413), M9 22% (75/340) +- Open PRs: 84 (morning) → 68 (updated, -16 net after 17 merges and new PRs opened) +- Open bugs: 50 (morning) → 447 (updated, +397 new bugs from agent-driven expansion) +- Open issues: ~500 (morning) → ~2362+ (massive agent-driven expansion continues) +- Milestone totals grew significantly: M3 (281→299), M4 (127→130), M5 (145→164), M6 (241→259), M7 (177→224), M8 (185→447), M9 (242→366) +- Milestone completions (updated): M3 73% (218/299), M4 77% (100/130), M5 77% (126/164), M6 67% (174/259), M7 57% (127/224), M8 18% (82/447), M9 29% (105/366) - Critical issues still open: #1782 (coverage 37% — below 97% threshold), #1791 (AmbiguousStep unit test crash), #1789/#1768 (path traversal vulnerabilities) - Session 3 remains active with 16 parallel workers and ~71 total concurrent agents -- PRs merged today: #2181 (TUI PermissionQuestionWidget docs), #2050 (CHANGELOG restructure), #2014 (domain model_config refactor), #1999 (aiohttp CVE-2026-34515 fix), #1990 (A2A JSON-RPC 2.0 field rename), #1969 (actor add rich output panels), #1865 (TLS handshake fix), #1841 (SSE formatter JSON-RPC 2.0), #1810 (flaky test fix), #1775 (behave-parallel runner script), #1733 (actor examples fix), #1644 (CI uv cache consolidation), #1633 (CI parallelization), #1584 (nox CI refactor), #1577 (plan workflow fix) +- PRs merged today: #2399 (noxfile DB template for slow/e2e tests), #2371 (timeline Day 54 update), #2181 (TUI PermissionQuestionWidget docs), #2050 (CHANGELOG restructure), #2014 (domain model_config refactor), #1999 (aiohttp CVE-2026-34515 fix), #1990 (A2A JSON-RPC 2.0 field rename), #1969 (actor add rich output panels), #1865 (TLS handshake fix), #1841 (SSE formatter JSON-RPC 2.0), #1810 (flaky test fix), #1775 (behave-parallel runner script), #1733 (actor examples fix), #1644 (CI uv cache consolidation), #1633 (CI parallelization), #1584 (nox CI refactor), #1577 (plan workflow fix) #### Milestone forecast @@ -4876,22 +4877,22 @@ Deadline risk: HIGH | M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE | | M3 (v3.2.0) | (2026-02-26) -> ETA 2026-04-20 | +53d | CRITICAL | | M4 (v3.3.0) | (2026-03-02) -> ETA 2026-04-22 | +51d | HIGH | -| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-04-16 | +41d | HIGH | -| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-04-28 | +49d | HIGH | -| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-05-07 | +40d | HIGH | +| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-04-20 | +45d | HIGH | +| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-01 | +52d | HIGH | +| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-05-14 | +47d | HIGH | | M8 (v3.7.0) | (no deadline) -> ETA 2026-06-15 | N/A | HIGH | -| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-10 | N/A | MEDIUM | +| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-01 | N/A | MEDIUM | #### Track forecast | Track | Status | ETA | Risk | Blocking | |-------|--------|-----|------|----------| | Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None | -| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-04-16 | MEDIUM | 26 open issues in v3.4.0; AWS CloudResource PR #1280 open | +| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-04-20 | MEDIUM | 35 open issues in v3.4.0; AWS CloudResource PR #1280 open | | Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-04-22 | HIGH | 27 open issues in v3.3.0; actor compiler UAT bugs; agent-created issues | -| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-04-20 | HIGH | 78 open issues in v3.2.0; correction/audit PRs open; agent-driven expansion | -| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | 324 open bugs; coverage at 37% (#1782 critical); AmbiguousStep crash (#1791) | -| Track T (Testing) | Active | Ongoing | HIGH | 61 open PRs need review; path traversal vulnerabilities (#1789, #1768) critical | +| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-04-20 | HIGH | 76 open issues in v3.2.0; correction/audit PRs open; agent-driven expansion | +| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | 447 open bugs; coverage at 37% (#1782 critical); AmbiguousStep crash (#1791) | +| Track T (Testing) | Active | Ongoing | HIGH | 68 open PRs need review; path traversal vulnerabilities (#1789, #1768) critical | #### Developer forecast @@ -4901,29 +4902,29 @@ Deadline risk: HIGH | Luis | -21d behind | active | HIGH | M6 (v3.5.0) features; server_connect fix (#1203); audit session (#1224); aiohttp CVE fix | | Hamza | -21d behind | active | HIGH | Resource DAG fix (#1228); v3.6.0 features; AWS CloudResource (#1280) | | Aditya | -21d behind | active | HIGH | M5 features; TDD counterparts; RendererRegistry (#1193); domain model refactor | -| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; UAT bug triage; 324 open bugs | +| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; UAT bug triage; 447 open bugs | | Rui | -21d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; flaky test fixes | | Mike/Brian | N/A | standby | LOW | N/A | #### Task inventory -Milestone per developer as of Day 54 end-of-day (2026-04-03). +Milestone per developer as of Day 54 updated (2026-04-03). | Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total | |-----------|------|--------|------|-------|-------|-----|------------|-------| | M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 | | M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 | -| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 78 open | 213/291 | -| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 27 open | 100/127 | -| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 26 open | 125/151 | -| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 76 open | 175/251 | -| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 68 open | 125/193 | -| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 335 open | 78/413 | -| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 265 open | 75/340 | +| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 81 open | 218/299 | +| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 30 open | 100/130 | +| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 38 open | 126/164 | +| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 85 open | 174/259 | +| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 97 open | 127/224 | +| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 365 open | 82/447 | +| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 261 open | 105/366 | | None | N/A | N/A | N/A | N/A | N/A | N/A | N/A | N/A | -| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~875 open** | **991/1862 closed** | +| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~957 open** | **1032/1989 closed** | -Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 54 end-of-day. Most open issues are unassigned or assigned to freemo (Jeff). Agents created 500+ new issues throughout Day 54; most are unassigned. M8 grew from 185→413, M9 grew from 242→340 due to agent-driven issue creation. +Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 54 updated. Most open issues are unassigned or assigned to freemo (Jeff). Agents created 500+ new issues throughout Day 54; most are unassigned. M8 grew from 185→447, M9 grew from 242→366 due to agent-driven issue creation. #### Story point allocation