docs(timeline): update schedule adherence Day 95 final (2026-04-05) #3391

Closed
freemo wants to merge 1 commit from docs/timeline-day95-final into master
Owner

Timeline Update — Day 95 Final (2026-04-05)

Updates the existing Day 95 schedule adherence entry with final end-of-day data reflecting significant agent-driven expansion across all milestones.

Key Changes

  • Open PRs: 92 → 115 (+23 new PRs opened)
  • Open bugs: 536 → 766 (+230 agent-driven expansion)
  • M3 (v3.2.0): 67% → 64% complete (228/357, was 223/334) — 129 open issues
  • M4 (v3.3.0): 63% → 60% complete (104/172, was 103/163) — 68 open issues
  • M5 (v3.4.0): 70% → 69% complete (126/183, was 126/179) — 57 open issues
  • M6 (v3.5.0): 67% → 55% complete (176/318, was 175/263) — 142 open issues
  • M7 (v3.6.0): 55% → 43% complete (130/305, was 127/232) — 175 open issues
  • M8 (v3.7.0): 52% → 43% complete (345/795, was 332/634) — 450 open issues
  • M9 (v3.8.0): 27% → 25% complete (117/462, was 105/393) — 345 open issues

Sections Updated

  • Gantt chart footer (bug/PR counts)
  • Gantt chart update log comment
  • Gantt chart risk register table
  • Gantt chart legend stat line (both charts)
  • Current Status Summary narrative
  • Day 95 Schedule Adherence entry (updated in-place, not duplicated)

Automated by CleverAgents Bot
Supervisor: Timeline | Agent: ca-timeline-updater

## Timeline Update — Day 95 Final (2026-04-05) Updates the existing Day 95 schedule adherence entry with final end-of-day data reflecting significant agent-driven expansion across all milestones. ### Key Changes - **Open PRs**: 92 → 115 (+23 new PRs opened) - **Open bugs**: 536 → 766 (+230 agent-driven expansion) - **M3 (v3.2.0)**: 67% → 64% complete (228/357, was 223/334) — 129 open issues - **M4 (v3.3.0)**: 63% → 60% complete (104/172, was 103/163) — 68 open issues - **M5 (v3.4.0)**: 70% → 69% complete (126/183, was 126/179) — 57 open issues - **M6 (v3.5.0)**: 67% → 55% complete (176/318, was 175/263) — 142 open issues - **M7 (v3.6.0)**: 55% → 43% complete (130/305, was 127/232) — 175 open issues - **M8 (v3.7.0)**: 52% → 43% complete (345/795, was 332/634) — 450 open issues - **M9 (v3.8.0)**: 27% → 25% complete (117/462, was 105/393) — 345 open issues ### Sections Updated - Gantt chart footer (bug/PR counts) - Gantt chart update log comment - Gantt chart risk register table - Gantt chart legend stat line (both charts) - Current Status Summary narrative - Day 95 Schedule Adherence entry (updated in-place, not duplicated) --- **Automated by CleverAgents Bot** Supervisor: Timeline | Agent: ca-timeline-updater
docs(timeline): update schedule adherence Day 95 final (2026-04-05)
All checks were successful
CI / status-check (pull_request) Successful in 1s
CI / benchmark-publish (pull_request) Has been skipped
CI / unit_tests (pull_request) Successful in 6m28s
CI / docker (pull_request) Successful in 11s
CI / coverage (pull_request) Successful in 10m18s
CI / e2e_tests (pull_request) Successful in 17m28s
CI / helm (pull_request) Successful in 23s
CI / lint (pull_request) Successful in 37s
CI / build (pull_request) Successful in 39s
CI / quality (pull_request) Successful in 40s
CI / integration_tests (pull_request) Successful in 22m21s
CI / typecheck (pull_request) Successful in 48s
CI / security (pull_request) Successful in 1m0s
CI / benchmark-regression (pull_request) Successful in 57m12s
9dccc0daa1
Author
Owner

Closing this PR as superseded by #3419, which contains more current Day 95 data (168 open PRs, 778 open bugs vs. 115/766 here). PR #3419 has been merged to master.


Automated by CleverAgents Bot
Supervisor: Implementation | Agent: ca-issue-worker

Closing this PR as superseded by #3419, which contains more current Day 95 data (168 open PRs, 778 open bugs vs. 115/766 here). PR #3419 has been merged to master. --- **Automated by CleverAgents Bot** Supervisor: Implementation | Agent: ca-issue-worker
freemo closed this pull request 2026-04-05 17:10:38 +00:00
All checks were successful
CI / status-check (pull_request) Successful in 1s
CI / benchmark-publish (pull_request) Has been skipped
CI / unit_tests (pull_request) Successful in 6m28s
Required
Details
CI / docker (pull_request) Successful in 11s
Required
Details
CI / coverage (pull_request) Successful in 10m18s
Required
Details
CI / e2e_tests (pull_request) Successful in 17m28s
CI / helm (pull_request) Successful in 23s
CI / lint (pull_request) Successful in 37s
Required
Details
CI / build (pull_request) Successful in 39s
Required
Details
CI / quality (pull_request) Successful in 40s
Required
Details
CI / integration_tests (pull_request) Successful in 22m21s
Required
Details
CI / typecheck (pull_request) Successful in 48s
Required
Details
CI / security (pull_request) Successful in 1m0s
Required
Details
CI / benchmark-regression (pull_request) Successful in 57m12s

Pull request closed

Sign in to join this conversation.
No reviewers
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core!3391
No description provided.