TEST-INFRA: [ci-pipeline-design] Parallelize CI jobs to improve pipeline speed #1650

Closed
opened 2026-04-02 23:23:10 +00:00 by freemo · 3 comments
Owner

Metadata

  • Branch: task/ci-parallelize-jobs-pipeline-speed
  • Commit Message: ci(pipeline): parallelize independent CI jobs to reduce overall pipeline execution time
  • Milestone: v3.7.0
  • Parent Epic: (to be linked — see orphan notice below)

Background and Context

The current CI pipeline in .forgejo/workflows/ci.yml runs most jobs sequentially. This slows down the pipeline unnecessarily. Many jobs — such as lint, typecheck, security, quality, unit_tests, and integration_tests — are independent of each other and can be run in parallel. Reducing pipeline execution time improves developer feedback loops and CI resource utilisation.

Subtasks

  • Analyze the dependencies between all jobs in .forgejo/workflows/ci.yml
  • Identify which jobs are truly independent and can run in parallel without ordering constraints
  • Modify ci.yml to run independent jobs (e.g. lint, typecheck, security, quality) in parallel
  • Use the needs keyword to define correct execution order for jobs that have genuine dependencies (e.g. coverage, docker depending on test jobs)
  • Validate that no circular or unintended blocking dependencies are introduced
  • Trigger a CI run to confirm the new parallel configuration executes successfully
  • Run nox (all default sessions), fix any errors
  • Verify coverage >= 97% via nox -s coverage_report

Definition of Done

This issue is complete when:

  • All subtasks above are completed and checked off
  • The CI pipeline runs successfully end-to-end with the new parallel configuration
  • The overall pipeline execution time is measurably reduced compared to the sequential baseline
  • The ci.yml file is updated to reflect the new parallel execution flow with correct needs declarations
  • A Git commit is created where the first line of the commit message matches the Commit Message in Metadata exactly
  • The commit is pushed to the remote on the branch matching the Branch in Metadata exactly
  • The commit is submitted as a pull request to master, reviewed, and merged
  • All nox stages pass
  • Coverage >= 97%

⚠️ Orphan Notice: No parent TEST-INFRA Epic was found in the repository. This issue requires manual linking to an appropriate parent Epic by the project owner before work begins.


Automated by CleverAgents Bot
Supervisor: Test Infrastructure | Agent: ca-new-issue-creator

## Metadata - **Branch**: `task/ci-parallelize-jobs-pipeline-speed` - **Commit Message**: `ci(pipeline): parallelize independent CI jobs to reduce overall pipeline execution time` - **Milestone**: v3.7.0 - **Parent Epic**: *(to be linked — see orphan notice below)* ## Background and Context The current CI pipeline in `.forgejo/workflows/ci.yml` runs most jobs sequentially. This slows down the pipeline unnecessarily. Many jobs — such as `lint`, `typecheck`, `security`, `quality`, `unit_tests`, and `integration_tests` — are independent of each other and can be run in parallel. Reducing pipeline execution time improves developer feedback loops and CI resource utilisation. ## Subtasks - [ ] Analyze the dependencies between all jobs in `.forgejo/workflows/ci.yml` - [ ] Identify which jobs are truly independent and can run in parallel without ordering constraints - [ ] Modify `ci.yml` to run independent jobs (e.g. `lint`, `typecheck`, `security`, `quality`) in parallel - [ ] Use the `needs` keyword to define correct execution order for jobs that have genuine dependencies (e.g. `coverage`, `docker` depending on test jobs) - [ ] Validate that no circular or unintended blocking dependencies are introduced - [ ] Trigger a CI run to confirm the new parallel configuration executes successfully - [ ] Run `nox` (all default sessions), fix any errors - [ ] Verify coverage >= 97% via `nox -s coverage_report` ## Definition of Done This issue is complete when: - [ ] All subtasks above are completed and checked off - [ ] The CI pipeline runs successfully end-to-end with the new parallel configuration - [ ] The overall pipeline execution time is measurably reduced compared to the sequential baseline - [ ] The `ci.yml` file is updated to reflect the new parallel execution flow with correct `needs` declarations - [ ] A Git commit is created where the **first line** of the commit message matches the Commit Message in Metadata exactly - [ ] The commit is pushed to the remote on the branch matching the **Branch** in Metadata exactly - [ ] The commit is submitted as a **pull request** to `master`, reviewed, and **merged** - [ ] All nox stages pass - [ ] Coverage >= 97% --- > ⚠️ **Orphan Notice**: No parent TEST-INFRA Epic was found in the repository. This issue requires manual linking to an appropriate parent Epic by the project owner before work begins. --- **Automated by CleverAgents Bot** Supervisor: Test Infrastructure | Agent: ca-new-issue-creator
freemo added this to the v3.7.0 milestone 2026-04-02 23:24:10 +00:00
Author
Owner

⚠️ Orphan Issue — Manual Linking Required

This issue was created without a parent Epic because no TEST-INFRA or CI-pipeline-design Epic currently exists in the repository. Per CONTRIBUTING.md, orphan issues are not permitted — every issue must be linked to a parent Epic.

Action required by project owner:

  1. Identify or create an appropriate parent Epic for TEST-INFRA / CI pipeline improvement work.
  2. Link this issue as a child of that Epic using Forgejo's dependency system (this issue should block the parent Epic).

The dependency link should be created as:

POST /api/v1/repos/cleveragents/cleveragents-core/issues/1650/blocks
{ "dependency_id": <PARENT_EPIC_NUMBER> }

Automated by CleverAgents Bot
Supervisor: Test Infrastructure | Agent: ca-new-issue-creator

⚠️ **Orphan Issue — Manual Linking Required** This issue was created without a parent Epic because no TEST-INFRA or CI-pipeline-design Epic currently exists in the repository. Per `CONTRIBUTING.md`, orphan issues are not permitted — every issue must be linked to a parent Epic. **Action required by project owner:** 1. Identify or create an appropriate parent Epic for TEST-INFRA / CI pipeline improvement work. 2. Link this issue as a child of that Epic using Forgejo's dependency system (this issue should **block** the parent Epic). The dependency link should be created as: ``` POST /api/v1/repos/cleveragents/cleveragents-core/issues/1650/blocks { "dependency_id": <PARENT_EPIC_NUMBER> } ``` --- **Automated by CleverAgents Bot** Supervisor: Test Infrastructure | Agent: ca-new-issue-creator
Author
Owner

Closing as duplicate of #1604 (CI setup consolidation). This CI improvement is already tracked.


Automated by CleverAgents Bot
Supervisor: Project Owner | Agent: ca-project-owner

Closing as duplicate of #1604 (CI setup consolidation). This CI improvement is already tracked. --- **Automated by CleverAgents Bot** Supervisor: Project Owner | Agent: ca-project-owner
freemo 2026-04-02 23:30:59 +00:00
Author
Owner

Closing as duplicate. CI parallelization and execution time improvements are tracked in #1604 (setup consolidation), #1536 (parallelize static analysis), and #1632 (split integration tests).


Automated by CleverAgents Bot
Supervisor: Project Owner | Agent: ca-project-owner

Closing as duplicate. CI parallelization and execution time improvements are tracked in #1604 (setup consolidation), #1536 (parallelize static analysis), and #1632 (split integration tests). --- **Automated by CleverAgents Bot** Supervisor: Project Owner | Agent: ca-project-owner
Sign in to join this conversation.
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
cleveragents/cleveragents-core#1650
No description provided.