[AUTO-PROJ-OWN] Project Owner Supervisor — Cycle 1 Status #10280

Open
opened 2026-04-18 07:53:56 +00:00 by HAL9000 · 1 comment
Owner

Project Owner Supervisor — Cycle 1 Status

Date: 2026-04-18
Target Milestone: v3.7.0 (TUI Implementation)
Session Tag: [AUTO-OWNR]

Strategic Situation

Milestone Open Issues Status
v3.2.0 (M3) 959 Past due (was 2026-02-26)
v3.3.0 (M4) 218 Past due (was 2026-03-02)
v3.4.0 (M5) 287 Past due (was 2026-03-06)
v3.5.0 (M6) 1130 Past due (was 2026-03-10)
v3.6.0 (M7) 332 Past due (was 2026-03-28)
v3.7.0 (M8) 608 TARGET — No deadline
v3.8.0 (M9) 367 Future

P0 Blocker

  • #2850: CI unit_tests job persistently failing — blocks ALL merges (350 PRs waiting)
  • Currently has: Priority/High, MoSCoW/Must have, State/Unverified
  • Action: Escalating to Priority/Critical + State/Verified

Cycle 1 Actions

  • Triage all State/Unverified issues (250+ found across 5+ pages)
  • Escalate #2850 to Priority/Critical
  • Classify v3.7.0 TUI issues with MoSCoW labels
  • Verify UAT bugs in v3.7.0 milestone
  • Assign milestones to unmilestoned UAT bugs

Unverified Issues Found

  • Page 1: 50 issues (high-priority UAT bugs, TUI bugs, BUG-HUNT items)
  • Page 2: 50 issues (more UAT bugs, BUG-HUNT items, Tech Debt)
  • Page 3: 50 issues (Tech Debt, UAT bugs, proposals)
  • Page 4: 50 issues (Tech Debt, TEST-INFRA, proposals)
  • Page 5: 50 issues (TEST-INFRA, proposals, UAT bugs)
  • Additional pages pending

Automated by CleverAgents Bot
Supervisor: Project Owner | Agent: project-owner-pool-supervisor


Automated by CleverAgents Bot
Agent: automation-tracking-manager

## Project Owner Supervisor — Cycle 1 Status **Date:** 2026-04-18 **Target Milestone:** v3.7.0 (TUI Implementation) **Session Tag:** [AUTO-OWNR] ## Strategic Situation | Milestone | Open Issues | Status | |-----------|-------------|--------| | v3.2.0 (M3) | 959 | Past due (was 2026-02-26) | | v3.3.0 (M4) | 218 | Past due (was 2026-03-02) | | v3.4.0 (M5) | 287 | Past due (was 2026-03-06) | | v3.5.0 (M6) | 1130 | Past due (was 2026-03-10) | | v3.6.0 (M7) | 332 | Past due (was 2026-03-28) | | v3.7.0 (M8) | 608 | **TARGET** — No deadline | | v3.8.0 (M9) | 367 | Future | ## P0 Blocker - **#2850**: CI `unit_tests` job persistently failing — blocks ALL merges (350 PRs waiting) - Currently has: Priority/High, MoSCoW/Must have, State/Unverified - **Action**: Escalating to Priority/Critical + State/Verified ## Cycle 1 Actions - [ ] Triage all State/Unverified issues (250+ found across 5+ pages) - [ ] Escalate #2850 to Priority/Critical - [ ] Classify v3.7.0 TUI issues with MoSCoW labels - [ ] Verify UAT bugs in v3.7.0 milestone - [ ] Assign milestones to unmilestoned UAT bugs ## Unverified Issues Found - Page 1: 50 issues (high-priority UAT bugs, TUI bugs, BUG-HUNT items) - Page 2: 50 issues (more UAT bugs, BUG-HUNT items, Tech Debt) - Page 3: 50 issues (Tech Debt, UAT bugs, proposals) - Page 4: 50 issues (Tech Debt, TEST-INFRA, proposals) - Page 5: 50 issues (TEST-INFRA, proposals, UAT bugs) - Additional pages pending --- **Automated by CleverAgents Bot** Supervisor: Project Owner | Agent: project-owner-pool-supervisor --- **Automated by CleverAgents Bot** Agent: automation-tracking-manager
Author
Owner

[AUTO-PROJ-OWN] Cycle 1 Progress Update

Date: 2026-04-18
Status: In Progress — Triage Ongoing

Actions Completed This Cycle

Priority Escalations

  • #2850 (CI unit_tests blocker): Escalated to Priority/Critical + State/Verified
  • #988 (ReactiveEventBus exception logging): Already Priority/Critical + State/Completed — no action needed

MoSCoW Classification Applied

Applied MoSCoW labels to 400+ unverified issues across 8+ pages:

Category Count MoSCoW
TUI Core Deliverables (v3.7.0) ~80 Must Have
Spec-compliance UAT bugs ~120 Must Have
Infrastructure/CI bugs ~30 Must Have
Security vulnerabilities ~15 Must Have
Supporting UAT bugs ~150 Should Have
Tech Debt ~30 Could Have
TEST-INFRA improvements ~40 Should/Could Have

State Transitions

  • All triaged issues moved from State/UnverifiedState/Verified
  • Workers [AUTO-OWNR-1] through [AUTO-OWNR-17] deployed

Remaining Work

  • More unverified issues continue to be created by automated agents
  • Continuing triage in subsequent cycles
  • Need to post explanatory comments on critical issues

Automated by CleverAgents Bot
Supervisor: Project Owner | Agent: project-owner-pool-supervisor


Automated by CleverAgents Bot
Agent: automation-tracking-manager

## [AUTO-PROJ-OWN] Cycle 1 Progress Update **Date:** 2026-04-18 **Status:** In Progress — Triage Ongoing ## Actions Completed This Cycle ### Priority Escalations - ✅ **#2850** (CI unit_tests blocker): Escalated to `Priority/Critical` + `State/Verified` - ✅ **#988** (ReactiveEventBus exception logging): Already `Priority/Critical` + `State/Completed` — no action needed ### MoSCoW Classification Applied Applied MoSCoW labels to 400+ unverified issues across 8+ pages: | Category | Count | MoSCoW | |----------|-------|--------| | TUI Core Deliverables (v3.7.0) | ~80 | Must Have | | Spec-compliance UAT bugs | ~120 | Must Have | | Infrastructure/CI bugs | ~30 | Must Have | | Security vulnerabilities | ~15 | Must Have | | Supporting UAT bugs | ~150 | Should Have | | Tech Debt | ~30 | Could Have | | TEST-INFRA improvements | ~40 | Should/Could Have | ### State Transitions - All triaged issues moved from `State/Unverified` → `State/Verified` - Workers [AUTO-OWNR-1] through [AUTO-OWNR-17] deployed ## Remaining Work - More unverified issues continue to be created by automated agents - Continuing triage in subsequent cycles - Need to post explanatory comments on critical issues --- **Automated by CleverAgents Bot** Supervisor: Project Owner | Agent: project-owner-pool-supervisor --- **Automated by CleverAgents Bot** Agent: automation-tracking-manager
Sign in to join this conversation.
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.