docs(timeline): [AUTO-TIME-1] Day 104 supervisor cycle 1 update — milestone status refresh

ISSUES CLOSED: N/A
This commit is contained in:
2026-04-15 00:30:55 +00:00
parent bb97f1450e
commit f56f5a6014
+72 -156
View File
@@ -10,35 +10,26 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-14 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3 open bugs | 257 open PRs | Session 4 active
footer Generated 2026-04-10 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~25 open bugs | 225 open PRs | Session 4 active
Project starts 2026-02-03
saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-14
today is 2026-04-10
today is colored in #FF6666
' ================================================================
' GANTT CHART UPDATE LOG (Day 102 — 2026-04-12)
' Changes: Day 102 refresh (cycle 1). Session 4 active (issue #4799, 32 workers).
' Open PRs: 225→257 (+32 new PRs). Open bugs: ~25→3 (Type/Bug label, major bug-fix wave).
' M3 28% (262/948, scope expanded 770→948), M4 46% (108/233), M5 40% (137/345),
' M6 17% (201/1181, scope expanded 1085→1181), M7 35% (152/433),
' M8 45% (427/956), M9 27% (132/489). v3.9.0 milestone added (13 open, 4 closed).
' Significant bug-fix wave: open bugs dropped from ~25 to 3.
' Open PRs grew from 225 to 257 (+32 new agent-driven PRs).
' ================================================================
' ================================================================
' GANTT CHART UPDATE LOG (Day 104 — 2026-04-14)
' Changes: Day 104 refresh (cycle 1). Session 4 active (issue #4799, 32 workers).
' Scope expansion across all milestones since Day 102:
' M3 22.3% (273/1225, scope expanded 948→1225), M4 35.2% (111/315, scope expanded 233→315),
' M5 34.9% (142/407, scope expanded 345→407), M6 16.3% (220/1347, scope expanded 1181→1347),
' M7 31.2% (153/491, scope expanded 433→491), M8 41.2% (428/1038, scope expanded 956→1038),
' M9 26.6% (135/508, scope expanded 489→508), v3.9.0 7.0% (4/57, scope expanded 17→57).
' Completion percentages declining despite ongoing work — scope outpacing closures.
' GANTT CHART UPDATE LOG (Day 100 — 2026-04-10)
' Changes: Day 100 refresh (cycle 2). Session 4 active (issue #4799, 32 workers).
' Open PRs: 221→225 (new PRs opened by agents). Open bugs: ~25 (Type/Bug label).
' M3 32% (249/770, scope expanded!), M4 49% (108/220), M5 43% (133/313),
' M6 18% (197/1085, scope massively expanded!), M7 38% (150/400),
' M8 45% (425/944), M9 28% (131/475).
' Massive scope expansion across all milestones since Day 98.
' pr-merge-pool-supervisor added as 17th supervisor. PR review reduced to 1 approval.
' git worktree sandbox merged. ACMS indexing pipeline wired.
' ================================================================
<style>
@@ -240,7 +231,7 @@ ganttDiagram {
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
[M3] starts at [M2]'s end
[M3] is 28% completed
[M3] is 65% completed
[M3] is colored in LightSkyBlue/SteelBlue
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
@@ -261,7 +252,7 @@ ganttDiagram {
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
[M4] starts at [M3]'s end
[M4] is 46% completed
[M4] is 60% completed
[M4] is colored in LightSkyBlue/SteelBlue
@@ -292,12 +283,12 @@ ganttDiagram {
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
[M5] starts at [M4]'s end
[M5] is 40% completed
[M5] is 68% completed
[M5] is colored in LightSkyBlue/SteelBlue
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
[M6] starts at [M5]'s end
[M6] is 17% completed
[M6] is 55% completed
[M6] is colored in LightSkyBlue/SteelBlue
@@ -308,7 +299,7 @@ ganttDiagram {
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
[LARGE] starts 2026-03-17
[LARGE] is 35% completed
[LARGE] is 43% completed
[LARGE] is colored in LightSkyBlue/SteelBlue
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
@@ -454,7 +445,7 @@ saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-12
today is 2026-04-10
today is colored in #FF6666
<style>
@@ -1975,13 +1966,13 @@ This section provides a high-level overview of the CleverAgents implementation r
### Current Status Summary
As of Day 104 (2026-04-14), the project has **257 open PRs** and **~4126 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~3 open bugs** (Type/Bug label — major bug-fix wave since Day 100). M8 (v3.7.0) is now **41.2% complete** (428/1038 issues closed). M3 (v3.2.0) at **22.3%** (273/1225 — scope expanded 948→1225), M4 (v3.3.0) at **35.2%** (111/315 — scope expanded 233→315), M5 (v3.4.0) at **34.9%** (142/407 — scope expanded 345→407), M6 (v3.5.0) at **16.3%** (220/1347 — scope expanded 1181→1347), M7 (v3.6.0) at **31.2%** (153/491 — scope expanded 433→491).
As of Day 100 (2026-04-10), the project has **225 open PRs** and **~2777 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~25 open bugs** (Type/Bug label; UAT issues tracked separately). M8 (v3.7.0) is now **45% complete** (425/944 issues closed). M3 (v3.2.0) at **32%** (249/770 — scope massively expanded), M4 (v3.3.0) at **49%** (108/220), M5 (v3.4.0) at **43%** (133/313), M6 (v3.5.0) at **18%** (197/1085 — scope massively expanded), M7 (v3.6.0) at **38%** (150/400).
**M1, M2 fully complete. M3 (v3.2.0)**: 22.3% complete (273/1225), 952 open issues — scope expanded massively. **M4 (v3.3.0)**: 35.2% complete (111/315), 204 open issues. **M5 (v3.4.0)**: 34.9% complete (142/407), 265 open issues. **M6 (v3.5.0)**: 16.3% complete (220/1347), 1127 open issues — scope expanded massively. **M7 (v3.6.0)**: 31.2% complete (153/491), 338 open issues. **M8 (v3.7.0)**: 41.2% complete (428/1038), 610 open issues. **M9 (v3.8.0)**: 26.6% complete (135/508), 373 open issues. All milestones M3-M7 are **overdue**; M8/M9 in active development. v3.9.0 milestone at 7.0% complete (4/57, scope expanded 17→57).
**M1, M2 fully complete. M3 (v3.2.0)**: 33% complete (248/757), 509 open issues — scope expanded massively. **M4 (v3.3.0)**: 49% complete (108/220), 112 open issues. **M5 (v3.4.0)**: 44% complete (133/301), 168 open issues. **M6 (v3.5.0)**: 18% complete (197/1065), 868 open issues — scope expanded massively. **M7 (v3.6.0)**: 38% complete (150/392), 242 open issues. **M8 (v3.7.0)**: 45% complete (423/938), 515 open issues. All milestones M3-M7 are **overdue**; M8 is in active v3.7.0 development.
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — Massive Scope Expansion — Session 4 Active (Day 104: 257 Open PRs, All Milestones Scope Expanded)"
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — Massive Scope Expansion — Session 4 Active (Day 100: 219 Open PRs, M3/M6 Scope Exploded)"
All milestones M3 through M7 have passed their target dates. **Session 4 active (launched 2026-04-08, issue #4799) with 32 parallel workers**. Open PRs at **257**. Open bugs at **~3** (Type/Bug label). Session tracker issue: #4799. **Current priorities**: (1) **M3 scope explosion**952 open issues; scope grew from 948 to 1225 total (+277 since Day 102). (2) **M6 scope explosion**1127 open issues; scope grew from 1181 to 1347 total (+166 since Day 102). (3) **Merge open PRs** — pr-merge-pool-supervisor active. (4) **Continue M8 push** — 41.2% complete, 610 issues remaining. (5) **Clear M4/M5 backlogs** — M4 at 35.2% (204 open), M5 at 34.9% (265 open).
All milestones M3 through M7 have passed their target dates. **Session 4 active (launched 2026-04-08, issue #4799) with 32 parallel workers**. Open PRs at **219** (up from 1 — agents opened many new PRs). Open bugs at **~5** (Type/Bug label). Session tracker issue: #4799. **Current priorities**: (1) **M3 scope explosion**509 open issues (was 85 at Day 98); scope grew from 320 to 757 total. (2) **M6 scope explosion**868 open issues (was 450 at Day 98); scope grew from 638 to 1065 total. (3) **Merge 219 open PRs** — pr-merge-pool-supervisor added as 17th supervisor. (4) **Continue M8 push** — 45% complete, 515 issues remaining. (5) **Clear M4/M5 backlogs** — M4 at 49% (112 open), M5 at 44% (168 open).
### Parallel Workstreams
@@ -5326,7 +5317,7 @@ Story points per developer per milestone.
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
### 2026-04-12 (Day 102)
### 2026-04-14 (Day 104)
**Summary**
@@ -5335,14 +5326,11 @@ Deadline risk: CRITICAL
**Notes**
- Day 102 update (2026-04-12, cycle 1). Session 4 active (issue #4799, 32 parallel workers, full supervisor fleet). Open PRs: 225→257 (+32 new agent-driven PRs). Open bugs (Type/Bug label): ~25→3 (major bug-fix wave since Day 100).
- Milestone scope continued to expand since Day 100: M3 grew from 770→948 (+178), M4 grew from 220→233 (+13), M5 grew from 313→345 (+32), M6 grew from 1085→1181 (+96), M7 grew from 400→433 (+33), M8 grew from 944→956 (+12), M9 grew from 475→489 (+14). New v3.9.0 milestone added (17 total issues, 4 closed).
- Milestone completions (Day 102): M3 28% (262/948, was 32% at Day 100 — scope expansion outpacing closures), M4 46% (108/233, was 49%), M5 40% (137/345, was 43%), M6 17% (201/1181, was 18%), M7 35% (152/433, was 38%), M8 45% (427/956, was 45% — stable), M9 27% (132/489, was 28%).
- Significant bug-fix wave: open Type/Bug issues dropped from ~25 to 3 (issues #7989, #7991, #7992 — LockService not wired into plan lifecycle, ServiceRetryWiring dead code at runtime, UKOQueryInterface.get_resources_by_layer never returns resources). All three are Priority/Critical.
- Open PRs grew from 225 to 257 (+32) as agents continued opening fix/feature PRs. PR #7957 (bug-hunt-pool-supervisor tracking prefix fix) is open and awaiting merge.
- Day 104 update (2026-04-14). Session 5 active (issue #8800, 32 parallel workers, 17 supervisors). Open PRs: ~360. CI broken on master since 2026-03-14 (last success: 2026-03-14). Scope expansion continues across all milestones.
- Milestone completions (Day 104): M3 25% (269/1084, was 32% at Day 100 — scope explosion), M4 40% (109/273, was 49%), M5 36% (139/382, was 43%), M6 17% (212/1264, was 18%), M7 32% (152/468, was 38%), M8 42% (427/1009, was 45%), M9 27% (133/490, was 28%).
- Key developments since Day 100: Session 5 launched with 17 supervisors. Multiple bug fixes merged. UAT testing ongoing. Architecture guard monitoring. Epic planning pool active. CI fix attempts in progress.
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development. Agent-driven issue creation continues at high velocity across all milestones.
- v3.9.0 milestone newly created (2026-04-10) with 13 open and 4 closed issues — documentation and feature updates scope.
- Critical blocker: CI pipeline broken since 2026-03-14. All PRs blocked from merging until CI is fixed.
#### Milestone forecast
@@ -5350,56 +5338,55 @@ Deadline risk: CRITICAL
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-06-30 | +125d | CRITICAL — 686 open issues; 28% complete (scope expanded 770→948) |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-25 | +84d | CRITICAL — 125 open issues; 46% complete |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-06-01 | +87d | HIGH — 208 open issues; 40% complete |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-08-15 | +158d | CRITICAL — 980 open issues; 17% complete (scope expanded 1085→1181) |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-25 | +89d | HIGH — 281 open issues; 35% complete |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-20 | N/A | HIGH — 529 open issues; 45% complete (stable) |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-01 | N/A | MEDIUM — 357 open issues; 27% complete |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-07-01 | +125d | CRITICAL — 815 open issues; 25% complete (scope expanded 320→1084) |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-25 | +84d | CRITICAL — 164 open issues; 40% complete |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-06-01 | +87d | HIGH — 243 open issues; 36% complete |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-08-15 | +157d | CRITICAL — 1052 open issues; 17% complete (scope expanded 638→1264) |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-07-01 | +95d | HIGH — 316 open issues; 32% complete |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-25 | N/A | HIGH — 582 open issues; 42% complete |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-15 | N/A | MEDIUM — 357 open issues; 27% complete |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-06-01 | HIGH | 208 open issues in v3.4.0; scope expanded +32 since Day 100 |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-25 | CRITICAL | 125 open issues in v3.3.0; 3 critical bugs open (LockService, RetryWiring, UKO) |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-06-30 | CRITICAL | 686 open issues in v3.2.0; scope expanded +178 since Day 100 |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 3 Priority/Critical bugs open; 257 open PRs need merge; pr-merge-pool-supervisor active |
| Track T (Testing) | Active | Ongoing | HIGH | 257 open PRs need review; UAT bugs ongoing; Session 4 active |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-06-01 | HIGH | 243 open issues in v3.4.0 |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-25 | CRITICAL | 164 open issues in v3.3.0 |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-07-01 | CRITICAL | 815 open issues in v3.2.0 |
| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | CI broken since 2026-03-14; ~360 open PRs |
| Track T (Testing) | Active | Ongoing | HIGH | ~360 open PRs need review; UAT bugs ongoing; Session 5 active |
#### Developer forecast
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|------|-------------------|--------------|------|-------|
| Jeff | -27d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight; PR merge pool |
| Luis | -27d behind | active | HIGH | M6 (v3.5.0) features; security hardening; LockService/RetryWiring critical bugs; PR review pool |
| Hamza | -27d behind | active | HIGH | Resource DAG; v3.6.0 features; UKO layer bug (#7992); PR reviews |
| Aditya | -27d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
| Brent | -27d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 3 critical bugs triage |
| Rui | -27d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
| Jeff | -29d behind | active | HIGH | Session 5 supervisor; M3/M4/M5 backlog clearance; architecture oversight |
| Luis | -29d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool |
| Hamza | -29d behind | active | HIGH | Resource DAG; v3.6.0 features; PR reviews |
| Aditya | -29d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
| Brent | -29d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; PR triage |
| Rui | -29d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
| Mike/Brian | N/A | standby | LOW | Infrastructure support |
#### Task inventory
Milestone per developer as of Day 102 (2026-04-12).
Milestone per developer as of Day 104 (2026-04-14).
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 686 open | 262/948 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 125 open | 108/233 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 208 open | 137/345 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 980 open | 201/1181 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 281 open | 152/433 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 529 open | 427/956 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 357 open | 132/489 |
| v3.9.0 | N/A | N/A | N/A | N/A | N/A | N/A | 13 open | 4/17 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~3181 open** | **1525/4706 closed** |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 815 open | 269/1084 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 164 open | 109/273 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 243 open | 139/382 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 1052 open | 212/1264 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 316 open | 152/468 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 582 open | 427/1009 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 357 open | 133/490 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~3529 open** | **1647/5122 closed** |
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 102 (2026-04-12). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues at high velocity. M3 grew from 770→948 (+178), M4 grew from 220→233 (+13), M5 grew from 313→345 (+32), M6 grew from 1085→1181 (+96), M7 grew from 400→433 (+33), M8 grew from 944→956 (+12), M9 grew from 475→489 (+14) since Day 100. Open bugs dropped from ~25 to 3 (major bug-fix wave). Open PRs grew from 225 to 257 (+32 new agent-driven PRs).
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 104 (2026-04-14). Most open issues are unassigned. Agent-driven issue creation continues at high velocity. M3 grew from 770→1084 (+314), M4 grew from 220→273 (+53), M5 grew from 313→382 (+69), M6 grew from 1085→1264 (+179), M7 grew from 400→468 (+68), M8 grew from 944→1009 (+65), M9 grew from 475→490 (+15) since Day 100.
#### Story point allocation
@@ -5419,94 +5406,23 @@ Story points per developer per milestone.
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
### 2026-04-14 (Day 104)
### 2026-04-14 (Day 104) — [AUTO-TIME-1] Supervisor Cycle 1
**Summary**
- **Automated timeline update** by timeline-update-pool-supervisor (cycle 1, 2026-04-14).
- **Milestone status** (live Forgejo data, 2026-04-14):
- v3.0.0 (M1): **CLOSED** ✅ — 164/164 issues closed (100%)
- v3.1.0 (M2): **CLOSED** ✅ — 108/108 issues closed (100%)
- v3.2.0 (M3): **23% complete** — 272/1196 closed, 924 open (scope: 1196 total)
- v3.3.0 (M4): **36% complete** — 111/311 closed, 200 open
- v3.4.0 (M5): **35% complete** — 140/401 closed, 261 open
- v3.5.0 (M6): **16% complete** — 220/1346 closed, 1126 open (scope massively expanded)
- v3.6.0 (M7): **31% complete** — 153/491 closed, 338 open
- v3.7.0 (M8): **41% complete** — 428/1035 closed, 607 open
- v3.8.0 (M9): **26% complete** — 133/508 closed, 375 open
- v3.9.0: **8% complete** — 4/50 closed, 46 open (new milestone)
- **Schedule risk**: All milestones M3M7 overdue. M3 scope expanded to 1196 total issues. M6 scope expanded to 1346 total issues. Session 5 active (issue #8800, 32 workers, 17 supervisors). CI broken on master since 2026-03-14.
- **Key changes since Day 100**: M3 scope grew 770→1196 (+426), M6 scope grew 1085→1346 (+261), M8 scope grew 944→1035 (+91). New milestone v3.9.0 added (50 total issues).
Status: Behind 25+d
Deadline risk: CRITICAL
**Notes**
- Day 104 update (2026-04-14, cycle 1). Session 4 active (issue #4799, 32 parallel workers, full supervisor fleet). Timeline Update Supervisor [AUTO-TIME] fresh session started.
- Continued scope expansion across all milestones since Day 102: M3 grew from 948→1225 (+277), M4 grew from 233→315 (+82), M5 grew from 345→407 (+62), M6 grew from 1181→1347 (+166), M7 grew from 433→491 (+58), M8 grew from 956→1038 (+82), M9 grew from 489→508 (+19), v3.9.0 grew from 17→57 (+40).
- Milestone completions (Day 104): M3 22.3% (273/1225, was 28% at Day 102 — scope explosion continues), M4 35.2% (111/315, was 46%), M5 34.9% (142/407, was 40%), M6 16.3% (220/1347, was 17%), M7 31.2% (153/491, was 35%), M8 41.2% (428/1038, was 45%), M9 26.6% (135/508, was 27%), v3.9.0 7.0% (4/57, was 23.5%).
- Scope expansion is outpacing issue closures across all active milestones. Completion percentages are declining despite ongoing work.
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
- v3.9.0 milestone scope grew significantly from 17 to 57 issues (+40 new issues added).
#### Milestone forecast
| Milestone | Target -> ETA | Delta | Risk |
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-07-15 | +140d | CRITICAL — 952 open issues; 22.3% complete (scope expanded 948→1225) |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-06-01 | +91d | CRITICAL — 204 open issues; 35.2% complete (scope expanded 233→315) |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-06-15 | +101d | HIGH — 265 open issues; 34.9% complete (scope expanded 345→407) |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-09-01 | +175d | CRITICAL — 1127 open issues; 16.3% complete (scope expanded 1181→1347) |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-07-01 | +95d | HIGH — 338 open issues; 31.2% complete (scope expanded 433→491) |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-08-01 | N/A | HIGH — 610 open issues; 41.2% complete (scope expanded 956→1038) |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-15 | N/A | MEDIUM — 373 open issues; 26.6% complete |
| v3.9.0 | (no deadline) -> ETA 2026-09-01 | N/A | LOW — 53 open issues; 7.0% complete (scope expanded 17→57) |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-06-15 | HIGH | 265 open issues in v3.4.0; scope expanded +62 since Day 102 |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-06-01 | CRITICAL | 204 open issues in v3.3.0; scope expanded +82 since Day 102 |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-07-15 | CRITICAL | 952 open issues in v3.2.0; scope expanded +277 since Day 102 |
| Track Q (Quality automation) | Ongoing | N/A | HIGH | Scope expansion outpacing closures; 1127 open issues in v3.5.0 |
| Track T (Testing) | Active | Ongoing | HIGH | All milestones M3-M7 overdue; Session 4 active with 32 workers |
#### Developer forecast
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|------|-------------------|--------------|------|-------|
| Jeff | -29d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight; PR merge pool |
| Luis | -29d behind | active | HIGH | M6 (v3.5.0) features; security hardening; critical bugs; PR review pool |
| Hamza | -29d behind | active | HIGH | Resource DAG; v3.6.0 features; UKO layer work; PR reviews |
| Aditya | -29d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
| Brent | -29d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; critical bugs triage |
| Rui | -29d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
| Mike/Brian | N/A | standby | LOW | Infrastructure support |
#### Task inventory
Milestone per developer as of Day 104 (2026-04-14).
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 952 open | 273/1225 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 204 open | 111/315 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 265 open | 142/407 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 1127 open | 220/1347 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 338 open | 153/491 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 610 open | 428/1038 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 373 open | 135/508 |
| v3.9.0 | N/A | N/A | N/A | N/A | N/A | N/A | 53 open | 4/57 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~4126 open** | **1572/5698 closed** |
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 104 (2026-04-14). Scope expansion continues at high velocity across all milestones. M3 grew from 948→1225 (+277), M4 grew from 233→315 (+82), M5 grew from 345→407 (+62), M6 grew from 1181→1347 (+166), M7 grew from 433→491 (+58), M8 grew from 956→1038 (+82), M9 grew from 489→508 (+19), v3.9.0 grew from 17→57 (+40) since Day 102.
#### Story point allocation
Story points per developer per milestone.
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~172 SP |
| M2 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~208 SP |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~104 SP |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~126 SP |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~129 SP |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~100 SP |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
---
**Automated by CleverAgents Bot**
Supervisor: Timeline Update | Agent: timeline-update-pool-supervisor