Merge pull request 'docs(timeline): update schedule adherence Day 95 (2026-04-05) — refreshed with live data' (#3080) from docs/timeline-day95-update-2026-04-05 into master
CI / benchmark-publish (push) Waiting to run
CI / lint (push) Successful in 27s
CI / quality (push) Successful in 32s
CI / typecheck (push) Successful in 59s
CI / security (push) Successful in 58s
CI / benchmark-regression (push) Waiting to run
CI / build (push) Successful in 23s
CI / helm (push) Successful in 23s
CI / unit_tests (push) Successful in 6m51s
CI / docker (push) Successful in 11s
CI / coverage (push) Successful in 10m40s
CI / e2e_tests (push) Successful in 19m12s
CI / integration_tests (push) Successful in 23m9s
CI / status-check (push) Successful in 1s
CI / benchmark-publish (push) Waiting to run
CI / lint (push) Successful in 27s
CI / quality (push) Successful in 32s
CI / typecheck (push) Successful in 59s
CI / security (push) Successful in 58s
CI / benchmark-regression (push) Waiting to run
CI / build (push) Successful in 23s
CI / helm (push) Successful in 23s
CI / unit_tests (push) Successful in 6m51s
CI / docker (push) Successful in 11s
CI / coverage (push) Successful in 10m40s
CI / e2e_tests (push) Successful in 19m12s
CI / integration_tests (push) Successful in 23m9s
CI / status-check (push) Successful in 1s
This commit was merged in pull request #3080.
This commit is contained in:
+37
-36
@@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
|
||||
@startgantt
|
||||
|
||||
title CleverAgents Core — Epic-Level Project Schedule
|
||||
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 536 open bugs | 76 open PRs | Session 3 active
|
||||
footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 536 open bugs | 92 open PRs | Session 3 active
|
||||
|
||||
Project starts 2026-02-03
|
||||
saturday are closed
|
||||
@@ -22,12 +22,12 @@ today is colored in #FF6666
|
||||
|
||||
' ================================================================
|
||||
' GANTT CHART UPDATE LOG (Day 95 — 2026-04-05)
|
||||
' Changes: Day 95 update. Open PRs: 64→76 (+12). Open bugs: 389→536 (+147 agent-driven).
|
||||
' Changes: Day 95 update (refreshed). Open PRs: 76→92 (+16). Open bugs: 536 (stable).
|
||||
' Open issues: continued agent-driven expansion across all milestones.
|
||||
' M3 70% (222/317), M4 72% (101/141), M5 75% (126/169), M6 67% (175/263),
|
||||
' M3 67% (223/334), M4 63% (103/163), M5 70% (126/179), M6 67% (175/263),
|
||||
' M7 55% (127/232), M8 52% (332/634), M9 27% (105/393).
|
||||
' Session 3 active. UAT pool supervisor and spec updater agents running.
|
||||
' New session tracker issues: #2874 (progress report), #2875 (UAT pool), #2876 (spec updater).
|
||||
' Session tracker issue: #3075 (autonomous build progress report).
|
||||
' ================================================================
|
||||
|
||||
<style>
|
||||
@@ -398,11 +398,11 @@ legend right
|
||||
| v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs |
|
||||
| v3.6.0 | Mar 27 | 2 | 100 | Deferred work |
|
||||
----
|
||||
**Risk Register (Day 95 — 2026-04-05)**
|
||||
**Risk Register (Day 95 — 2026-04-05 refreshed)**
|
||||
|= Epic |= Completion |= Risk |= Blocker |
|
||||
| M3 (#357) | 70% | **CRITICAL** | 95 open issues in v3.2.0 |
|
||||
| M4 (#358) | 72% | **HIGH** | 40 open issues in v3.3.0 |
|
||||
| M5 (#359) | 75% | **HIGH** | 43 open issues in v3.4.0 |
|
||||
| M3 (#357) | 67% | **CRITICAL** | 111 open issues in v3.2.0 |
|
||||
| M4 (#358) | 63% | **CRITICAL** | 60 open issues in v3.3.0 |
|
||||
| M5 (#359) | 70% | **HIGH** | 53 open issues in v3.4.0 |
|
||||
| M6 (#360) | 67% | **HIGH** | 88 open issues in v3.5.0 |
|
||||
| M7 (#361) | 55% | **HIGH** | 105 open issues in v3.6.0 |
|
||||
| M8 (#362) | 52% | **HIGH** | 302 open issues in v3.7.0 (agent expansion) |
|
||||
@@ -418,7 +418,7 @@ legend right
|
||||
----
|
||||
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
|
||||
~1649 total story points | ~3300 estimated hours
|
||||
**536 open bugs — 76 open PRs — Session 3 active (16 workers, ~71 agents)**
|
||||
**536 open bugs — 92 open PRs — Session 3 active (16 workers, ~71 agents)**
|
||||
end legend
|
||||
|
||||
@endgantt
|
||||
@@ -4949,13 +4949,14 @@ Deadline risk: HIGH
|
||||
|
||||
**Notes**
|
||||
|
||||
- Day 95 update. Open PRs increased from 64 → 76 (+12 new PRs). Open bugs increased from 389 → 536 (+147 agent-driven expansion).
|
||||
- Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. New session tracker issues created: #2874 (autonomous build progress report), #2875 (UAT pool supervisor v3.7.0), #2876 (spec updater).
|
||||
- Milestone totals continued to grow due to agent-driven issue creation: M3 (296→317), M4 (130→141), M5 (163→169), M6 (259→263), M7 (213→232), M8 (438→634), M9 (359→393).
|
||||
- Milestone completions (Day 95): M3 70% (222/317), M4 72% (101/141), M5 75% (126/169), M6 67% (175/263), M7 55% (127/232), M8 52% (332/634), M9 27% (105/393).
|
||||
- M8 (v3.7.0) made significant progress: 19% → 52% complete (81→332 closed issues), though milestone also expanded from 438→634 total issues.
|
||||
- Day 95 update (refreshed 2026-04-05). Open PRs: 92 (up from 76 earlier today, +16 new PRs). Open bugs: 536 (stable). Session tracker issue: #3075.
|
||||
- Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. UAT pool supervisor, PR reviewer pool, implementation pool, and spec updater agents all running.
|
||||
- Milestone totals continued to grow due to agent-driven issue creation: M3 (317→334), M4 (141→163), M5 (169→179), M6 (263 stable), M7 (232 stable), M8 (634 stable), M9 (393 stable).
|
||||
- Milestone completions (Day 95 refreshed): M3 67% (223/334), M4 63% (103/163), M5 70% (126/179), M6 67% (175/263), M7 55% (127/232), M8 52% (332/634), M9 27% (105/393).
|
||||
- M3 and M4 completion percentages declined from earlier Day 95 reading (M3: 70%→67%, M4: 72%→63%) because agent-driven issue creation is outpacing closures.
|
||||
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
|
||||
- UAT pool supervisor (#2875) and spec updater (#2876) agents are running autonomously, continuing to discover and file spec compliance issues.
|
||||
- UAT pool supervisor (#3075) and spec updater agents are running autonomously, continuing to discover and file spec compliance issues.
|
||||
- PR #3073 (docs/timeline-day95-refresh) is open with updated milestone data — this entry supersedes it.
|
||||
|
||||
|
||||
#### Milestone forecast
|
||||
@@ -4964,35 +4965,35 @@ Deadline risk: HIGH
|
||||
|-----------|---------------|-------|------|
|
||||
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
|
||||
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-04-25 | +58d | CRITICAL |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-04-28 | +57d | HIGH |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-04-28 | +53d | HIGH |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-05 | +56d | HIGH |
|
||||
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-05-20 | +53d | HIGH |
|
||||
| M8 (v3.7.0) | (no deadline) -> ETA 2026-06-15 | N/A | HIGH |
|
||||
| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-05 | N/A | MEDIUM |
|
||||
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-04-28 | +61d | CRITICAL — 111 open issues; agent-driven expansion outpacing closures |
|
||||
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-02 | +61d | CRITICAL — 60 open issues; completion dropped 72%→63% |
|
||||
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-02 | +57d | HIGH — 53 open issues; 70% complete |
|
||||
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-10 | +61d | HIGH — 88 open issues; 67% complete |
|
||||
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-05-25 | +58d | HIGH — 105 open issues; 55% complete |
|
||||
| M8 (v3.7.0) | (no deadline) -> ETA 2026-06-20 | N/A | HIGH — 302 open issues; 52% complete |
|
||||
| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-10 | N/A | MEDIUM — 288 open issues; 27% complete |
|
||||
|
||||
#### Track forecast
|
||||
|
||||
| Track | Status | ETA | Risk | Blocking |
|
||||
|-------|--------|-----|------|----------|
|
||||
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
|
||||
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-04-28 | MEDIUM | 43 open issues in v3.4.0; continued agent-driven expansion |
|
||||
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-04-28 | HIGH | 40 open issues in v3.3.0; UAT spec compliance bugs ongoing |
|
||||
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-04-25 | HIGH | 95 open issues in v3.2.0; agent-driven expansion |
|
||||
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-02 | MEDIUM | 53 open issues in v3.4.0; continued agent-driven expansion |
|
||||
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-02 | CRITICAL | 60 open issues in v3.3.0; UAT spec compliance bugs ongoing; completion dropped |
|
||||
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-04-28 | CRITICAL | 111 open issues in v3.2.0; agent-driven expansion outpacing closures |
|
||||
| Track Q (Quality automation) | Ongoing | N/A | HIGH | 536 open bugs; continued agent-driven bug creation |
|
||||
| Track T (Testing) | Active | Ongoing | HIGH | 76 open PRs need review; UAT pool supervisor active (#2875) |
|
||||
| Track T (Testing) | Active | Ongoing | HIGH | 92 open PRs need review; UAT pool supervisor active (#3075) |
|
||||
|
||||
#### Developer forecast
|
||||
|
||||
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|
||||
|------|-------------------|--------------|------|-------|
|
||||
| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance |
|
||||
| Luis | -21d behind | active | HIGH | M6 (v3.5.0) features; security hardening; audit session |
|
||||
| Hamza | -21d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource |
|
||||
| Aditya | -21d behind | active | HIGH | M5 features; TDD counterparts; domain model work |
|
||||
| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance; 92 open PRs |
|
||||
| Luis | -21d behind | active | HIGH | M6 (v3.5.0) features; security hardening; audit session; PR review pool |
|
||||
| Hamza | -21d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews |
|
||||
| Aditya | -21d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
|
||||
| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 536 open bugs triage |
|
||||
| Rui | -21d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt |
|
||||
| Rui | -21d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
|
||||
| Mike/Brian | N/A | standby | LOW | N/A |
|
||||
|
||||
#### Task inventory
|
||||
@@ -5003,16 +5004,16 @@ Milestone per developer as of Day 95 (2026-04-05).
|
||||
|-----------|------|--------|------|-------|-------|-----|------------|-------|
|
||||
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
|
||||
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 95 open | 222/317 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 40 open | 101/141 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 43 open | 126/169 |
|
||||
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 111 open | 223/334 |
|
||||
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 60 open | 103/163 |
|
||||
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 53 open | 126/179 |
|
||||
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 88 open | 175/263 |
|
||||
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 105 open | 127/232 |
|
||||
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 302 open | 332/634 |
|
||||
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 288 open | 105/393 |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~961 open** | **1294/2245 closed** |
|
||||
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1007 open** | **1191/2198 closed** |
|
||||
|
||||
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95. Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M8 grew from 438→634, M9 grew from 359→393 due to continued agent activity.
|
||||
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 (refreshed 2026-04-05). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues across all milestones. M3 grew from 317→334, M4 grew from 141→163, M5 grew from 169→179 due to continued agent activity.
|
||||
|
||||
#### Story point allocation
|
||||
|
||||
|
||||