From c81afea06b00a8dbd1e2bc7d528dc6772bf8e613 Mon Sep 17 00:00:00 2001 From: Jeffrey Phillips Freeman Date: Thu, 2 Apr 2026 19:48:26 +0000 Subject: [PATCH] docs(timeline): update schedule adherence Day 53 (2026-04-02) MIME-Version: 1.0 Content-Type: text/plain; charset=UTF-8 Content-Transfer-Encoding: 8bit End-of-day refresh: UAT supervisor fleet (cycles 11-131) discovered 100+ spec compliance bugs, surging open bug count from 50 to 155. M8 (v3.7.0) net regression from 60% to 55% (36/65) due to 29 new UAT issues. Updated milestone completion rates, gantt chart legend, risk register, current status summary, and schedule adherence entry with end-of-day data. Key changes: - Open bugs: 50 → 155 (+105 UAT discoveries) - Open PRs: 47 → 50 (+3 new UAT/bug PRs) - Open issues: 289 → 362 (+73 new UAT/refactor/bug issues) - M3 83% (190/227), M4 77% (89/115), M5 88% (126/143) - M6 78% (165/211), M7 75% (114/152), M8 55% (36/65), M9 42% (17/40) --- docs/timeline.md | 118 +++++++++++++++++++++++------------------------ 1 file changed, 59 insertions(+), 59 deletions(-) diff --git a/docs/timeline.md b/docs/timeline.md index d92538a31..c531f8dcb 100644 --- a/docs/timeline.md +++ b/docs/timeline.md @@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto @startgantt title CleverAgents Core — Epic-Level Project Schedule -footer Generated 2026-04-02 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 50 open bugs | 47 open PRs | Session 3 active +footer Generated 2026-04-02 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 155 open bugs | 50 open PRs | Session 3 active Project starts 2026-02-03 saturday are closed @@ -21,12 +21,12 @@ today is 2026-04-02 today is colored in #FF6666 ' ================================================================ -' GANTT CHART UPDATE LOG (Day 53 — updated mid-day refresh, v3.7.0 push) -' Changes: Session 3 active. 55+ PRs merged since session start. Open PRs: 45→47 (+2 new). -' Open issues: 274→289 (+15 new UAT/refactor issues in v3.7.0). Open bugs: 50 (stable). -' M3 84% (194/229), M4 78% (97/124), M5 88% (126/142), M6 78% (164/209), -' M7 76% (113/148), M8 60% (36/60), M9 42% (17/40). -' v3.7.0 (M8) push: 30 new UAT/refactor issues added; TUI PRs #1302/#1294/#1268 open. +' GANTT CHART UPDATE LOG (Day 53 — end-of-day refresh, v3.7.0 UAT wave) +' Changes: Session 3 active. 55+ PRs merged. Open PRs: 47→50 (+3 new UAT/bug PRs). +' Open issues: 289→362 (+73 new UAT/refactor/bug issues). Open bugs: 50→155 (+105 UAT discoveries). +' M3 83% (190/227), M4 77% (89/115), M5 88% (126/143), M6 78% (165/211), +' M7 75% (114/152), M8 55% (36/65), M9 42% (17/40). +' v3.7.0 UAT wave: 100+ new UAT bug issues opened by UAT supervisor fleet (cycles 11-131). ' ================================================================