docs(timeline): update schedule adherence Day 101 (2026-04-12)
CI / unit_tests (pull_request) Waiting to run
CI / lint (pull_request) Waiting to run
CI / typecheck (pull_request) Waiting to run
CI / security (pull_request) Waiting to run
CI / quality (pull_request) Waiting to run
CI / integration_tests (pull_request) Waiting to run
CI / e2e_tests (pull_request) Waiting to run
CI / coverage (pull_request) Blocked by required conditions
CI / benchmark-regression (pull_request) Blocked by required conditions
CI / benchmark-publish (pull_request) Waiting to run
CI / build (pull_request) Waiting to run
CI / docker (pull_request) Blocked by required conditions
CI / helm (pull_request) Waiting to run
CI / push-validation (pull_request) Waiting to run
CI / status-check (pull_request) Blocked by required conditions

This commit is contained in:
2026-04-12 05:39:33 +00:00
parent 35ff97a641
commit a8b0670f57
+122 -34
View File
@@ -10,26 +10,25 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-10 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~25 open bugs | 225 open PRs | Session 4 active
footer Generated 2026-04-12 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~206 open bugs | 251 open PRs | Session 4 active
Project starts 2026-02-03
saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-10
today is 2026-04-12
today is colored in #FF6666
' ================================================================
' GANTT CHART UPDATE LOG (Day 100 — 2026-04-10)
' Changes: Day 100 refresh (cycle 2). Session 4 active (issue #4799, 32 workers).
' Open PRs: 221→225 (new PRs opened by agents). Open bugs: ~25 (Type/Bug label).
' M3 32% (249/770, scope expanded!), M4 49% (108/220), M5 43% (133/313),
' M6 18% (197/1085, scope massively expanded!), M7 38% (150/400),
' M8 45% (425/944), M9 28% (131/475).
' Massive scope expansion across all milestones since Day 98.
' pr-merge-pool-supervisor added as 17th supervisor. PR review reduced to 1 approval.
' git worktree sandbox merged. ACMS indexing pipeline wired.
' GANTT CHART UPDATE LOG (Day 101 — 2026-04-12)
' Changes: Day 101 refresh. Session 4 active (issue #4799, 32 workers).
' Open PRs: 225→251 (+26 new PRs opened by agents). Open bugs: ~206 (Type/Bug label, up from ~25).
' M3 28% (258/926, scope expanded 770→926), M4 47% (108/230, scope expanded 220→230),
' M5 40% (137/341, scope expanded 313→341), M6 17% (201/1178, scope expanded 1085→1178),
' M7 35% (152/432, scope expanded 400→432), M8 45% (427/953), M9 27% (132/489).
' Continued scope expansion across all milestones. Bug count surged from ~25 to ~206.
' Recent merges: docs(timeline) Day 100, automation-tracking-manager docs, actor context showcase.
' ================================================================
<style>
@@ -231,7 +230,7 @@ ganttDiagram {
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
[M3] starts at [M2]'s end
[M3] is 65% completed
[M3] is 28% completed
[M3] is colored in LightSkyBlue/SteelBlue
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
@@ -252,7 +251,7 @@ ganttDiagram {
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
[M4] starts at [M3]'s end
[M4] is 60% completed
[M4] is 47% completed
[M4] is colored in LightSkyBlue/SteelBlue
@@ -283,12 +282,12 @@ ganttDiagram {
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
[M5] starts at [M4]'s end
[M5] is 68% completed
[M5] is 40% completed
[M5] is colored in LightSkyBlue/SteelBlue
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
[M6] starts at [M5]'s end
[M6] is 55% completed
[M6] is 17% completed
[M6] is colored in LightSkyBlue/SteelBlue
@@ -299,7 +298,7 @@ ganttDiagram {
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
[LARGE] starts 2026-03-17
[LARGE] is 43% completed
[LARGE] is 35% completed
[LARGE] is colored in LightSkyBlue/SteelBlue
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
@@ -401,15 +400,15 @@ legend right
| v3.5.0 | Mar 10 | 2 | 151 | Autonomy hardening + server stubs |
| v3.6.0 | Mar 27 | 2 | 100 | Deferred work |
----
**Risk Register (Day 100 — 2026-04-10)**
**Risk Register (Day 101 — 2026-04-12)**
|= Epic |= Completion |= Risk |= Blocker |
| M3 (#357) | 32% | **CRITICAL** | 521 open issues in v3.2.0 (scope expanded 320→770) |
| M4 (#358) | 49% | **CRITICAL** | 112 open issues in v3.3.0 |
| M5 (#359) | 43% | **HIGH** | 180 open issues in v3.4.0 |
| M6 (#360) | 18% | **CRITICAL** | 888 open issues in v3.5.0 (massive scope expansion) |
| M7 (#361) | 38% | **HIGH** | 250 open issues in v3.6.0 |
| M8 (#362) | 45% | **HIGH** | 519 open issues in v3.7.0 |
| SEC (#363) | 28% | **HIGH** | 344 open issues in v3.8.0 |
| M3 (#357) | 28% | **CRITICAL** | 668 open issues in v3.2.0 (scope expanded 770→926) |
| M4 (#358) | 47% | **CRITICAL** | 122 open issues in v3.3.0 |
| M5 (#359) | 40% | **HIGH** | 204 open issues in v3.4.0 |
| M6 (#360) | 17% | **CRITICAL** | 977 open issues in v3.5.0 (scope expanded 1085→1178) |
| M7 (#361) | 35% | **HIGH** | 280 open issues in v3.6.0 |
| M8 (#362) | 45% | **HIGH** | 526 open issues in v3.7.0 |
| SEC (#363) | 27% | **HIGH** | 357 open issues in v3.8.0 |
----
**Color Key**
|= Color |= Meaning |
@@ -417,11 +416,11 @@ legend right
| <back:LightSkyBlue> </back> | In Progress |
| <back:#E8E8E8> </back> | Not Started |
| <back:Gold> <> </back> | Milestone Target |
| <back:#FF6666> | </back> | Today (2026-04-10) |
| <back:#FF6666> | </back> | Today (2026-04-12) |
----
29 Epics | 9 Legendaries | 7 Milestones | 6 Developers
~1649 total story points | ~3300 estimated hours
**~25 open bugs (Type/Bug) — 225 open PRs — Session 4 active (32 workers)**
**~206 open bugs (Type/Bug) — 251 open PRs — Session 4 active (32 workers)**
end legend
@endgantt
@@ -445,7 +444,7 @@ saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-10
today is 2026-04-12
today is colored in #FF6666
<style>
@@ -1932,7 +1931,7 @@ legend right
| Brent (brent.edwards) | Quality / QA | 170 | ~340h |
| Rui (hurui200320) | Testing | 8 | ~16h |
----
**Per-Milestone (done/total issues) — Day 37**
**Per-Milestone (done/total issues) — Day 101**
|= Dev |= v3.0 |= v3.1 |= v3.2 |= v3.3 |= v3.4 |= v3.5 |= v3.6 |
| Jeff | Done | Done | 12/16 | 9/10 | 22/22 | 14/18 | 0/5 |
| Luis | Done | Done | 2/5 | 4/7 | 2/2 | 7/11 | 0/4 |
@@ -1950,11 +1949,11 @@ legend right
| <back:LightSkyBlue> </back> | Issue: In Progress |
| <back:#E8E8E8> </back> | Issue: Not Started |
| <back:Gold> <> </back> | Milestone Target |
| <back:#FF6666> | </back> | Today (2026-04-10) |
| <back:#FF6666> | </back> | Today (2026-04-12) |
----
271 Issues | 29 Epics | 9 Legendaries | 7 Milestones
~1649 total story points | ~3300 estimated hours
**~5 open bugs (Type/Bug) — 219 open PRs — Session 4 active (32 workers)**
**~206 open bugs (Type/Bug) — 251 open PRs — Session 4 active (32 workers)**
end legend
@endgantt
@@ -1966,13 +1965,13 @@ This section provides a high-level overview of the CleverAgents implementation r
### Current Status Summary
As of Day 100 (2026-04-10), the project has **225 open PRs** and **~2777 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~25 open bugs** (Type/Bug label; UAT issues tracked separately). M8 (v3.7.0) is now **45% complete** (425/944 issues closed). M3 (v3.2.0) at **32%** (249/770 — scope massively expanded), M4 (v3.3.0) at **49%** (108/220), M5 (v3.4.0) at **43%** (133/313), M6 (v3.5.0) at **18%** (197/1085 — scope massively expanded), M7 (v3.6.0) at **38%** (150/400).
As of Day 101 (2026-04-12), the project has **251 open PRs** and **~2338 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~206 open bugs** (Type/Bug label; surged from ~25 — UAT bug-hunt wave ongoing). M8 (v3.7.0) is now **45% complete** (427/953 issues closed). M3 (v3.2.0) at **28%** (258/926 — scope expanded 770→926), M4 (v3.3.0) at **47%** (108/230), M5 (v3.4.0) at **40%** (137/341), M6 (v3.5.0) at **17%** (201/1178 — scope expanded 1085→1178), M7 (v3.6.0) at **35%** (152/432).
**M1, M2 fully complete. M3 (v3.2.0)**: 33% complete (248/757), 509 open issues — scope expanded massively. **M4 (v3.3.0)**: 49% complete (108/220), 112 open issues. **M5 (v3.4.0)**: 44% complete (133/301), 168 open issues. **M6 (v3.5.0)**: 18% complete (197/1065), 868 open issues — scope expanded massively. **M7 (v3.6.0)**: 38% complete (150/392), 242 open issues. **M8 (v3.7.0)**: 45% complete (423/938), 515 open issues. All milestones M3-M7 are **overdue**; M8 is in active v3.7.0 development.
**M1, M2 fully complete. M3 (v3.2.0)**: 28% complete (258/926), 668 open issues — scope expanded massively. **M4 (v3.3.0)**: 47% complete (108/230), 122 open issues. **M5 (v3.4.0)**: 40% complete (137/341), 204 open issues. **M6 (v3.5.0)**: 17% complete (201/1178), 977 open issues — scope expanded massively. **M7 (v3.6.0)**: 35% complete (152/432), 280 open issues. **M8 (v3.7.0)**: 45% complete (427/953), 526 open issues. All milestones M3-M7 are **overdue**; M8 is in active v3.7.0 development.
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — Massive Scope Expansion — Session 4 Active (Day 100: 219 Open PRs, M3/M6 Scope Exploded)"
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — Massive Scope Expansion — Session 4 Active (Day 101: 251 Open PRs, ~206 Open Bugs, M3/M6 Scope Exploded)"
All milestones M3 through M7 have passed their target dates. **Session 4 active (launched 2026-04-08, issue #4799) with 32 parallel workers**. Open PRs at **219** (up from 1 — agents opened many new PRs). Open bugs at **~5** (Type/Bug label). Session tracker issue: #4799. **Current priorities**: (1) **M3 scope explosion**509 open issues (was 85 at Day 98); scope grew from 320 to 757 total. (2) **M6 scope explosion**868 open issues (was 450 at Day 98); scope grew from 638 to 1065 total. (3) **Merge 219 open PRs** — pr-merge-pool-supervisor added as 17th supervisor. (4) **Continue M8 push** — 45% complete, 515 issues remaining. (5) **Clear M4/M5 backlogs** — M4 at 49% (112 open), M5 at 44% (168 open).
All milestones M3 through M7 have passed their target dates. **Session 4 active (launched 2026-04-08, issue #4799) with 32 parallel workers**. Open PRs at **251** (up from 225 — agents opened 26 new PRs). Open bugs at **~206** (Type/Bug label; surged from ~25 — UAT bug-hunt wave). Session tracker issue: #4799. **Current priorities**: (1) **M3 scope explosion**668 open issues; scope grew from 770 to 926 total. (2) **M6 scope explosion**977 open issues; scope grew from 1085 to 1178 total. (3) **Merge 251 open PRs** — pr-merge-pool-supervisor active. (4) **Triage ~206 open bugs** — UAT bug-hunt wave ongoing. (5) **Clear M4/M5 backlogs** — M4 at 47% (122 open), M5 at 40% (204 open).
### Parallel Workstreams
@@ -2078,6 +2077,7 @@ The following major areas are fully or substantially implemented:
- **Day 95 end-of-day merges — 5 PRs merged (Day 95, 2026-04-05)**: Additional spec compliance and fix PRs merged. Key merges: fix(cli) render spec-required panels in agents plan rollback rich output (#3279, v3.5.0, fixes #3445), fix(cli) add spec-required Validation and Merge panels and correct title/message in plan apply (#3460, v3.5.0), fix(cli) compute real impact counts in agents actor remove command (#3463, v3.5.0), fix(session) correct field names and data types in Session.as_cli_dict() for spec compliance (#3461, v3.5.0), fix(providers) remove type: ignore suppressions from registry.py and resolve underlying type errors (#3459, v3.5.0). Open PRs: 170→179 (+9 new agent PRs). Open bugs: 809→866 (+57 new UAT/bug-hunt bugs). M8 milestone grew from 796→822 issues.
- **Day 96 session launch — 75 PRs merged/closed (Day 96, 2026-04-06)**: Session 3 new build session launched (issue #3775). Massive PR merge/close wave: open PRs dropped from 183 to 108 (-75 PRs). Milestone progress: M3 65% (246/377, +18 closed), M4 60% (109/183, +5 closed), M5 68% (136/199, +10 closed), M7 43% (152/350, +14 closed), M8 46% (418/917, +59 closed), M9 28% (131/467, +13 closed). PR #3774 (Click 8.2+ compatibility fix) opened and pending CI resolution. Session tracker: #3775. Priority issue #3776 created for PR #3774 CI failures.
- **Day 98 session 4 launch — massive merge wave (Day 98, 2026-04-08)**: Session 4 launched (issue #4799) with 32 parallel workers and full supervisor fleet targeting v3.2.0v3.7.0 completion. Open PRs dropped from 108 to 1 (massive merge wave between Day 96 and Day 98). Milestone progress since Day 96: M3 73% (235/320, +8%), M4 67% (108/161, +7%), M5 71% (130/183, +3%), M7 48% (150/312, +5%), M8 47% (403/855, +1%). M6 (v3.5.0) scope expanded massively from 327 to 638 total issues (+311 new issues added by agents), dropping apparent completion from 55% to 29% (188/638). UAT tester discovered spec compliance bug: `agents resource show` missing 5 required panels (#4798). Spec-updater proposed restructuring monolithic docs/specification.md (46,739 lines) into docs/specification/ directory — issue #4807 filed with `needs feedback` label. PR #4805 opened: docs: add Milestone Plan section to specification.
- **Day 101 merges — docs, CLI fixes, testing improvements (Day 101, 2026-04-12)**: Several PRs merged since Day 100. Key merges: docs(timeline) Day 100 schedule adherence update (PR #6893, merged 2026-04-11), automation-tracking-manager centralization and tracking system docs expansion (PR #5289, merged 2026-04-11), actor context management showcase with remove/export/import (PR #4220, merged 2026-04-11), fix(cli) add deleted_at field to project delete JSON/YAML output (PR #6639, v3.5.0), fix(cli) display full ULIDs in plan tree output for CLI usability (PR #6571), fix(testing) add guard logic to Robot tdd_expected_fail listener to prevent flaky CI (PR #5659). Open PRs grew from 225 to 251 (+26 new agent PRs). Open bugs surged from ~25 to ~206 (UAT bug-hunt wave active).
### What Remains To Be Done
@@ -5316,3 +5316,91 @@ Story points per developer per milestone.
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
### 2026-04-12 (Day 101)
**Summary**
Status: Behind 25+d
Deadline risk: CRITICAL
**Notes**
- Day 101 update (2026-04-12). Session 4 active (issue #4799, 32 parallel workers, full supervisor fleet). Open PRs: 225→251 (+26 new PRs opened by agents). Open bugs (Type/Bug label): ~206 (surged from ~25 — UAT bug-hunt wave ongoing).
- Continued scope expansion across all milestones since Day 100: M3 grew from 770→926 (+156 new issues), M4 grew from 220→230 (+10), M5 grew from 313→341 (+28), M6 grew from 1085→1178 (+93), M7 grew from 400→432 (+32), M8 grew from 944→953 (+9), M9 grew from 475→489 (+14).
- Milestone completions (Day 101): M3 28% (258/926, was 32% at Day 100 — scope explosion), M4 47% (108/230, was 49%), M5 40% (137/341, was 43%), M6 17% (201/1178, was 18%), M7 35% (152/432, was 38%), M8 45% (427/953, was 45%), M9 27% (132/489, was 28%).
- Recent merges since Day 100: docs(timeline) Day 100 update (PR #6893), automation-tracking-manager centralization docs (PR #5289), actor context management showcase (PR #4220), fix(cli) project delete deleted_at field (PR #6639), fix(cli) plan tree full ULIDs (PR #6571), fix(testing) Robot tdd_expected_fail guard logic (PR #5659).
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development. Agent-driven issue creation continues at high velocity across all milestones. Bug count surge from ~25 to ~206 indicates active UAT testing wave.
#### Milestone forecast
| Milestone | Target -> ETA | Delta | Risk |
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-07-01 | +126d | CRITICAL — 668 open issues; 28% complete (scope expanded 770→926) |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-25 | +84d | CRITICAL — 122 open issues; 47% complete |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-06-01 | +87d | HIGH — 204 open issues; 40% complete |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-08-15 | +158d | CRITICAL — 977 open issues; 17% complete (scope expanded 1085→1178) |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-30 | +94d | HIGH — 280 open issues; 35% complete |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-20 | N/A | HIGH — 526 open issues; 45% complete |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-01 | N/A | MEDIUM — 357 open issues; 27% complete |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-06-01 | HIGH | 204 open issues in v3.4.0; scope expanded +28 issues since Day 100 |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-25 | CRITICAL | 122 open issues in v3.3.0; scope expanded +10 issues since Day 100 |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-07-01 | CRITICAL | 668 open issues in v3.2.0; scope expanded +156 issues since Day 100 |
| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | ~206 Type/Bug open bugs (UAT bug-hunt wave surging); 251 open PRs need merge |
| Track T (Testing) | Active | Ongoing | HIGH | 251 open PRs need review; UAT bugs surging; Session 4 active |
#### Developer forecast
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|------|-------------------|--------------|------|-------|
| Jeff | -26d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight |
| Luis | -26d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool |
| Hamza | -26d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews |
| Aditya | -26d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing |
| Brent | -26d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; ~206 open bugs triage |
| Rui | -26d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
| Mike/Brian | N/A | standby | LOW | Infrastructure support |
#### Task inventory
Milestone per developer as of Day 101 (2026-04-12).
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 668 open | 258/926 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 122 open | 108/230 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 204 open | 137/341 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 977 open | 201/1178 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 280 open | 152/432 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 526 open | 427/953 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 357 open | 132/489 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~3134 open** | **1567/4707 closed** |
#### Story point allocation
Story points per developer per milestone.
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~172 SP |
| M2 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~208 SP |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~104 SP |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~126 SP |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~129 SP |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~100 SP |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |